Question

In: Finance

5. You are considering two independent projects. The required return for both projects is 13 percent....

5. You are considering two independent projects. The required return for both projects is 13 percent. Project A has an initial cost of $145,000 and cash inflows of $62,000, $53,000, and $70,000 for Years 1 to 3, respectively. Project B has an initial cost of $95,000 and cash inflows of $40,000, $44,000, and $35,000 for Years 1 to 3, respectively. Given this information, which one of the following statements is correct based on the NPV and IRR methods of analysis?
      
AYou should accept both projects.      
BYou should accept Project A and reject Project B      
CYou should accept Project B and reject Project A.      
DNPV indicates accept Project A while IRR indicates accepting Project B.      
EYou should reject both projects.

Solutions

Expert Solution

Project A
Discount rate 13.000%
Year 0 1 2 3
Cash flow stream -145000 62000 53000 70000
Discounting factor 1.000 1.130 1.277 1.443
Discounted cash flows project -145000.000 54867.257 41506.774 48513.511
NPV = Sum of discounted cash flows
NPV Project A = -112.46
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project A
IRR is the rate at which NPV =0
IRR 12.96%
Year 0 1 2 3
Cash flow stream -145000.000 62000.000 53000.000 70000.000
Discounting factor 1.000 1.130 1.276 1.441
Discounted cash flows project -145000.000 54889.022 41539.711 48571.268
NPV = Sum of discounted cash flows
NPV Project A = 0.000
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project B
Discount rate 13.000%
Year 0 1 2 3
Cash flow stream -95000 40000 44000 35000
Discounting factor 1.000 1.130 1.277 1.443
Discounted cash flows project -95000.000 35398.230 34458.454 24256.756
NPV = Sum of discounted cash flows
NPV Project B = -886.56
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project B
IRR is the rate at which NPV =0
IRR 12.44%
Year 0 1 2 3
Cash flow stream -95000.000 40000.000 44000.000 35000.000
Discounting factor 1.000 1.124 1.264 1.422
Discounted cash flows project -95000.000 35574.913 34803.297 24621.790
NPV = Sum of discounted cash flows
NPV Project B = 0.000
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

As NPVs are negative and IRR less than discount rate


Related Solutions

You are considering two independent projects that have a required return of 15 percent. Project A...
You are considering two independent projects that have a required return of 15 percent. Project A has an initial cost of $198,700 and cash inflows of $67,200, $109,600, and $88,700 for years 1 to 3 respectively. Project B has an initial cost of $102,000 and cash inflows of $37,600 and $91,200 for years 1 and 2, respectively. Given this information, which one of the following statements is correct based on the NPV and IRR methods of analysis? You should accept...
You are considering two independent projects. The required rate of return is 13.75 percent for Project...
You are considering two independent projects. The required rate of return is 13.75 percent for Project A and 14.25 percent for Project B. Project A has an initial cost of $51,400 and cash inflows of $21,400, $24,900, and $22,200 for Years 1 to 3, respectively. Project B has an initial cost of $38,300 and cash inflows of $23,000 a year for 2 years. Which project(s), if either, should you accept? Accept both A and B Reject both A and B...
You are considering two independent projects with the following cash flows. The required return for both...
You are considering two independent projects with the following cash flows. The required return for both projects is 10%. Given this information, which one of the following is correct? Year Project A Project B 0 -$950,000 -$125,000 1 $330,000    $   55,000 2 $400,000    $   50,000 3 $450,000    $ 50,000 A. You should accept project B since it has the higher IRR and reject project A because you cannot accept both projects. B. You should accept project A because it has...
You are considering two independent projects that have differing requirements. Project A has a required return...
You are considering two independent projects that have differing requirements. Project A has a required return of 12 percent compared to Project B's required return of 13.5 percent. Project A costs $75,000 and has cash flows of $21,000, $49,000, and $12,000 for Years 1 to 3, respectively. Project B has an initial cost of $70,000 and cash flows of $15,000, $18,000, and $41,000 for Years 1 to 3, respectively. Based on the NPV, you should:
Your division is considering two projects. The required rate of return for both projects is 10%....
Your division is considering two projects. The required rate of return for both projects is 10%. Below are the cash flows of both the projects:         Projects Initial investment Year 1 Year 2 Year 3 Year 4 A         -$30 $5 $10 $15 $20 B -$30 $20 $10 $8 $6 Calculate the Payback period and discounted payback period. Why are they different? . Calculate the NPV for both the projects Which projects should be accepted? if both the projects are independent....
A company is considering two mutually exclusive projects, the company’s required return is 8 percent and...
A company is considering two mutually exclusive projects, the company’s required return is 8 percent and they do not have any capital constraints. Based on the profitability index, what is your recommendation concerning these projects?                                                             Project            A                                 Project B                                     Year    Cash Flow                   Year    Cash Flow                                        0       -$38,500                        0       -$42,000                                        1         $20,000                        1         $10,000                                        2         $24,000                        2         $40,000 Neither project is acceptable. You should accept both projects since both of their PIs are greater than 1. You should accept project A since it has the higher PI. You should accept...
You are considering the following two mutually exclusive projects. The required return on each project is...
You are considering the following two mutually exclusive projects. The required return on each project is 14 percent. Which project should you accept and what is the best reason for that decision? Year Project A Project B 0 −$ 24,000 −$ 21,000 1 9,500 6,500 2 16,200 9,800 3 8,700 15,200 Project A; because it pays back faster Project A; because it has the higher profitability index Incorrect Project B; because it has the higher profitability index Project B; because...
ee. You are considering two independent projects with cashflow information below. Both have been assigned a...
ee. You are considering two independent projects with cashflow information below. Both have been assigned a discount rate of 8%. Based on the profitability index, what is your recommendation concerning these projects? Year Project A Project B 0 -$39,500 -$42,000 1 20,000 10,000 2 24,000 35,000 A You should accept both projects since both of their PIs are positive B You should accept both projects since both of their PIs are greater than 1 C You should only accept project...
Bausch Company is presented with the following two mutually exclusive projects. The required return for both...
Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 15 percent. Year Project M Project N 0 –$140,000      –$359,000      1 61,500      159,300      2 73,400      168,400      3 68,100      154,800      4 40,500      110,400      a. What is the IRR for each project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV for each project? (Do not round intermediate calculations...
You are considering an investment in two projects, A and B. Both projects will cost $115,000,...
You are considering an investment in two projects, A and B. Both projects will cost $115,000, and the projected cash flows are as follows: YEAR PROJECT A PROJECT B 1 $7,188    $51,750 2 $21,562    $38,812 3 $40,250    $28,750 4 $50,315    $21,563 5    $57,500 $14,375 Using Excel and show formulas a. Assuming that the WACC is 9.4%, calculate the payback period, discounted payback period, NPV, PI, IRR, and MIRR. If the projects are mutually exclusive, which...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT