In: Finance
KORONA Manufacturing is considering investing in
either of two mutually exclusive projects, A and B. The firm has a
14 percent cost of capital, and the risk-free rate is currently 9
percent. The initial investment, expected cash inflows, and
certainty equivalent factors associated with each of the projects
are shown in the following table.
Project A
Project B
Initial investment (II)
$ 40,000
$ 56,000
Year (t)
Cash inflows (CFt)
Certainty equivalent factors (αt)
Cash inflows (CFt)
Certainty equivalent factors (αt)
1
$20,000
0.90
$20,000
0.95
2
16,000
0.80
25,000
0.90
3
12,000
0.60
15,000
0.85
4
10,000
0.50
20,000
0.80
5
10,000
0.40
10,000
0.80
Find the net present value (unadjusted for risk) for
each project.
Find the certainty equivalent net present value for each
project
Compare and discuss your findings in a) and b) above. Which, if
either, of the projects do you recommend that the firm accept?
Explain. (
a)
The Net present value is calculated by NPV function in excel => Initial Investment + NPV(0.14. Cash-flows year1-5)
Here, the discount rate is 0.14 or 14% which is the cost of capital of the firm
Year | Project A | Project B |
0 | -40000 | -56000 |
1 | 20000 | 20000 |
2 | 16000 | 25000 |
3 | 12000 | 15000 |
4 | 10000 | 20000 |
5 | 10000 | 10000 |
NPV | $9,069.49 | $7,940.41 |
Hence the NPV for project A = $9069.49 and NPV for project B = $7940.41
b)
Certainty equivalent cash-flows are obtained by multiplying cash-flows with Certainty equivalent factors
Year | Project A Cashflows | Certainty equivalent factors | Project A Certainty equivalent cash-flows |
0 | -40000 | 1 | -40000 |
1 | 20000 | 0.9 | 18000 |
2 | 16000 | 0.8 | 12800 |
3 | 12000 | 0.6 | 7200 |
4 | 10000 | 0.5 | 5000 |
5 | 10000 | 0.4 | 4000 |
Year | Project B Cashflows | Certainty equivalent factors | Project B Certainty equivalent cash-flows |
0 | -56000 | 1 | -56000 |
1 | 20000 | 0.95 | 19000 |
2 | 25000 | 0.9 | 22500 |
3 | 15000 | 0.85 | 12750 |
4 | 20000 | 0.8 | 16000 |
5 | 10000 | 0.8 | 8000 |
Calculating the NPV of certainty equivalent cash-flows using NPV similar to part a)
Certainty equivalent cash-flows | ||
Year | Project A | Project B |
0 | -40000 | -56000 |
1 | 18000 | 19000 |
2 | 12800 | 22500 |
3 | 7200 | 12750 |
4 | 5000 | 16000 |
5 | 4000 | 8000 |
NPV | ($4,463.67) | $213.81 |
Certainty equivalent NPV for Project A = -$4463.67 and for Project B = $213.81
c)
If the certainty factor is not taken (unadjusted for risk) into consideration (Part a), NPV of project A is higher than Project B suggesting Project A is more profitable.
However, when the cash-flows are adjusted for risk through the certainty factor (Part b), NPV of Project B is higher than that of Project A.
Hence, after considering the risk associated with cash-flows, Project B must be accepted by the firm.