Question

In: Finance

Comparing all methods. Risky Business is looking at a project with the following estimated cash​ flow:...

Comparing all methods. Risky Business is looking at a project with the following estimated cash​ flow: Initial investment at start of​ project: ​$12,300,000 Cash flow at end of year​ one: ​$2,214,000 Cash flow at end of years two through​ six: ​$2,460,000 each year Cash flow at end of years seven through​ nine: ​$2,878,200 each year Cash flow at end of year​ ten: ​$2,214,000 Risky Business wants to know the payback​ period, NPV,​ IRR, MIRR, and PI of this project. The appropriate discount rate for the project is 10​%. If the cutoff period is 6 years for major​ projects, determine whether the management at Risky Business will accept or reject the project under the five different decision models.

Solutions

Expert Solution

Risky business
Year Cash flow stream Cumulative cash flow
0 -12300000 -12300000
1 2214000 -10086000
2 2460000 -7626000
3 2460000 -5166000
4 2460000 -2706000
5 2460000 -246000
6 2460000 2214000
7 2878200 5092200
8 2878200 7970400
9 2878200 10848600
10 2214000 13062600
Payback period is the time by which undiscounted cashflow cover the intial investment outlay
this is happening between year 5 and 6
therefore by interpolation payback period = 5 + (0-(-246000))/(2214000-(-246000))
5.1 Years

accept project as payback period is less than cut off period of 6 years

Risky business
Discount rate 10.000%
Year 0 1 2 3 4 5 6 7 8 9 10
Cash flow stream -12300000 2214000 2460000 2460000 2460000 2460000 2460000 2878200 2878200 2878200 2214000
Discounting factor 1.000 1.100 1.210 1.331 1.464 1.611 1.772 1.949 2.144 2.358 2.594
Discounted cash flows project -12300000.000 2012727.273 2033057.851 1848234.410 1680213.100 1527466.455 1388605.868 1476971.696 1342701.542 1220637.765 853592.843
NPV = Sum of discounted cash flows
NPV Risky business = 3084208.80
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
accept project as NPV is greater than 0
PI= (NPV+initial inv.)/initial inv.
=(3084208.8+12300000)/12300000
1.25
accept project as PI is greater than 1

IRR

False False Center Center
Risky business
IRR is the rate at which NPV =0
IRR 15.38%
Year 0 1 2 3 4 5 6 7 8 9 10
Cash flow stream -12300000.000 2214000.000 2460000.000 2460000.000 2460000.000 2460000.000 2460000.000 2878200.000 2878200.000 2878200.000 2214000.000
Discounting factor 1.000 1.154 1.331 1.536 1.772 2.045 2.359 2.722 3.141 3.624 4.181
Discounted cash flows project -12300000.000 1918891.839 1847910.213 1601598.838 1388118.762 1203093.841 1042731.234 1057380.078 916439.929 794285.953 529549.313
NPV = Sum of discounted cash flows
NPV Risky business = 0.000
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 15.38%

accept project as IRR is greater than discount rate

Combination approach
All negative cash flows are discounted back to the present and all positive cash flows are compounded out
to the end of the project’s life
Thus year 8 modified cash flow=(5220496.19)+(5273228.47)+(4793844.07)+(4358040.06)+(3961854.6)+(3601686)+(3830884.2)+(3482622)+(3166020)+(2214000)
=39902675.59
Thus year 0 modified cash flow=-12300000
=-12300000
Discount rate 10.000%
Year 0 1 2 3 4 5 6 7 8 9 10
Cash flow stream -12300000.000 2214000.000 2460000.000 2460000.000 2460000.000 2460000.000 2460000.000 2878200.000 2878200.000 2878200.000 2214000.000
Discount factor 1.000 1.100 1.210 1.331 1.464 1.611 1.772 1.949 2.144 2.358 2.594
Compound factor 2.594 2.358 2.144 1.949 1.772 1.611 1.464 1.331 1.210 1.100 1.000
Discounted cash flows -12300000.000 0 0 0 0 0 0 0 0 0 0
Compounded cash flows 0.000 5220496.19 5273228.47 4793844.07 4358040.06 3961854.6 3601686 3830884.2 3482622 3166020 2214000
Modified cash flow -12300000.000 0 0 0 0 0 0 0 0 0 39902675.590
Discounting factor (using MIRR) 1.000 1.125 1.265 1.423 1.601 1.801 2.026 2.279 2.564 2.884 3.244
Discounted cash flows -12300000.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 12300000.000
NPV = Sum of discounted cash flows
NPV= 0.00
MIRR is the rate at which NPV = 0 0.00
MIRR= 12.49%
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Compounding factor = (1 + reinvestment rate)^(time of last CF-Corresponding period in years)
Compounded Cashflow= Cash flow stream*compounding factor

MIRR is greater than cost of capital hence accept the project


Related Solutions

Comparing all methods. Risky Business is looking at a project with the following estimated cash​ flow:...
Comparing all methods. Risky Business is looking at a project with the following estimated cash​ flow: Risky Business wants to know the payback​ period, NPV,​ IRR, MIRR, and PI of this project. The appropriate discount rate for the project is 12​%. If the cutoff period is 6 years for major​ projects, determine whether the management at Risky Business will accept or reject the project under the five different decision models. What is the payback period for the new project at...
Comparing all methods. Risky Business is looking at a project with the following estimated cash​ flow:...
Comparing all methods. Risky Business is looking at a project with the following estimated cash​ flow: Initial investment at start of​ project: ​$10,700,000 Cash flow at end of year​ one: ​$1,819,000 Cash flow at end of years two through​ six: ​$2,140,000 each year Cash flow at end of years seven through​ nine: ​$2,000,900 each year Cash flow at end of year​ ten: ​$1,539,154 Risky Business wants to know the payback​ period, NPV,​ IRR, MIRR, and PI of this project. The...
Comparing all methods. Risky Business is looking at a project with the estimated cash flow as?...
Comparing all methods. Risky Business is looking at a project with the estimated cash flow as? follows: Initial investment at start of? project:???$12 comma 600 comma 000 Cash flow at end of year? one:???$2 comma 268 comma 000 Cash flow at end of years two through? six:???$2 comma 520 comma 000 each year Cash flow at end of years seven through? nine:???$2 comma 948 comma 400 each year Cash flow at end of year? ten:???$2 comma 268 comma 000 Risky...
Risky Business is looking at a project with the following estimated cash​ flow: Initial investment at...
Risky Business is looking at a project with the following estimated cash​ flow: Initial investment at start of​ project: ​$10,000,000 Cash flow at end of year​ one: ​$1,700,000 Cash flow at end of years two through​ six: ​$2,000 each year Cash flow at end of years seven through​ nine: ​$2,040,000 each year Cash flow at end of year​ ten: ​$1,569,231 Risky Business wants to know the payback​ period, NPV,​ IRR, MIRR, and PI of this project. The appropriate discount rate...
Risky Business is looking at a project with the estimated cash flow as​ follows: Initial investment...
Risky Business is looking at a project with the estimated cash flow as​ follows: Initial investment at start of​ project:$12,200,000 Cash flow at end of year​ one: $2,196,000 Cash flow at end of years two through​ six:$2,440,000 each year Cash flow at end of years seven through​ nine:$2,635,200 each year Cash flow at end of year​ ten: $2,027,077 Risky Business wants to know the payback​ period, NPV,​ IRR, and PI of this project. The appropriate discount rate for the project...
•You are looking at a new project and you have estimated the following cash flows: Year...
•You are looking at a new project and you have estimated the following cash flows: Year 0: CF = -$150,000 Year 1-2: CF = $80,000 Year 3-4: CF = $50,000 Year 5-6: CF = $30,000 Year 7: CF = -$180,000 Your cost of capital is 10% Please calculate NPV and IRR, and decide whether we should take this project?
1)you've estimated the following cash flows (in$) for a project A. B year. cash flow 0...
1)you've estimated the following cash flows (in$) for a project A. B year. cash flow 0 -5,300 1 1,325 2 2,148 3 2,209 what is the IRE for the project 2)you've estimated the following cash flows (in$) for 2 projects: A. B. C.    year. ProjectA. ProjectB 0. -78 -261 1 15 50 2 21 73 3 29 82 4 35 127 the required return is 7% for both projects What is the IRR for project B? What is the...
Operating cash flow​ (growing each​ year; MACRS). Miglietti Restaurants is looking at a project with the...
Operating cash flow​ (growing each​ year; MACRS). Miglietti Restaurants is looking at a project with the following forecasted​ sales: ​ first-year sales quantity of 31,000​ with an annual growth rate of 4.00​% over the next ten years. The sales price per unit will start at $42 and will grow at 2.50​% per year. The production costs are expected to be 55​% of the current​ year's sales price. The manufacturing equipment to aid this project will have a total cost​ (including...
You are considering a project with the following cash​ flows: YEAR                      PROJECT CASH FLOW    ...
You are considering a project with the following cash​ flows: YEAR                      PROJECT CASH FLOW     0                         -60,000     1                         25,000     2                         25,000     3                         25,000     4                         25,000 If the appropriate discount rate is 11 ​percent, what is the​ project's discounted payback​ period in years?
What are the best methods to use for cash flow analysis in your business or personal...
What are the best methods to use for cash flow analysis in your business or personal life?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT