Question

In: Finance

Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....

Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,800,000 investment in threading equipment to get the project started; the project will last for six years. The accounting department estimates that annual fixed costs will be $700,000 and that variable costs should be $200 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the six-year project life. It also estimates a salvage value of $680,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $300 per ton. The engineering department estimates you will need an initial net working capital investment of $580,000. You require a 18 percent return and face a marginal tax rate of 30 percent on this project.

  

a-1

What is the estimated OCF for this project?

  

  OCF $   

  

a-2

What is the estimated NPV for this project? (Round your answer to 2 decimal places. (e.g., 32.16))

  

  NPV $   
b.

Suppose you believe that the accounting department’s initial cost and salvage value projections are accurate only to within ±15 percent; the marketing department’s price estimate is accurate only to within ±10 percent; and the engineering department’s net working capital estimate is accurate only to within ±5 percent. What is your worst-case and best-case scenario for this project? (Negative amounts should be indicated by a minus sign. Round your answers to 2 decimal places. (e.g., 32.16))

  

  Worst-case $   
  Best-case $   

Solutions

Expert Solution

a-1. OCF = NI + depreciation

= [Qty*(selling price - variable cost) - fixed cost]*(1-tax%) + depreciationperYear*(tax%) ...(1)

= [40,000*(300-200) - 700,000]*(1-30%) + 5,800,000/6*(30%)

= $ 2,600,000

a-2. NPV

= - Initial Investment - Initial Working Capital + PV(OCF)yr1_to_yr6 + PV(FreedUpWorkingCapitalyr6) + PV[SalvageValue (1-tax%)]yr6 ...(2)

= -5,800,000 - 580,000 + [2.6M/1.18 + 2.6M/1.182 +2.6M/1.183 +2.6M/1.184 +2.6M/1.185 +2.6M/1.186] + [580,000 + 680,000*(1-30%)]/1.186

=  -5,800,000 - 580,000 + 9,093,766.656 + [580,000 + 680,000*(1-30%)]/1.186

= 3,104,942.361 =$ 3,104,942.36 (rounded)

{Note: we can calculate following in financial calculator:

[2.6M/1.18 + 2.6M/1.182 +2.6M/1.183 +2.6M/1.184 +2.6M/1.185 +2.6M/1.186]

PMT=2,600,000, N=6, I/Y=18, Compute (CPT) PV and we get PV=-9,093,766.656}

b. worst case

we will get worst case when we have high initial cost (+15%), high working capital (+5%), price estimate is low (-10%), salvage value is low (-15%),

Using (1) & making adjustments for worst case values, our OCFworst

= [40,000* (300*0.9 - 200) - 700,000]*(1-30%) + 5,800,000(1.15)/6*(30%)

= $1,803,500

Using (2) & making adjustments for worst case values, our NPVworst

= -5,800,000*1.15 - 580,000*1.05 + [1,803,500/1.18 + 1,803,500/1.182 +1,803,500/1.183 +1,803,500/1.184 +1,803,500/1.185 +1,803,500/1.186] + [580,000*1.05 + 680,000*(1-15%)(1-30%)]/1.186

= -5,800,000*1.15 - 580,000*1.05 + 6,307,926.217 + [580,000*1.05 + 680,000*(1-15%)(1-30%)]/1.186

= -595,604.3749 = $ -595604.37 (rounded)

b. best case

we will get worst case when we have low initial cost (-15%), low working capital (-5%), price estimate is high (+10%), salvage value is high (+15%),

Using (1) & making adjustments for best case values, our OCFbest

= [40,000* (300*1.1 - 200) - 700,000]*(1-30%) + 5,800,000(0.85)/6*(30%) = 3,396,500

Using (2) & making adjustments for best case values, our NPVbest

= -5,800,000*0.85 - 580,000*0.95 + [3,396,500/1.18 + 3,396,500/1.182 +3,396,500/1.183 +3,396,500/1.184 +3,396,500/1.185 +3,396,500/1.186] + [580,000*0.95 + 680,000*(1.15)(1-30%)]/1.186

= -5,800,000*0.85 - 580,000*0.95 + 11,879,607.1 + [580,000*0.95 + 680,000*(1.15)(1-30%)]/1.186

= 6,805,489.103 = $ 6,805,489.10 (rounded)


Related Solutions

Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production.
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $4,800,000 investment in threading equipment to get the project started; the project will last for 3 years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $220 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 3-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,200,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $800,000 and that variable costs should be $350 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $6,000,000 investment in threading equipment to get the project started; the project will last for six years. The accounting department estimates that annual fixed costs will be $700,000 and that variable costs should be $200 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the six-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,800,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $700,000 and that variable costs should be $210 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,600,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $600,000 and that variable costs should be $250 per ton. Further, the accounting department will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life and estimate a...
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,700,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,125,000 and that variable costs should be $210 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. The marketing department estimates that the...
Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production. You will need an initial $3,400,000 investment in threading equipment to get the project started; the project will last for four years. The accounting department estimates that annual fixed costs will be $800,000 and that variable costs should be $180 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the four-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production. You will need an initial $2,800,000 investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $750,000 and that variable costs should be $260 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production. You will need an initial $3,400,000 investment in threading equipment to get the project started; the project will last for four years. The accounting department estimates that annual fixed costs will be $800,000 and that variable costs should be $180 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the four-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $4,900,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,175,000 and that variable costs should be $220 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT