Question

In: Finance

You are considering two independent projects that have differing requirements. Project A has a required return...

You are considering two independent projects that have differing requirements. Project A has a required return of 12 percent compared to Project B's required return of 13.5 percent. Project A costs $75,000 and has cash flows of $21,000, $49,000, and $12,000 for Years 1 to 3, respectively. Project B has an initial cost of $70,000 and cash flows of $15,000, $18,000, and $41,000 for Years 1 to 3, respectively. Based on the NPV, you should:

Solutions

Expert Solution

We will calculate the Net Present Value (NPV) of both the projects.

Net Present value (NPV) = Present value of future cash inflows - initial investment

For Project A:

We will calculate the present value of future cash flows by the following formula:

PV = FV / (1 + r%)n

where, FV = Future value, PV = Present value, r = rate of interest = 12%, n= time period

For calculating the present value the given cash flows, we will calculate the present values of all the years and add them up. Now,putting the values in the above equation, we get,

PV = $21000 / (1 + 12%)+ $49000 / (1 + 12%)2 + $12000 / (1 + 12%)3

PV = $21000 / (1 + 0.12)+ $49000 / (1 + 0.12)2 + $12000 / (1 + 0.12)3

PV = $21000 / (1.12)+ $49000 / (1.12)2 + $12000 / (1.12)3

PV = $18750+ ($49000 / 1.2544) + ($12000 / 1.404928)

PV = $18750 + $39062.5 + $8541.36

PV = $66353.86

Now, we will calculate the Net Present Value (NPV) as per below:

Net Present value (NPV) = Present value of future cash inflows - initial investment

Initial investment = $75000, Present value of future cash flows = $66353.86

Putting the values in the above equation, we get,

Net Present value (NPV) = $66353.86 - $75000  

Net Present value (NPV) = - $8646.14

For Project B:

We will calculate the present value of future cash flows by the following formula:

PV = FV / (1 + r%)n

where, FV = Future value, PV = Present value, r = rate of interest = 13.5%, n= time period

For calculating the present value the given cash flows, we will calculate the present values of all the years and add them up. Now,putting the values in the above equation, we get,

PV = $15000 / (1 + 13.5%)+ $18000 / (1 + 13.5%)2 + $41000 / (1 + 13.5%)3

PV = $15000 / (1 + 0.135)+ $18000 / (1 + 0.135)2 + $41000 / (1 + 0.135)3

PV = $15000 / (1.135)+ $18000 / (1.135)2 + $41000 / (1.135)3

PV = $13215.8590+ ($18000 / 1.288225) + ($41000 / 1.462135)

PV = $13215.8590 + $13972.7143 + $28041.1863

PV = $55229.7596

Now, we will calculate the Net Present Value (NPV) as per below:

Net Present value (NPV) = Present value of future cash inflows - initial investment

Initial investment = $70000, Present value of future cash flows = $55229.7596

Putting the values in the above equation, we get,

Net Present value (NPV) = $55229.7596 - $70000

Net Present value (NPV) = - $14770.24

Since the Net Present Value (NPV) of both the projects is negative, so, based on NPV, we should not accept either of the projects.


Related Solutions

You are considering two independent projects that have a required return of 15 percent. Project A...
You are considering two independent projects that have a required return of 15 percent. Project A has an initial cost of $198,700 and cash inflows of $67,200, $109,600, and $88,700 for years 1 to 3 respectively. Project B has an initial cost of $102,000 and cash inflows of $37,600 and $91,200 for years 1 and 2, respectively. Given this information, which one of the following statements is correct based on the NPV and IRR methods of analysis? You should accept...
You are considering two independent projects. The required rate of return is 13.75 percent for Project...
You are considering two independent projects. The required rate of return is 13.75 percent for Project A and 14.25 percent for Project B. Project A has an initial cost of $51,400 and cash inflows of $21,400, $24,900, and $22,200 for Years 1 to 3, respectively. Project B has an initial cost of $38,300 and cash inflows of $23,000 a year for 2 years. Which project(s), if either, should you accept? Accept both A and B Reject both A and B...
5. You are considering two independent projects. The required return for both projects is 13 percent....
5. You are considering two independent projects. The required return for both projects is 13 percent. Project A has an initial cost of $145,000 and cash inflows of $62,000, $53,000, and $70,000 for Years 1 to 3, respectively. Project B has an initial cost of $95,000 and cash inflows of $40,000, $44,000, and $35,000 for Years 1 to 3, respectively. Given this information, which one of the following statements is correct based on the NPV and IRR methods of analysis?...
You are considering two independent projects with the following cash flows. The required return for both...
You are considering two independent projects with the following cash flows. The required return for both projects is 10%. Given this information, which one of the following is correct? Year Project A Project B 0 -$950,000 -$125,000 1 $330,000    $   55,000 2 $400,000    $   50,000 3 $450,000    $ 50,000 A. You should accept project B since it has the higher IRR and reject project A because you cannot accept both projects. B. You should accept project A because it has...
​(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B....
​(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B. The initial cash outlay associated with project A is ​$50,000​ and the initial cash outlay associated with project B is ​$70,000 The required rate of return on both projects is 9 percent. The expected annual free cash inflows from each project are in the popup​ window: Calculate the NPV​, PI​, and IRR for each project and indicate if the project should be accepted.   ...
(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B....
(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B. The initial cash outlay associated with project A is ​$50,000 and the initial cash outlay associated with project B is ​$70,000 The required rate of return on both projects is 12 percent. The expected annual free cash inflows from each project are in the popup​ window: .Calculate the NPV​, PI​, and IRR for each project and indicate if the project should be accepted. a....
Your division is considering two projects. The required rate of return for both projects is 10%....
Your division is considering two projects. The required rate of return for both projects is 10%. Below are the cash flows of both the projects:         Projects Initial investment Year 1 Year 2 Year 3 Year 4 A         -$30 $5 $10 $15 $20 B -$30 $20 $10 $8 $6 Calculate the Payback period and discounted payback period. Why are they different? . Calculate the NPV for both the projects Which projects should be accepted? if both the projects are independent....
eBook Ziege Systems is considering the following independent projects for the coming year: Project Required Investment...
eBook Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 10.75% High B 5 million 13.25 High C 3 million 8.75 Low D 2 million 7.75 Average E 6 million 11.75 High F 5 million 11.75 Average G 6 million 5.75 Low H 3 million 10.50 Low Ziege's WACC is 9.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 13.25% High B 5 million 10.75 High C 3 million 8.75 Low D 2 million 8.00 Average E 6 million 11.75 High F 5 million 11.75 Average G 6 million 6.00 Low H 3 million 10.50 Low Ziege's WACC is 9.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 14.75% High B 5 million 12.25 High C 3 million 10.25 Low D 2 million 9.50 Average E 6 million 13.25 High F 5 million 13.25 Average G 6 million 7.50 Low H 3 million 12.75 Low Ziege's WACC is 10.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT