In: Statistics and Probability
Given the following data, construct a three-sigma range control chart.
Day of Sample | Sample Values |
Saturday | 22,19,20 |
Sunday | 21,20,17 |
Monday | 16,17,18 |
Tuesday | 20,16,21 |
Wednesday | 23,20,20 |
Thursday | 19,16,21 |
a. If Friday's results are 15,14,21 is the process in control?
b.Construct a three-sigma means control chart and determine if the process is still in control on Friday.
Result:
Given the following data, construct a three-sigma range control chart.
Day of Sample |
Sample Values |
Saturday |
22,19,20 |
Sunday |
21,20,17 |
Monday |
16,17,18 |
Tuesday |
20,16,21 |
Wednesday |
23,20,20 |
Thursday |
19,16,21 |
a. If Friday's results are 15,14,21 is the process in control?
Quality Control Process Charts |
|||||
Sample size |
3 |
||||
Number of samples |
6 |
||||
Mean |
Range |
||||
Upper Control Limit, UCL |
22.97 |
9.44 |
|||
Center |
19.22 |
3.67 |
|||
Lower Control Limit, LCL |
15.47 |
0.00 |
Range for Friday is 21-14=7 is within the control limits. Process is in control
b.Construct a three-sigma means control chart and determine if the process is still in control on Friday.
Mean for Friday is 16.67 is within the control limits. Process is in control