In: Accounting
Sticky Wickets manufactures Cricket Bats. In May 2010 the
budgeted sales and production were 19,000 bats and the standard
cost card is as follows:
Std
Cost
Std Cost
Material (2kgs @
$5/kg)
10
Labour (3 hrs at
$12/hr)
36
Overheads (3 hrs @
$1/hr)
3
Marginal
Cost
49
Selling
Price
68
Contribution
19
Total fixed costs in the period were budgeted at $100,000 and were
absorbed on the basis of labour hours worked.
In May 2010 the following results were achieved.
40,000kg of wood were bought at a cost of $196,000, this produced 19,200 cricket bats. No inventory of raw materials is held. The labour was paid for 62,000 hours and the total cost was $694,000. Labour worked for 61,500 hours.
Variable overheads in the period were $67,000.
The sales price was reduced to protect the sales levels. However, only 18,000 cricket bats were sold at an average price of $65.
Total fixed costs in May were $107,000.
Required : Calculate the sales, materials, labour, variable overheads, fixed overheads variances and any other appropriate variances in as much detail as possible.
Sales Price Variance = (Std Price - Actual Price)*Actual units sold
= ($68 - $65)*18,000 = $54,000 Adverse
Sales volume contribution margin = (Budgeted Sales volume - Actual Sales Volume)*Contribution per unit
= (19,000 - 18,000)*$19 = $19,000 Adverse
Materials Price Variance = (Actual Qty*Std Price) - Actual Material Cost
= (40,000 kgs*$5 per kg) - $196,000
= $200,000 - $196,000 = $4,000 Favorable
Materials Usage Variance = (Std Qty - Actual Qty)*Std Price
= [(19,200*2kg) - 40,000]*$5 per kg
= (38,400 - 40,000)*$5 = $8,000 Adverse
Labor Rate Variance = (Actual Hours*Std rate) - Actual Material Cost
= (62,000 hrs*$12 per hr) - $694,000
= $744,000 - $694,000 = $50,000 Favorable
Labor Efficiency Variance = (Std hrs - Actual hrs worked)*Std Rate
= [(19,200*3 hrs) - 61,500 hrs)*$12 per hr
= (57,600 hrs - 61,500 hrs)*$12 = $46,800 Adverse
Labor Idle Variance = (62,000 hrs - 61,500 hrs)*Std Rate
= 500*$12 = $6,000 Adverse
Variable Overhead rate Variance = (Actual Hours*Std rate) - Actual OH Cost
= (62,000 hrs*$1 per hr) - $67,000 = $2,000 Adverse
Variable OH Efficiency Variance = (Std Hrs - Actual Hrs)*Std Rate
= [(19,200*3 hrs) - 62,000]$1
= (57,600 - 62,000)*$1 = $4,400 Adverse
Budgeted fixed OH = $100,000
Budgeted Labor Hours = 19,000 units*3 hrs = 57,000 hrs
Budgeted Rate per hour = $100,000/57,000 hrs
Absorbed Fixed OH = ($100,000/57,000)*62,000 hrs = $108,772
Fixed Overhead Variance = Absorbed Fixed OH - Actual Fixed OH
= $108,772 - $107,000 = $1,772 Favorable