In: Accounting
Activity-Based Costing
Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools:
Fabrication Department |
Finishing Department |
Cost Driver | |
---|---|---|---|
Maintenance | $ 54,000 | 27,000 | Machine hours |
Materials handling | 81,000 | 40,500 | Material moves |
Machine | 189,000 | 13,500 | Machine setups |
Inspections |
- |
67,500 |
Inspection hours |
Total |
$ 324,000 |
$ 148,500 |
The following activity predictions were also made for the year:
Fabrication Department |
Finishing Department |
|
---|---|---|
Machine hours | 5,000 | 2,500 |
Material moves | 1,500 | 750 |
Machine setups | 350 | 25 |
Inspection hours | - | 500 |
It is assumed that the cost per unit of activity for a given activity does not vary between departments. Steampunk's president, Abner Punk, is trying to evaluate the company's product mix strategy regarding two of its product models, SW100 and SG150. The company has been using a company wide overhead rate based on machine hours but is considering switching to either department rates of activity-based rate. The production manager has provided the following data for the production of a batch of 100 units for each of these models:
SW100 | SG150 | |
---|---|---|
Direct materials cost | $ 18,000 | $ 27,000 |
Direct labor cost | $ 7,200 | $ 5,400 |
Machine hours (Fabrication) | 250 | 350 |
Machine hours (Finishing) | 100 | 50 |
Materials moves | 20 | 40 |
Machine setups | 5 | 10 |
Inspection hours | 15 | 30 |
a. Determine the cost of one unit each of SW100 and SG150, assuming a company-wide overhead rate is used based on total machine hours.
Round rate to two decimal places.
Overhead rate based on total machine hours: Answer
per machine hour
Use rounded overhead rate calculated about for calculations below. Round cost answers to the nearest whole number. Round cost per unit to two decimal places.
Product Costs per Unit | SW100 | SG150 |
---|---|---|
Direct materials | Answer | Answer |
Direct labor | Answer | Answer |
Manufacturing overhead | Answer | Answer |
Total cost per batch | Answer | Answer |
Number of units per batch | Answer | Answer |
Cost per unit | Answer | Answer |
b. Determine the cost of one unit of SW100 and SG150, assuming department overhead rates are used. Overhead is assigned based on machine hours in both departments.
Round to two decimal places, if applicable.
Overhead rate based on machine hours for Fabrication Dept.: Answer
per machine hour.
Overhead rate based on machine hours for Finishing Dept.: Answer
per machine hour.
Use rounded overhead rate calculated above for calculations below. Round cost answers to the nearest whole number, when needed. Round cost per unit to two decimal places, if needed.
Product Costs per Unit | SW100 | SG150 |
---|---|---|
Direct materials | Answer | Answer |
Direct labor | Answer | Answer |
Manufacturing overhead: | ||
Fabrication Dept. | Answer | Answer |
Finishing Dept. |
Answer |
Answer |
Total cost per batch |
Answer |
Answer |
Number of units per batch | Answer | Answer |
Cost per unit |
Answer |
Answer |
c. Determine the cost of one unit of SW100 and SG150, assuming activity-based overhead rates are used for maintenance, materials handling, machine setup, and inspection activities.
Round rate to two decimal places, if applicable.
Activity-based overhead rates: | |
Maintenance | Answer |
Materials handling | Answer |
Machine setup | Answer |
Inspection activities | Answer |
Use rounded overhead rate calculated above for calculations below. Round cost answers to the nearest whole number, when needed. Round cost per unit to two decimal places, if needed.
Product Costs per Unit | SW100 | SG150 |
---|---|---|
Direct materials | Answer | Answer |
Direct labor | Answer | Answer |
Manufacturing overhead: | ||
Maintenance activity | Answer | Answer |
Maintenance handling activity | Answer | Answer |
Machine setups activity | Answer | Answer |
Inspections activity |
Answer |
Answer |
Total cost per batch | Answer | Answer |
Number of units per batch | Answer | Answer |
Cost per unit |
Answer |
Answer |
Calculation of the Cost per unit:
Notes:
Total Overheads=$ 472500
Total Machine hours=7500 machine hours
Overheads per machine hour=$ 472500/7500 machine hours=$ 63per machine hour
Particulars |
SW 100 |
SG 150 |
Direct Materials |
$ 18000 |
$ 27000 |
Direct Labor Cost |
$ 7200 |
$ 5400 |
Overheads |
$ 22050 ($ 63*350 Hours) |
$ 25200 ($ 63*400 Hours) |
Total Cost of a Batch |
$ 47250 |
$ 57600 |
Number of units |
100 |
100 |
Total Cost per unit |
$ 472.50 |
$ 576 |
Overhead rate based on machine hours for Finishing Dept.: $ 59.4 per machine hour. .(See Note Below)
Notes:
Total machine hours for Fabrication Dept=5000 hours
Overhead Cost per hour=$ 64.8 per machine hour
Total overheads of for Finishing Dept=$ 148500
Total machine hours for Finishing Dept=2500 hours
Overhead Cost per hour=$ 59.4 per machine hour
Calculation of Cost per unit
Particulars |
SW 100 |
SG 150 |
Direct Materials |
$ 18000 |
$ 27000 |
Direct Labor |
$ 7200 |
$ 5400 |
Manufacturing Overhead |
||
Fabrication Department |
$ 16200 ($ 64.8 per hour*250 Hours) |
$ 22680 ($ 64.8 per hour*350 Hours) |
Finishing Department |
$ 5940 ($ 59.4 per hour* 100 hours) |
$ 2970 ($ 59.4 per hour* 50 hours) |
Total cost per Batch |
$ 47340 |
$ 58050 |
Number of units per batch |
100 |
100 |
Cost per unit |
$ 473.4 |
$ 580.5 |
Activity |
Rate |
Maintenance |
$ 10.8 per machine hour hour |
Material handling |
$ 52 per material move |
Machine setup |
$ 540 per machine setup |
inspection |
$ 135 per inspection hour |
Note 1:
Calculation of activity based overhead rate
Activity (A) |
Cost pool(B) |
Cost Driver (C) |
Cost /Cost driver(D)=(B)/(C ) |
Maintenance |
$ 81000 |
Machine hours (7500 hours) |
$ 10.8 per machine hour hour |
Material Handling |
$ 121500 |
Material moves (2250 material moves) |
$ 52 per material move |
Machine Setup |
$ 202500 |
Machine setups (375 machine setups) |
$ 540 per machine setup |
Inspection |
$ 67500 |
Inspection hours (500 inspection hours) |
$ 135 per inspection hour |
Total |
$ 472500 |
Calculation of cost per unit
Particulars |
SW 100 |
SG 150 |
Direct materials |
$ 18000 |
$ 27000 |
Direct labor |
$ 7200 |
$ 5400 |
Maintenance |
$ 3780 ($ 10.8 per machine hour hour* 350 hours) |
$ 4320 ($ 10.8 per machine hour hour *400 hours) |
Material handling |
$ 1040 ($ 52 per material move* 20 moves) |
$ 2080 ($ 52 per material move* 40 moves) |
Machine setups |
$ 2700 ($ 540 per machine setup*5 Seups) |
$ 5400 ($ 540 per machine setup* 10 setups) |
Inspection |
$ 2025 ($ 135 per inspection hour* 15 hours) |
$ 4050 ($ 135 per inspection hour* 30 hours) |
Total Cost |
$ 34745 |
$ 48250 |
Number of units |
100 |
100 |
Cost per unit |
$ 347.45 |
$ 482.5 |