Project Name Tea Shop Project Number 034 Project Manager Adelaja Osho Prioritization High Owner(s) Mr. Alade(Property...

Project Name

Tea Shop

Project Number

034

Project Manager

Adelaja Osho

Prioritization

High

Owner(s)

Mr. Alade(Property Owner)

Start Date:

04-29-2018

Scheduled Completion Date:

12-30-2018

Mission/ Purpose

What is your project going to accomplish? How does this project relate to overall goals and objectives of the company? It is part of a program or larger project?

This project will give clients and customers an open mind of how natural products can save money and enrich you to make you feel good about yourself, inside and outside.

This project will also allow the management of a budget when the right products are researched and tested.

SOW

What will this project create? What is the product of the project? At a high level, how do you plan on doing the work of the project? What are the high-level deliverables for this project?

The All natural Tea project proposes to plan, design, construct and implement a structured business.

The vision of the project is to improve greater use of natural products for coffee and tea rather that man made products.

Objectives

What objectives, if any, of the company is this project designed to meet?

Increase the business by introducing consumers to all natural products that’s cost efficient.

Increase accessibility when all other teas shops are closed.

Increase awareness of various teas and how it benefits your health.

Increase sales and growth by providing reward incentives for becoming a loyal customer

Business Need

Why should we do this project? What will be gained, changed, or modified? Is there a financial or business reason to do this project? This area should contain any feasibility studies, NPV, PI, PB, or PBD used to advance the project.

All Natural Tea is a business that will allow customers to understand the major difference in natural products vs. man made products. However, this will be cost efficient because there will be tons of research and travelling in locating these natural products. It may instances where I, the project manager will do the worldwide travelling in retrieving sample products. Of course, we are a startup business because from personal experience, in order to be healthy and to stay healthy is to become a natural consumer.

My team and I do under that there is cost involved which will involve using a minor part of the budget. Once All Natural Tea launches, our business will not be just a place to buy natural products but to extend literature on why you as a consumer will make an educated guess on what will work them.

All team/upper echelons will be trained aside from their project positions on the major differences

Project Manager and Stakeholders

Who will lead this project? Who are the major stakeholders?

Adelaja Osho will be leading the project.

They major stakeholders will be the customer that we are putting the coffee shop together for. They are paying us to get their business up and running in a timely manner.

Milestones

What are the key milestone dates associated with the project?

Electrical, plumbing and wireless network - Completed by 10/26/18

Inspection Date - 10/26/18

Equipment Delivery and Setup - Completed by 10/26/18

Material ordered and delivered - Completed by 10/26/18

Tea shop ready to open by - 12/30/18

Budget

What is the order-of-magnitude budget for this project?

Our budget for the tea shop will run around $2, 500,000. This is taking for granted that the customer has already rented a building and we will only be working on the actual business end.

User Acceptance Criteria/Quality

What are the minimum success criteria as defined by the key stakeholders?

The minimum criteria are as follows:

All utilities such as electrical, plumbing and the wireless network are in proper working order.

The store has a comfortable feel to it that welcomes customers while being efficient for the staff.

To have all machinery in place and working before opening day.

To have the tea and food items ordered and ready to be put to use.

High-Level Project Assumptions

New hardware is functional

Utilities and Plumbing are installed and fully functional

Purchasing certain goods and equipment

Staff is trained and assigned hour

What are the assumptions on which the project is based?

High-Level Project Constraints

What are the major limiting factors that affect the project?

Insufficient Funds

Location not being selected on time

Climate change will affect this tea project, particularly smallholders who are least equipped to cope with it

The market

The customer

Value proposition

Exclusions and Boundaries

To be included:

The boundaries of the project would be to allow small changes to the design of the project once it has already started.

Shortening or extending the project completion as needed.

Exclusion to the project would consist of redesigning the project once it has commenced along with switching locations last minute.

To not be included:

Business Plan

Startup Location and Operating Budget

Interviewing and Training of the Staff

What are the boundaries of the project? What is to be included and what is to be excluded from the project?

Major Risks

What are the major risks affecting the project?

Estimates are inaccurate

Short on resources

Requirements are incomplete

Location of the Tea Shop

KEY STAKEHOLDERS

Project Manager Authority Level

Adelaja Osho

Project Core Team

None

Subject Matter Experts (SMEs)(include company and channel designations if applicable)

The All natural Tea Company

APPROVALS

Type Name

Alade Ademola Gbolahan

Signature

Ademola A. Gbolahan

Date

10/25/2018

Project Manager Approval:

Adelaja Osho

10-25-2018

Customer/Sponsor Approval:

Mr. Alade

Create a project scope statement on template below using project charter on Tea Shop above?

Project Scope Statement

Project Name

Project Number

Project Manager

Prioritization

Owner(s)

Statement of Work—Project Description and

Project Product

This section is typically a detailed amplification of the project SOW and mission from the Project Charter. This also includes how you intent to accomplish the project. “We intend to do this. . . and here are the steps we intend to use to accomplish the project.”

This section is typically a detailed amplification of the SOW product description from the Project Charter. What will the product of the project look like or what should it be able to do when completed?

Project Deliverables

What are the tangible outputs or services of this project? What big-picture items will have to be created or performed in order to accomplish the statement of work? These are the deliverables to be found in the WBS.

Project Objectives

What are the cost, schedule, and quality objectives of this project?

Project Assumptions

What are the assumptions on which the project is based?

Project Constraints

What are the major limiting factors that affect the project?

Exclusions

What are the boundaries of the project? What is to be included and what is to be excluded from the project?

Acceptance Criteria

What must the product be able to do when completed to be acceptable to the customer? What standards or regulations must the product meet? What performance specifications must the product meet to be acceptable to the customer?

Technical Requirements

How should the product work? What features should it have? What functionality must it have?

APPROVALS

Type Name

Signature

Date

Project Manager Approval:

Customer/Sponsor Approval:

Create a project scope statement on template below using project charter on Tea Shop above?

I need an expert to answer this questions!

Solutions

Expert Solution

Project Scope Statement

Project Name

Tea Shop

Project Number

034

Project Manager

Adelaja Osho

Prioritization

High

Owner(s)

Mr. Alade(Property Owner)

Statement of Work—Project Description and

Project Product

Client Background & project description:

All Natural Tea is a startup business and its focus is to provide the awareness to customers for the usage of natural products instead of manmade or artificial products. This project is a startup business because from personal experience, it is with the objective of : in order to be healthy and to stay healthy is to become a natural consumer.

Research will be done for this by retrieving variety of sample products worldwide.

Following are main objective of business :

  1. All Natural Tea want to increase the business by introducing consumers to all natural products that’s cost efficient.
  2. All Natural Tea want to increase accessibility when all other teas shops are closed.
  3. All Natural Tea want to increase awareness of various teas and how it benefits consumer’s health

This purpose of this project is to provide an open mind to clients and customers of how natural products can save money and enrich consumer’s to make them feel good about themselves, inside and outside.

This project will also allow the management of a budget when the right products are researched and tested.

All Natural Tea want to extend literature on why consumer will make an educated guess on what will work them.

Training to all team and upper echelons will be part of the project. Training should be based on their project positions or roles in business

Project Plan Activities:

Project Activity

Time to completion

Activity 1:Installation all utilities such as electrical, plumbing and the wireless network

Project Start date+4 week

Activity 2: Testing & Acceptance of all utilities equipment that those are in proper working order.

Project Start date+5 week

Activity 3: Store Setup with Interior, amenities to give comfortable feel welcome of customers and staff.

Project Start date+6 w Project Start date+5 week

Activity 4: Procurement of all machinery in place and working before opening day.

Project Start date+8 week

Activity 5: Procurement of the tea and food items and ready to be put to use.

Project Start date+9 week

Activity 5: Training to staff

Project Start date+9 week

Our specialties:

We have enough experience to do this project and have proper business understanding. We have delivered our entire project with timely deliverables.

Below is our plan to accomplish this project:

Project Deliverables

Deliverables

Time to completion

Installation & Testing of all utilities & Networking

Project Start date+5 week

Store Readiness to work

Project Start date+6 week

Procurement of all machinery with working condition

Project Start date+8 week

Procurement of the tea and food items and ready to be put to use.

Project Start date+9 week

Training to staff

Project Start date+9 week

Project Objectives

Cost of Project:

S.No

Project Activity

Cost (INR)

1

Installation all utilities such as electrical, plumbing and the wireless network

500000/-

2

Store Setup with Interior, amenities to give comfortable feel welcome of customers and staff.

500000/-

3

Procurement of all machinery in place and working before opening day.

2500000/-

4

Procurement of the tea and food items and ready to be put to use.

500000/-

5

Training to staff

300000/-

Total

4300000/-

Schedule:

Deliverables

Time to completion

Installation & Testing of all utilities & Networking

Project Start date+5 week

Store Readiness to work

Project Start date+6 week

Procurement of all machinery with working condition

Project Start date+8 week

Procurement of the tea and food items and ready to be put to use.

Project Start date+9 week

Training to staff

Project Start date+9 week

Quality:

We have enough experience to do this project and have proper business understanding. We have delivered our entire project with timely deliverables.

We had already handled 10 project of this criteria with experience 20 years in this field.

Project Assumptions

  1. List of all machinery and equipment should be finalized and facilities should be listed as per need of business.
  2. Number & type of staff details should be provided for training purpose and it should be finalized in contract agreement.

Project Constraints

  1. Machinery & equipment will be procured for finalized quantity and their functional and technical requirement should be finalized in contract agreement.

Exclusions

NA

Acceptance Criteria

  1. All utilities such as electrical, plumbing and the wireless network are in proper working order.
  2. The store has a comfortable feel to it that welcomes customers while being efficient for the staff.
  3. To have all machinery in place and working before opening day.
  4. To have the tea and food items ordered and ready to be put to use.

Technical Requirements

  1. electrical, plumbing and the wireless network should be in proper working position
  2. Store should have complete setup with all business amenities
  3. Availabilty of best Tea and food of natural type.

APPROVALS

Alade Ademola Gbolahan

Alade Ademola Gbolahan

Project Manager Approval:

Adelaja Osho

Customer/Sponsor Approval:

Mr. Alade


Related Solutions

You are the owner of a chain of tea shop in Thailand, brewing and selling the...
You are the owner of a chain of tea shop in Thailand, brewing and selling the latest types of teas internally but buying all necessary factors from the market. Your 50 or so shops located around the city can seat around 20 patrons each and currently only sell caffeinated drinks. At this stage of growing your business you are considering vertical and horizontal integration. Using the theory of the optimal boundary of the firm, discuss the make-or-buy decision as well...
You have become the owner-manager of a small local bubble tea seller that has outlets in...
You have become the owner-manager of a small local bubble tea seller that has outlets in 10 prime shopping-center locations across Singapore. Given the structure of this market discussed in question 3, you are considering vertical and horizontal integration. Using the theory of the optimal boundary of the firm, discuss the make-or-buy decision as well as the scope for horizontal integration and diversification of your firm. What stages of the vertical chain should you consider conducting inhouse? What other horizontal...
You have become the owner-manager of a small local bubble tea seller that has outlets in...
You have become the owner-manager of a small local bubble tea seller that has outlets in 10 prime shopping-center locations across Singapore. Given the structure of this market is monopolistic competition, you are considering vertical and horizontal integration. Using the theory of the optimal boundary of the firm, discuss the make-or-buy decision as well as the scope for horizontal integration and diversification of your firm. What stages of the vertical chain should you consider conducting inhouse? What other horizontal markets...
You have become the owner-manager of a small local bubble tea seller that has outlets in...
You have become the owner-manager of a small local bubble tea seller that has outlets in 10 prime shopping-center locations across Singapore. Given the structure of this market discussed in question 3, you are considering vertical and horizontal integration. Using the theory of the optimal boundary of the firm, discuss the make-or-buy decision as well as the scope for horizontal integration and diversification of your firm. What stages of the vertical chain should you consider conducting inhouse? What other horizontal...
To Savor or to Groupon? Mr. Chang, the owner of Enter the Dragon, a high-end Asian...
To Savor or to Groupon? Mr. Chang, the owner of Enter the Dragon, a high-end Asian restaurant in Chicago, was puzzled by the choices put before him by the Groupon sales representative. He could offer a daily deal at Groupon (a $60 coupon for $30) that would be seen by hundreds of thousands of Groupon subscribers in the Chicago region, or he could offer a more tailored discount at Savored, a restaurant reservation site also owned by Groupon. Business had...
You are a project manager. Attached you have a project definition provided by a Project Owner....
You are a project manager. Attached you have a project definition provided by a Project Owner. You have assisted the owner in developing a brief scope based on the project objective. From this limited scope you are to create a design proposal as an architectural(discipline) 1)Why are we doing this project? –Project objective provided by owner 2)What is needed to accomplish the end objective of the project? (plans, specifications, industry standards) 3)What is the cost to complete the project? 4)How...
(A) Mr. Obenten is an owner-manager of a small business, which started some few months ago....
(A) Mr. Obenten is an owner-manager of a small business, which started some few months ago. He is contemplating on how he can plan and sustain his business growth. As a business growth consultant, discuss the three (3) things he needs to do in preparing for his business growth.                                                            
Part a The Bogue High School Gift Shop purchases sweatshirts emblazoned with the school name and...
Part a The Bogue High School Gift Shop purchases sweatshirts emblazoned with the school name and logo from a vendor in Montego Bay at a cost of $2,000 each. The annual holding cost for a sweatshirt is calculated as 1.5% of the purchase cost. It costs the Gift Shop $500 to place a single order. The Gift Shop manager estimates that 900 sweatshirts will be sold during each month of the upcoming academic year. i) Determine the highest number of...
create a project charter GENERAL PROJECT INFORMATION Project Name: Project Sponsor: Project Manager: Email Address: Phone...
create a project charter GENERAL PROJECT INFORMATION Project Name: Project Sponsor: Project Manager: Email Address: Phone Number: Organizational Unit: Process Impacted: Expected Start Date: Expected Completion Date: Expected Savings: Estimated Costs: PROBLEM, ISSUE, GOALS, OBJECTIVES, DELIVERABLES Problem or Issue: Purpose of Project: Business Case: Goals/Metrics: Expected Deliverables: PROJECT SCOPE & SCHEDULE Within Scope Outside of Scope PROJECT RESOURCES & COSTS Project Team Support Resources Special Needs PROJECT BENEFITS & CUSTOMERS Process Owner Key Stakeholders Final Customers Expected Benefits PROJECT RISKS,...
1: Mr. Mahmoud is the owner of EFG company his finance manager Miss. Bushra presented financial...
1: Mr. Mahmoud is the owner of EFG company his finance manager Miss. Bushra presented financial statements with big difference of percentage declined in terms of assets, net income and high increased of liabilities compared to the last year. Mr. Mahmoud ask Miss. Bushra to give explanation, that did not satisfy him. Mr. Mahmoud decided to hire external auditor to clear his doubts. Based on the above scenario: 1. Wite at least 3 interpretations of financial statement which the auditor...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT