Question

In: Accounting

Woodland Industries manufactures and sells custom-made windows. Its job costing system was designed using an activity-based...

Woodland Industries manufactures and sells custom-made windows. Its job costing system was designed using an activity-based costing approach. Direct materials and direct labor costs are accumulated separately, along with information concerning three manufacturing overhead cost drivers (activities). Assume that the direct labor rate is $14 per hour and that there were no beginning inventories. The following information was available for 2016, based on an expected production level of 45,700 units for the year, which will require 219,000 direct labor hours:

Activity Cost Driver Budgeted Costs for 2016 Cost Driver Used as Allocation Base Cost Allocation Rate
Materials handling $ 48,180 Number of parts used $ 0.22 per part
Cutting and lathe work 2,163,720 Number of parts used 9.88 per part
Assembly and inspection 4,511,400 Direct labor hours 20.60 per hour

The following production, costs, and activities occurred during the month of July:

Units Produced Direct Materials Costs Number of Parts Used Direct Labor Hours
3,380 $101,500 2,677 13,500

PART A IS CORRECT

Required:

a. Calculate the total manufacturing costs and the cost per unit of the windows produced during the month of July (using the activity-based costing approach). (Round "Cost per unit produced" to 2 decimal places.)

Total manufacturing cost $406,638
Cost per unit produced $120.31

NEED HELP WITH PART B

b. Assume instead that Woodland Industries applies manufacturing overhead on a direct labor hours basis (rather than using the activity-based costing system previously described). Calculate the total manufacturing cost and the cost per unit of the windows produced during the month of July. (Hint: You will need to calculate the predetermined overhead application rate using the total budgeted overhead costs for 2016.) (Round "Cost per unit produced" to 2 decimal places.)

Total manufacturing cost
Cost per unit produced

Solutions

Expert Solution

Activity Cost Driver Budgeted Costs Cost Driver Used as Allocation Base Cost Allocation Rate
Materials handling 48,180 Number of parts used 0.22 per part
Cutting and lathe work 21,63,720 Number of parts used 9.88 per part
Assembly and inspection 45,11,400 Direct labor hours 20.6 per hour
A Calculation of Total Manufacturing Costs: Based ABC
Direct Material 1,01,500
Overhead Cost:
Materials handling 589 (0.22*2677)
Cutting and lathe work 26,449 (9.88*2677)
Assembly and inspection 2,78,100 (20.60*13500)
Total Cost 4,06,638
Units 3380
Cost Per Unit 120.31
B Activity Cost Driver Budgeted Costs
Materials handling 48,180
Cutting and lathe work 21,63,720
Assembly and inspection 45,11,400
Total Cost 67,23,300
DLH 2,19,000
Cost Per DLH 30.70
Calculation of Total Manufacturing Costs: Blanket Rate
Direct Material 1,01,500
Overhead Cost (13500*30.70) 4,14,450
Total Cost 5,15,950
Units 3380
Cost Per Unit 152.65

Related Solutions

Woodland Industries manufactures and sells custom-made windows. Its job costing system was designed using an activity-based...
Woodland Industries manufactures and sells custom-made windows. Its job costing system was designed using an activity-based costing approach. Direct materials and direct labor costs are accumulated separately, along with information concerning three manufacturing overhead cost drivers (activities). Assume that the direct labor rate is $19 per hour and that there were no beginning inventories. The following information was available for 2016, based on an expected production level of 53,800 units for the year, which will require 215,000 direct labor hours:...
Clear View is a manufacturer of custom windows and uses a job-costing system at its Orlando,...
Clear View is a manufacturer of custom windows and uses a job-costing system at its Orlando, FL plant. The plant has a machining department and a finishing department. Clear View uses normal costing with two direct-cost categories (direct materials and direct manufacturing labor) and two manufacturing overhead cost pools (the machining department with machine-hours as the allocation base and the finishing department with direct manufacturing labor costs as the allocation base). The 2014 budget for the plant is as follows:...
Chris has a custom curtain and chair cover shop. The job-costing system was designed using an...
Chris has a custom curtain and chair cover shop. The job-costing system was designed using an activity-based approach. There are two direct-cost categories (direct materials and direct labor) and three indirect cost pools. These three cost pools represent three activity areas of work at the shop. Activity Area Cost Driver Used for Allocation Cost-Allocation Rate Materials handling Number of pieces in the pattern $2.00 per piece Stitching Number of pieces in the pattern $25.00 per piece Assambly/Installation Direct labor hours...
Chris has a custom curtain and chair cover shop. The job-costing system was designed using an...
Chris has a custom curtain and chair cover shop. The job-costing system was designed using an activity-based approach. There are two direct-cost categories (direct materials and direct labor) and three indirect cost pools. These three cost pools represent three activity areas of work at the shop. Activity Area Cost Driver Used for Allocation Cost-Allocation Rate Materials handling Number of pieces in the pattern $2.00 per piece Stitching Number of pieces in the pattern $25.00 per piece Assembly/Installation Direct labor hours...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $101,200 Number of moves 4,000 Engineering 142,400 Number of change orders 8,000 Other overhead 358,800 Direct labor hours 52,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $54,250 Number of moves 2,500 Engineering 120,700 Number of change orders 8,500 Other overhead 148,500 Direct labor hours 45,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $108,000 Number of moves 4,500 Engineering 165,000 Number of change orders 10,000 Other overhead 263,200 Direct labor hours 47,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Based on activity based costing article, briefly summarise how the costing system was designed and implemented...
Based on activity based costing article, briefly summarise how the costing system was designed and implemented in your real-life organisation?
Activity-Based Costing Zeus Industries manufactures two types of electrical power units, custom and standard, which involve...
Activity-Based Costing Zeus Industries manufactures two types of electrical power units, custom and standard, which involve four factory overhead activities—production setup, procurement, quality control, and materials management. An activity analysis of the overhead revealed the following estimated activity costs and activity bases for these activities: Activity Activity Cost Activity Base Production setup $ 60,750 Number of setups Procurement 136,500 Number of purchase orders (PO) Quality control 182,000 Number of inspections Materials management 180,000 Number of components Total $559,250 The activity-base...
Activity-Based Costing Zeus Industries manufactures two types of electrical power units, custom and standard, which involve...
Activity-Based Costing Zeus Industries manufactures two types of electrical power units, custom and standard, which involve four factory overhead activities—production setup, procurement, quality control, and materials management. An activity analysis of the overhead revealed the following estimated activity costs and activity bases for these activities: Activity Activity Cost Activity Base Production setup $ 56,250 Number of setups Procurement 147,000 Number of purchase orders (PO) Quality control 168,000 Number of inspections Materials management 82,000 Number of components Total $453,250 The activity-base...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT