Question

In: Finance

KORONA Manufacturing is considering investing in either of two mutually exclusive projects, A and B. The...

KORONA Manufacturing is considering investing in either of two mutually exclusive projects, A and B. The firm has a 14 percent cost of capital, and the risk-free rate is currently 9 percent. The initial investment, expected cash inflows, and certainty equivalent factors associated with each of the projects are shown in the following table.

Project A
Project B

Initial investment (II)
$ 40,000
$ 56,000

Year (t)
Cash inflows (CFt)
Certainty equivalent factors (αt)
Cash inflows (CFt)
Certainty equivalent factors (αt)

   1
    $20,000                                             
            0.90                        
   $20,000             
          0.95

   2
      16,000                         
            0.80                    
     25,000             
          0.90

   3
      12,000                        
            0.60                       
     15,000                   
          0.85

   4                                     
      10,000
            0.50                    
     20,000                      
          0.80

   5
      10,000                            
            0.40                 
     10,000               
          0.80

Find the net present value (unadjusted for risk) for each project.
Find the certainty equivalent net present value for each project
Compare and discuss your findings in a) and b) above. Which, if either, of the projects do you recommend that the firm accept? Explain. (

Solutions

Expert Solution

a)

The Net present value is calculated by NPV function in excel => Initial Investment + NPV(0.14. Cash-flows year1-5)

Here, the discount rate is 0.14 or 14% which is the cost of capital of the firm

Year Project A Project B
0 -40000 -56000
1 20000 20000
2 16000 25000
3 12000 15000
4 10000 20000
5 10000 10000
NPV $9,069.49 $7,940.41

Hence the NPV for project A = $9069.49 and NPV for project B = $7940.41

b)

Certainty equivalent cash-flows are obtained by multiplying cash-flows with Certainty equivalent factors

Year Project A Cashflows Certainty equivalent factors Project A Certainty equivalent cash-flows
0 -40000 1 -40000
1 20000 0.9 18000
2 16000 0.8 12800
3 12000 0.6 7200
4 10000 0.5 5000
5 10000 0.4 4000

Year Project B Cashflows Certainty equivalent factors Project B Certainty equivalent cash-flows
0 -56000 1 -56000
1 20000 0.95 19000
2 25000 0.9 22500
3 15000 0.85 12750
4 20000 0.8 16000
5 10000 0.8 8000

Calculating the NPV of certainty equivalent cash-flows using NPV similar to part a)

Certainty equivalent cash-flows
Year Project A Project B
0 -40000 -56000
1 18000 19000
2 12800 22500
3 7200 12750
4 5000 16000
5 4000 8000
NPV ($4,463.67) $213.81

Certainty equivalent NPV for Project A = -$4463.67 and for Project B = $213.81

c)

If the certainty factor is not taken (unadjusted for risk) into consideration (Part a), NPV of project A is higher than Project B suggesting Project A is more profitable.

However, when the cash-flows are adjusted for risk through the certainty factor (Part b), NPV of Project B is higher than that of Project A.

Hence, after considering the risk associated with cash-flows, Project B must be accepted by the firm.


Related Solutions

ABC Company is considering investing in two mutually exclusive projects, L and S. The two projects’...
ABC Company is considering investing in two mutually exclusive projects, L and S. The two projects’ forecasted cash flows are shown as below. WACC is 10%. Year 0 1 2 3 4 Project L CF ($) -1,000    700 500 200 0 Project S CF ($) -1,200 100 300 800 1,000 a. Calculate the NPVs for both projects. b. Calculate the IRRs for both projects. c. Calculate the Discounted Paybacks for both projects. [Draw a timeline] d. Based on your...
A firm is considering two mutually exclusive projects, A and B. The projects are different in...
A firm is considering two mutually exclusive projects, A and B. The projects are different in that they have different returns depending on general economic conditions. The firm forecasts that return on the market, and the returns on each project, along with their associated probabilities will be given by the following table. You can assume a 5% risk free rate and a 6% market risk premium. Assume the CAPM holds. Compare the expected returns to the cost of capital for...
Swenson's is considering two mutually exclusive projects, Projects A and B, and has determined that the...
Swenson's is considering two mutually exclusive projects, Projects A and B, and has determined that the crossover rate for these projects is 11.7 percent and the required return for both projects is 9 percent. Given this you know that: Multiple Choice both projects have a zero NPV at a discount rate of 11.7 percent. neither project will be accepted if the discount rate is less than 11.7 percent. the project that is acceptable at a discount rate of 11 percent...
Your company is considering investing in one of two mutually exclusive projects. The cost of capital...
Your company is considering investing in one of two mutually exclusive projects. The cost of capital is 11%. The first project Has $25,000 annual cash inflows, a 10-year life, and will cost $120,000 at time zero. The second project has a 7-year life, Annual cash inflows of $20,000 per year, and a cost of $75,000 at time zero. Which project has the highest NPV. Assuming that these projects will most likely be repeated indefinitely into the future, which project would...
Your company is considering investing in one of two mutually exclusive projects. The cost of capital...
Your company is considering investing in one of two mutually exclusive projects. The cost of capital is 11%. The first project Has $25,000 annual cash inflows, a 10-year life, and will cost $120,000 at time zero. The second project has a 7-year life, Annual cash inflows of $20,000 per year, and a cost of $75,000 at time zero. Which project has the highest NPV. Assuming that these projects will most likely be repeated indefinitely into the future, which project would...
Heller Airlines is considering two mutually exclusive projects, A and B. The projects have the same...
Heller Airlines is considering two mutually exclusive projects, A and B. The projects have the same risk. Below are the cash flows from each project: Project A Project B Year Cash Flow Cash Flow 0 -$2,000 -$10,000 1 6,000 15,000 a. Graph the NPV profile of each investment. b. Indicate the crossover point and calculate the crossover rate. c. If the cost of capital is 8%, which project should be chosen and why?
Stephens, Inc. is considering investing in one of two mutually exclusive 4-year projects. Project A requires...
Stephens, Inc. is considering investing in one of two mutually exclusive 4-year projects. Project A requires equipment with a cost of $140,000 and increases net income by $5,000, $10,000, $20,000 and $30,000 in years 1-4, respectively. Project B requires equipment with a cost of $200,000 and increases cash flow by $70,000 per year in years 1-4. Both projects have a 4-year life and the equipment will be depreciated using straight-line depreciation. What is the NPV of project A at a...
IRRlMutually exclusive projects   Bell Manufacturing is attempting to choose the better of two mutually exclusive projects...
IRRlMutually exclusive projects   Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the​ firm'swarehouse capacity. The relevant cash flows for the projects are shown in the following​ table: Initial investment        $500,000         $320,000 Year                 1          $130,000         $130,000 2          $120,000         $120,000 3          $130,000         $105,000 4          $200,000         $90,000 5          $250,000         $40,000 The​ firm's cost of capital is 17​%. a.  Calculate the IRR for each of the projects. Assess the acceptability of each project on the basis of the IRRs. b.  Which project is​ preferred?
Good old XYZ Corp. is considering two mutually exclusive projects, A & B in order to...
Good old XYZ Corp. is considering two mutually exclusive projects, A & B in order to expand their product line. The cost accountants determined the following: A’s initial investment must be $42,400, while project B will cost $60,000. Project A has projected cash flows of $23,000 a year, and project B of $24,000 a year. The project should last 3 years.   In addition, the following rates has been given: the prime = 7%; Labor = 6%; the firm’s cost of...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $10,000 for 10 years. Project B costs $80,000 and generates cash flows of $2,000 for six years and then cash flows of $28,000 for four years. Report rates in percentage form to two decimal places i.e. 10.03% not 10% At what discount rate would make you indifferent between choosing one project or another? What is the highest discount rate in which...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT