Question

In: Statistics and Probability

A cost estimator for a construction company has collected the data found in the source file...

A cost estimator for a construction company has collected the data found in the source file Estimation.xlsx describing the total cost (Y) of 97 difference projects and the following 3 independent variables thought to exert relevant influence on the total cost: total units of work required (X1), contracted units of work per day (X2), and city/location of work (X3). The cost estimator would like to develop a regression model to predict the total cost of a project as a function of these 3 independent variables.

b. Suppose the estimator wants to use the total units of work required (X1), contracted units of work per day (X2), and city/location of work (X3) as the independent variables to predict total cost. What should be the regression function between Y and X1, X2, and X3? What is the adjusted R-squared value of this model? What conclusions can you make? (Note that X3 is a dummy variable. You should process it into different categories as I showed you in the class lecture. You should expand X3 into Location1, Location 2, …. Location 5 to differentiate the six locations.)

Solutions

Expert Solution

I have answered the question below

Please up vote for the same and thanks!!!

Do reach out in the comments for any queries

Answer:

To select the model that shows the highest adjusted, perform the following steps:

1. Select the entire data. Go to XL MinerPredictMultiple Linear Regression as shown below:

The following dialogue box will appear. The screenshot is shown below:

2. Update the dialogue box. Move the dependent variable(Y) to the output variable and move all the independent variables to the selected variable column to find the best fitted model as shown below:

3. Click on Next and the following dialog box appears:

4. Click on Variable Selection on the upper right side and the dialog box shown below appears:

Click on the finish and the final result is shown below:

From the above table, it is clear that the selected model would be the one with variables Units of work and City. It is because this model has the highest adjustedwhich is greater than the other two. The combination of (units of work) and (city) has.

6. To calculate the equation for this model, click on Choose Subset as shown below:

After the dialog box appears, click on Next and then Finish and the following results is shown below:

Therefore, the equation is.


Related Solutions

The personnel director for a small manufacturing company has collected the data found in the table...
The personnel director for a small manufacturing company has collected the data found in the table 1 describing the salary (Y) earned by each machinist in the factory along with the average performance rating (X1) over the past 3 years, the years of service (X2), and the number of different machines each employee is certified to operate (X3). The personnel director wants to build a regression model to estimate the average salary an employee should expect to receive based on...
Cost of Quality Analysis The ABC Company has collected the following cost data for the year:  ...
Cost of Quality Analysis The ABC Company has collected the following cost data for the year:             Receiving Inspection $ 15,232 Production Scrap $   32,150 Rejected Products $ 6,200   Product Design $ 25,422 Customer Adjustment Credit $ 85,654 Online Inspection $ 17,248 Quality Team Meeting $ 7,540 Downgrading Products $ 1,125,328 Customer Need survey $ 3,250 Final test $         25,758 Prototyping $ 136,802   Organize these costs in COQ categories and put any non-QOC data in the NQ category. Compute the...
The data on a loan has been collected in the Microsoft ExcelOnline file below. Open...
The data on a loan has been collected in the Microsoft Excel Online file below. Open the spreadsheet and perform the required analysis to answer the questions below.Open spreadsheeta. Complete an amortization schedule for a $35,000 loan to be repaid in equal installments at the end of each of the next three years. The interest rate is 11% compounded annually. Round all answers to the nearest cent.BeginningRepaymentEndingYearBalancePaymentInterestof PrincipalBalance1$  $  $  $  $  2$  $  $  $  $  3$  $  $  $  $  b. What percentage of the payment represents interest and what percentage represents principal...
how to export source data to excel file in python?
how to export source data to excel file in python?
The data on a loan has been collected in the Microsoft Excel Online file below. Open...
The data on a loan has been collected in the Microsoft Excel Online file below. Open the spreadsheet and perform the required analysis to answer the questions below. Amortization schedule Loan amount to be repaid (PV) $39,000.00 Interest rate (r) 11.00% Length of loan (in years) 3 a. Setting up amortization table Formula Calculation of loan payment #N/A Year Beginning Balance Payment Interest 1 2 3 b. Calculating % of Payment Representing Interest and Principal for Each Year Year Payment...
The data on a loan has been collected in the Microsoft Excel Online file below. Open...
The data on a loan has been collected in the Microsoft Excel Online file below. Open the spreadsheet and perform the required analysis to answer the questions below. a. Complete an amortization schedule for a $22,000 loan to be repaid in equal installments at the end of each of the next three years. The interest rate is 8% compounded annually. Round all answers to the nearest cent. Beginning Repayment Ending Year Balance Payment Interest of Principal Balance 1 $   $  ...
Konza Company has collected the following cost and production data from their manufacturing operations over the...
Konza Company has collected the following cost and production data from their manufacturing operations over the past eight months. Period Units Produced Total costs (Sh) 1 2,200 10,500 2 3,100 12,750 3 5,600 18,500 4 1,700 9,250 5 6,300 20,750 6 8,100 25,250 7 5,050 17,625 8 3,000 12,500 (a) Using the high-low method ; i. Estimate the fixed production costs, ii. Estimate the variable production cost per unit, (b) Establish a cost estimating function for the total production costs....
The data in the attached excel file comes from Consumer Reports and was collected over a...
The data in the attached excel file comes from Consumer Reports and was collected over a two-year period. It gives the average mpg over a 195-mile trip, the weight of the vehicle (pounds), engine displacement (liters), number of cylinders, horsepower, type of transmission (0 = manual, 1 = automatic), the number of gears and whether the car was foreign (1) or domestic (0). Part a: Build a model for predicting the average mpg based on the data in the attached...
A group students collected data on the speed of vehicles traveling through a construction zone on...
A group students collected data on the speed of vehicles traveling through a construction zone on a state highway, where the posted speed was 45 mph. The recorded speed (in mph) of 15 randomly selected vehicles is given below. 35 37 40 41 42 44 46 49 52 54 58 61 64 66 67 1. Use Excel Data Analysis to find the mean, median, and mode of the data set. Make sure that you clearly state or point out which...
A group students collected data on the speed of vehicles traveling through a construction zone on...
A group students collected data on the speed of vehicles traveling through a construction zone on a state highway, where the posted speed was 45 mph. The recorded speed (in mph) of 15 randomly selected vehicles is given below. You should be able to copy and paste them into Excel. 35 37 40 41 42 44 46 49 52 54 58 61 64 66 67 - Use Excel Data Analysis to find the mean, median, and mode of the data...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT