Question

In: Accounting

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:

2018 2019 2020
Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400
Estimated costs to complete as of year-end 5,609,000 2,054,000 0
Billings during the year 1,900,000 3,946,000 4,154,000
Cash collections during the year 1,700,000 3,500,000 4,800,000


Westgate Construction uses the completed contract method of accounting for long-term construction contracts.

Required:

1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2019 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2020 (credit "Various accounts" for construction costs incurred).
3. Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract.
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

2018 2019 2020
Cost incurred during the year $ 2,510,000 $ 3,855,000 $ 3,210,000
Estimated costs to complete as of year-end 5,710,000 3,210,000 0


5.
Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

2018 2019 2020
Cost incurred during the year $ 2,510,000 $ 3,855,000 $ 4,065,000
Estimated costs to complete as of year-end 5,710,000 4,210,000 0

Solutions

Expert Solution

  • All working forms part of the answer

Requirement 1

2018

2019

2020

Revenue

$       2,900,000.00

$       4,500,000.00

$          2,600,000.00

Gross Profits (Loss)

$           609,000.00

$          945,000.00

$              340,600.00

--Working

Working

2018

2019

2020

A

Contract Price

$     10,000,000.00

$    10,000,000.00

$        10,000,000.00

B

Cost Incurred to Date

$       2,291,000.00

$       5,846,000.00

$          8,105,400.00

C

Estimated cost yet to be incurred to complete the contract

$       5,609,000.00

$       2,054,000.00

$                                -   

D = B+C

Total Cost

$       7,900,000.00

$       7,900,000.00

$          8,105,400.00

E = (B/D) x 100

% of Completion

29.00%

74.00%

100.00%

F = A x E

Revenue to date

$       2,900,000.00

$       7,400,000.00

$        10,000,000.00

G

Revenue of Previous year

$                            -  

$       2,900,000.00

$          7,400,000.00

H = F - G

Net Revenue this year

$       2,900,000.00

$       4,500,000.00

$          2,600,000.00

I (=B)

Cost to date

$       2,291,000.00

$       5,846,000.00

$          8,105,400.00

J

Cost to date of previous year

$                            -  

$       2,291,000.00

$          5,846,000.00

K = I - J

Net Cost for the year

$       2,291,000.00

$       3,555,000.00

$          2,259,400.00

L = H - K

Gross Profits

$           609,000.00

$          945,000.00

$              340,600.00

  • Requirement 2

Requirement 2A

Date

Accounts title

Debit

Credit

2018

Construction in Progress

$           2,291,000.00

   Various accounts

$      2,291,000.00

(construction cost incurred)

2018

Accounts receivables

$           1,900,000.00

Billing on Construction contracts

$      1,900,000.00

(amount billed during the year)

2018

Cash

$           1,700,000.00

Accounts receivables

$      1,700,000.00

(cash received)

2018

Construction in Progress

$               609,000.00

Cost of construction

$           2,291,000.00

Revenue from Long Term contract

$      2,900,000.00

(revenue recognised)

Requirement 2B

Date

Accounts title

Debit

Credit

2019

Construction in Progress

$        3,555,000.00

   Various accounts

$ 3,555,000.00

(construction cost incurred)

2019

Accounts receivables

$        3,946,000.00

Billing on Construction contracts

$ 3,946,000.00

(amount billed during the year)

2019

Cash

$        3,500,000.00

Accounts receivables

$ 3,500,000.00

(cash received)

2019

Construction in Progress

$           945,000.00

Cost of construction

$        3,555,000.00

Revenue from Long Term contract

$ 4,500,000.00

(revenue recognised)

Requirement 2C

Date

Accounts title

Debit

Credit

2020

Construction in Progress

$      2,259,400.00

   Various accounts

$ 2,259,400.00

(construction cost incurred)

2020

Accounts receivables

$      4,154,000.00

Billing on Construction contracts

$ 4,154,000.00

(amount billed during the year)

2020

Cash

$      4,800,000.00

Accounts receivables

$ 4,800,000.00

(cash received)

2020

Construction in Progress

$          340,600.00

Cost of construction

$      2,259,400.00

Revenue from Long Term contract

$ 2,600,000.00

(revenue recognised)

  • Requirement 3

Requirement 3

Balance Sheet [Partial]

2018

2019

Current Assets:

Accounts receivables

$          200,000.00

$          646,000.00

Construction in progress

$       2,900,000.00

$          7,400,000.00

Less: Billings

$     (1,900,000.00)

$        (5,846,000.00)

Costs and profits in excess of billings

$       1,000,000.00

$      1,554,000.00

Current Liabilities:

Accounts Payable

$                            -  

$                            -  

  • Requirement 4

2018

2019

2020

Revenue

$                      3,053,528

$                     3,593,992

$                          3,352,480

Gross Profit (Loss)

$                         543,528

$                       (118,528)

$                                         -  

Working

2018

2019

2020

A

Contract Price

$             10,000,000.00

$             10,000,000.00

$                  10,000,000.00

B

Cost Incurred to Date

$                2,510,000.00

$               6,365,000.00

$                    9,575,000.00

C

Estimated cost yet to be incurred to complete the contract

$                5,710,000.00

$               3,210,000.00

$                                         -  

D = B+C

Total Cost

$                8,220,000.00

$               9,575,000.00

$                    9,575,000.00

E = (B/D) x 100

% of Completion

30.54%

66.48%

100.00%

F = A x E

Revenue to date

$                3,053,527.98

$               6,647,519.58

$                  10,000,000.00

G

Revenue of Previous year

$                                     -  

$               3,053,527.98

$                    6,647,519.58

H = F - G

Net Revenue this year

$                3,053,527.98

$               3,593,991.60

$                    3,352,480.42

I (=B)

Cost to date

$                2,510,000.00

$               6,365,000.00

$                    9,575,000.00

J

Cost to date of previous year

$                                     -  

$               2,510,000.00

$                    6,365,000.00

K = I - J

Net Cost for the year

$                2,510,000.00

$               3,855,000.00

$                    3,210,000.00

L = A - D

Estimated Gross Profit (Loss)

$                1,780,000.00

$                   425,000.00

$                        425,000.00

M

Gross Profit (Loss) to be recognised

$                   543,527.98

$                 (118,527.98)

$                                         -  


Related Solutions

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate Construction uses the completed contract method...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate Construction uses the completed contract method...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018. 2019 2020 Cost incurred during the year $2,624,000  $3,690,000  $2,074,600 Estimated costs to complete as of year-end 5,576,000   1,886,000 0 Billings during the year 2,200,000   4,114,000   3,686,000 Cash collections during the year 2,000,000   3,800,000   4,200,000 Westgate Construction uses the completed contract method of accounting for long-term construction contracts. Required: 1. Calculate the...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,610,000 $ 3,162,000 $ 2,230,800 Estimated costs to complete as of year-end 6,390,000 2,028,000 0 Billings during the year 2,100,000 3,672,000 4,228,000 Cash collections during the year 1,850,000 3,000,000 5,150,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,610,000 $ 3,162,000 $ 2,230,800 Estimated costs to complete as of year-end 6,390,000 2,028,000 0 Billings during the year 2,100,000 3,672,000 4,228,000 Cash collections during the year 1,850,000 3,000,000 5,150,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,640,000 $ 2,300,000 $ 2,926,000 Estimated costs to complete as of year-end 6,160,000 2,660,000 0 Billings during the year 2,080,000 2,860,000 5,060,000 Cash collections during the year 1,840,000 2,800,000 5,360,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 3,150,000 $ 2,475,000 Estimated costs to complete as of year-end 5,400,000 2,250,000 0 Billings during the year 2,150,000 3,100,000 4,750,000 Cash collections during the year 1,875,000 3,100,000 5,025,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,059,000 $ 2,627,000 $ 2,655,400 Estimated costs to complete as of year-end 5,041,000 2,414,000 0 Billings during the year 2,190,000 2,496,000 5,314,000 Cash collections during the year 1,895,000 2,400,000 5,705,000 Westgate recognizes revenue over time according to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT