Question

In: Finance

Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production....

Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4.3 million investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $1.025 million and that variable costs should be $190 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a salvage value of $400,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $290 per ton. The engineering department estimates you will need an initial net working capital investment of $410,000. You require a return of 13 percent and face a tax rate of 22 percent on this project.
a-1. What is the estimated OCF for this project? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)
a-2. What is the estimated NPV for this project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)
b. Suppose you believe that the accounting department’s initial cost and salvage value projections are accurate only to within ±15 percent; the marketing department’s price estimate is accurate only to within ±10 percent; and the engineering department’s net working capital estimate is accurate only to within ±5 percent. What is your worst-case and best-case scenario for this project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)

Solutions

Expert Solution

All financials below are in $

a - 1

OCF = NOPAT + Depreciation

Depreciation = 4,300,000 / 5 =  860,000

NOPAT = [(Sale price - variable cost) x Nos.of units - fixed costs - depreciation] x (1 - tax rate) = [(290 - 190) x 30,000 - 1,025,000 - 860,000] x (1 - 22%) = 869,700

Hence, OCF given by C = 869,700 + 860,000 = $ 1,729,700

a - 2

Initial investment, C0 = Purchase cost + initial working capital = 4,300,000 + 410,000 = 4,710,000

Terminal cash flows, CT = Post tax salvage value + release of working capital = 400,000 x (1 - 22%) + 410,000 =  722,000

Number of years, N = 5 years, Discount rate = R = 13%

Hence, NPV = - C0 + C / R x [1 - (1 + R)-N] + CT x (1 + R)-N = - 4,710,000 + 4,069,700 / 13% x [1 - (1 + 13%)-5] + 722,000 x (1 + 13%)-5 =   1,765,627.59

a - 3

Best case

Initial investment, C0 = Purchase cost + initial working capital = 4,300,000 x (1 - 15%) + 410,000 x (1 - 5%) = 4,044,500

Terminal cash flows, CT = Post tax salvage value + release of working capital = 400,000 x (1 + 15%) x (1 - 22%) + 410,000 x (1 - 5%) =   748,300

OCF = NOPAT + Depreciation

Depreciation = 4,300,000 x (1 - 15%) / 5 = 731,000

NOPAT = [(Sale price - variable cost) x Nos.of units - fixed costs - depreciation] x (1 - tax rate) = [(290 x (1 + 10%) - 190) x 30,000 - 1,025,000 - 731,000] x (1 - 22%) = 1,648,920

Hence, OCF given by C = 1,648,920 + 731,000 = 2,379,920

Hence, Best case NPV = - 4,044,500 + 2,379,920 / 13% x [1 - (1 + 13%)-5] + 748,300 x (1 + 13%)-5 = 4,732,376.28

Worst case scenario:

Initial investment, C0 = Purchase cost + initial working capital = 4,300,000 x (1 + 15%) + 410,000 x (1 + 5%) =   5,375,500

Terminal cash flows, CT = Post tax salvage value + release of working capital = 400,000 x (1 - 15%) x (1 - 22%) + 410,000 x (1 + 5%) =   695,700

OCF = NOPAT + Depreciation

Depreciation = 4,300,000 x (1 + 15%) / 5 = 989,000

NOPAT = [(Sale price - variable cost) x Nos.of units - fixed costs - depreciation] x (1 - tax rate) = [(290 x (1 - 10%) - 190) x 30,000 - 1,025,000 - 989,000] x (1 - 22%) = 90,480

Hence, OCF given by C = 90,480 + 989,000 = 1,079,480

Hence, Worst case NPV = - 5,375,500 + 1,079,480  / 13% x [1 - (1 + 13%)-5] + 695,700 x (1 + 13%)-5 = - 1,201,121.11


Related Solutions

Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $3,800,000 investment in threading equipment to get the project started; the project will last for four years. The accounting department estimates that annual fixed costs will be $600,000 and that variable costs should be $340 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the four-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4.3 million investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $1.025 million and that variable costs should be $190 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a...
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production.
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $4,800,000 investment in threading equipment to get the project started; the project will last for 3 years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $220 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 3-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,700,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,125,000 and that variable costs should be $210 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. The marketing department estimates that the...
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,200,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $800,000 and that variable costs should be $350 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production. You will need an initial $3,400,000 investment in threading equipment to get the project started; the project will last for four years. The accounting department estimates that annual fixed costs will be $800,000 and that variable costs should be $180 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the four-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production. You will need an initial $2,800,000 investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $750,000 and that variable costs should be $260 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $6,000,000 investment in threading equipment to get the project started; the project will last for six years. The accounting department estimates that annual fixed costs will be $700,000 and that variable costs should be $200 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the six-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,800,000 investment in threading equipment to get the project started; the project will last for six years. The accounting department estimates that annual fixed costs will be $700,000 and that variable costs should be $200 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the six-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production. You will need an initial $3,400,000 investment in threading equipment to get the project started; the project will last for four years. The accounting department estimates that annual fixed costs will be $800,000 and that variable costs should be $180 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the four-year project life. It also estimates a salvage value...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT