Question

In: Accounting

HalimSdnBhd uses a standard costing system. The standard cost card for one product is shown below:...

HalimSdnBhd uses a standard costing system. The standard cost card for one product is shown below:

Direct Material 4 kg at RM5 per kg                      RM 20

Direct Labor 2 hours at RM8 per hour 16

Variable Overhead 2 hours at RM 7.5 per hour15

Total Product Cost 51

The budgeted output and sales was 1,000 units. Actual output for the period was 1,300 units . Actual cost was as follows:

Direct Material:                       5,000 kg, costing 22,750

Direct Labor:                      2,860 hours, costing 21,450

Required:

Compute the following variances, indicating whether each variance is favorable or unfavorable.

Total of direct- material variances.

Direct-material price variance.

Direct-material usage variance.

Total of direct-labor variances.

Direct-labor rate variance.

Direct-labor efficiency variance.

Solutions

Expert Solution

1.

Actual price of direct material = Total cost of material/total quantity

          = $ 22,750/5,000 = $ 4.55 per kg

Direct material price variance = (Actual price – Standard price) x Actual quantity

                                          = ($ 4.55 - $ 5) x 5,000 = $ 0.45 x 5,000 = - $ 2,250        F

2.             

Standard quantity of direct material for actual production

= Standard material quantity needed per unit x actual unit of production

= 4 kgs x 1,300 = 5,200 kgs

Direct material usages variance = (Actual quantity - Standard quantity) x Standard price

                                             = (5,000 – 5,200) x $ 5

                                            = - 200 x $ 5 = - $ 1,000      F

3.

Actual direct labor rate = total direct labor cost/No. of hours worked

                                          = $ 21,450/2,860 = 7.50 per hour

Labor rate Variance = (Actual rate - Standard rate) × Actual hour

                                     = ($ 7.50 - $ 8) x 2,860

                                     = - $ 0.50 x 2,860 = - $ 1,430       F

4.

Standard hours of direct labor for actual production

= Standard hours needed per unit x actual unit of production

= 2 hours x 1,300 = 2,600 hours

Labor efficiency Variance = (Actual hours - Standard hours) x Standard rate

                                    = (2,860 – 2,600) x $ 8

                = 260 x $ 8 = $ 2,080      U


Related Solutions

Owen limited uses a standard costing system. The standard cost card for one product is shown...
Owen limited uses a standard costing system. The standard cost card for one product is shown below. Direct material                  4kg @$5 per kg                                 20 Direct labour                      2 hour @ $8 per hour                     16 Variable overhead           2 hours @ $3.5 per hour               7 Total variable cost                                                                            43 Fixed overhead                 2 hours @ $7 per hour                   14 Total production cost                                                                     57 Standard selling price                                                                     70 Standard profit margin                                                                   13 The budgeted output and sales was 1000 units. Actual production and...
Wallis Company manufactures only one product and uses a standard cost system. The company uses a...
Wallis Company manufactures only one product and uses a standard cost system. The company uses a predetermined plantwide overhead rate that relies on direct labor-hours as the allocation base. All of the company's manufacturing overhead costs are fixed—it does not incur any variable manufacturing overhead costs. The predetermined overhead rate is based on a cost formula that estimated $2,892,000 of fixed manufacturing overhead for an estimated allocation base of 289,200 direct labor-hours. Wallis does not maintain any beginning or ending...
Phoenix Company manufactures only one product and uses a standard cost system. The company uses a...
Phoenix Company manufactures only one product and uses a standard cost system. The company uses a plantwide predetermined overhead rate that relies on direct labor-hours as the allocation base. The predetermined overhead rate is based on a cost formula that estimated $2,887,200 of fixed and variable manufacturing overhead for an estimated allocation base of 240,600 direct labor-hours. Phoenix does not maintain any beginning or ending work in process inventory. The company’s beginning balance sheet is as follows: Phoenix Company Balance...
Wallis Company manufactures only one product and uses a standard cost system. The company uses a...
Wallis Company manufactures only one product and uses a standard cost system. The company uses a predetermined plantwide overhead rate that relies on direct labor-hours as the allocation base. All of the company's manufacturing overhead costs are fixed—it does not incur any variable manufacturing overhead costs. The predetermined overhead rate is based on a cost formula that estimated $2,886,000 of fixed manufacturing overhead for an estimated allocation base of 288,600 direct labor-hours. Wallis does not maintain any beginning or ending...
The standard cost card for a product indicates that one unit of the product requires 8...
The standard cost card for a product indicates that one unit of the product requires 8 kilograms of a raw material at $0.80 per kilogram. The production of the product in April was 870 units, but production had been budgeted for 850 units. During April, 7,150 kilograms of the raw material were purchased for $5,577. All the kilograms of the raw material purchased were used in production. What was the materials quantity variance? $152 F $152 U $280 F $280...
Friar Inc produces one product and the company uses a standard cost system and determines that...
Friar Inc produces one product and the company uses a standard cost system and determines that it should take one hour of direct labor to produce one unit. The normal production capacity is 150,000 units per year. The total budgeted overhead at normal capacity is 450,000 dollars comprised of 195,000 of variable costs and 255,000 of fixed costs. Overhead is applied on the basis of direct labor hours. During the current year, the company produced 156,000 units worked 160,000 direct...
Regency Corp. uses a standard cost system to account for the costs of its one product....
Regency Corp. uses a standard cost system to account for the costs of its one product. Fixed overhead is applied to production at a rate of $27.10 per unit, based on budgeted production is 2,445 per month. During November, Regency produced 2,295 units. Fixed overhead incurred totaled $70,420. a. Calculate the fixed overhead spending variance. b. Calculate the fixed overhead volume variance.
Edney Company employs a standard cost system for product costing. The per-unit standard cost of its...
Edney Company employs a standard cost system for product costing. The per-unit standard cost of its product is: Raw materials $ 14.50 Direct labor (2 direct labor hours × $8.00 per hour) 16.00 Manufacturing overhead (2 direct labor hours × $11.00 per hour) 22.00 Total standard cost per unit $ 52.50 The manufacturing overhead rate is based on a normal capacity level of 600,000 direct labor hours. (Normal capacity is defined as the level of capacity needed to satisfy average...
Edney Company employs a standard cost system for product costing. The per-unit standard cost of its...
Edney Company employs a standard cost system for product costing. The per-unit standard cost of its product is: Raw materials $ 14.00 Direct labor (2 direct labor hours × $8.00 per hour) 16.00 Manufacturing overhead (2 direct labor hours × $10.00 per hour) 20.00 Total standard cost per unit $ 50.00 The manufacturing overhead rate is based on a normal capacity level of 600,000 direct labor hours. (Normal capacity is defined as the level of capacity needed to satisfy average...
Edney Company employs a standard cost system for product costing. The per-unit standard cost of its...
Edney Company employs a standard cost system for product costing. The per-unit standard cost of its product is: Raw materials $ 14.00 Direct labor (2 direct labor hours × $8.00 per hour) 16.00 Manufacturing overhead (2 direct labor hours × $10.00 per hour) 20.00 Total standard cost per unit $ 50.00 The manufacturing overhead rate is based on a normal capacity level of 600,000 direct labor hours. (Normal capacity is defined as the level of capacity needed to satisfy average...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT