Question

In: Advanced Math

You are responsible for developing a supervisory training programme for a company. The following table shows...

You are responsible for developing a supervisory training programme for a company. The following table shows the relationships between the activities that must be completed, along with estimates of the durations in days.

Table 1: Activity Times and Predecessors

Activity Immediate Predecessors Optimistic Time (a) Most Likely time (m) Pessimistic Time (b)
A - 3 7 13
B - 5 10 17
C A,B 3 5 8
D C 5 12 14
E C 2 5 9
F E 2 5 15
G E,F 5 8 12
H D 6 10 12
I E,H 3 4 8
J G, I 4 7 10

Required
(a) Draw the activity network for this problem (either AON or AOA)
(b) Determine the Expected Time and Variance for each activity (show in a table).
Round off times to two decimal places where fractional.
(c) Show the activity schedule (ES, EF, LS, LF) as well as slack (in table).
(d) Determine and state the critical path for this project. This must be based on
your work in c) and not by inspection.
(e) What are the expected time and the variance of the project?
(f) What is the probability the project will be finished within 49 days?
(g) What time should be set such that there is a 99% chance of completion?
(h) What is the probability the project will take between 45 and 50 days?

Solutions

Expert Solution

Project Evaluation and Review Technique is used


Related Solutions

A company wished to know if the training programme that they developed for a particular task...
A company wished to know if the training programme that they developed for a particular task was effective. 20 employees were timed performing the task before and after the training. The times were recorded and are given in Table 1. Table 1 Time spent performing the task (in minutes) Before training After training 27 24 28 23 22 20 26 24 21 21 31 24 29 24 27 23 29 22 29 25 28 23 28 24 28 25 27...
1. You are tasked with developing a research programme for one of the areas mentioned below....
1. You are tasked with developing a research programme for one of the areas mentioned below. Outline (i) the main objective, (ii) the expected outcomes and (iii) at least four specific research projects to be executed. The programmes are (a) Biochar production and utilization, (b) Non-timber Forest Products development
You are the project director responsible for creating an implementation timeline that addresses the training and...
You are the project director responsible for creating an implementation timeline that addresses the training and go-live activities for a nursing documentation system that will be implemented on 20 units and involve 350 users. Determine whether the implementation will be staggered or occur simultaneously on all units and provide your rationale.
Many of you are responsible for either developing a budget or meeting a budget developed for...
Many of you are responsible for either developing a budget or meeting a budget developed for your department. Use your experience or research the topic to answer any three of the following questions. Identify at least three benefits of budgeting in helping managers plan and control a business. How does a budget benefit management in its control function? What is the benefit of continuous budgeting? Why should each department participate in preparing its own budget? How does budgeting help management...
Following is an extract from the database of a construction company. The table shows the height...
Following is an extract from the database of a construction company. The table shows the height of walls in feet and the cost of raising them. The estimated simple linear regression equation is given as Ŷ = b0 + b1X. (Hint: Use Excel functions). Height (ft) Cost ($) 4 670 3 430 7 810 9 1100 6 790 8 880 5 760 11 1200 1) What is the value of the coefficient b1? A) 254.8371 B) 0.010697 C) -2.14625 D)...
1: As a medical assistant you may be responsible for training and MA's. . how much...
1: As a medical assistant you may be responsible for training and MA's. . how much can you prepare them to properly protect themselves from exposure to infection agents. 2:list major types of infectious agents . Describe the infection cycle including: a. the infection agents; b. reservoir; c.susceptible host; d. means of transaction; portals of entry; portals of exit.
A Company manufactures and sells two products: A and B. The following table shows the information...
A Company manufactures and sells two products: A and B. The following table shows the information relating to these products: A B Total Selling price per unit $20 $40 Variable cost per unit $10 $20 Total Fixed costs $80,000 Required: If Sales mix is 2 :3 for A and B respectively, calculate the breakeven point in units and in dollars for each of the two products.
You are given the following demand table which shows the relationship between the price of a...
You are given the following demand table which shows the relationship between the price of a Honda Civic and the quantity demanded of Civics and Toyota Corollas: Price of Civic Quantity of Civics Quantity of Corollas $20,000 600 1000 $16,000 1200 800 a) What is the arc price elasticity of demand for Civics? b) What is the cross-price elasticity of demand for Corollas with respect to Civics?
The following table is used for a number of questions below. The table above shows the...
The following table is used for a number of questions below. The table above shows the responses of a survey of teenagers aged 14-18 when asked at what age they thought they would become financially independent. Age of Financial Independence Number of Responses 16-20 191 21-24 467 25-27 244 28 or older 42 What do the teens expect is the probability of being financially independent before age 25? A recent Gallup poll found that only 14 percent of 24- to...
Question The following table shows a cross-tabulation of 300 employees of a small manufacturing company by...
Question The following table shows a cross-tabulation of 300 employees of a small manufacturing company by age and department. DEPARTMENT Age Production Sales Technical Total < 25 50 50 2 102 25-40 70 24 50 144 > 40 40 10 4 54 Total 160 84 56 300 If an employee is selected at random from this population, calculate the probability that the employee is: 7. Employee aged under 25 years * 5 points Your answer 8. Employee from Production *...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT