In: Accounting
In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
2018 |
2019 |
2020 |
|||||||
Cost incurred during the year |
$ |
2,523,000 |
$ |
3,177,000 |
$ |
1,980,000 |
|||
Estimated costs to complete as of year-end |
6,177,000 |
1,800,000 |
0 |
||||||
Billings during the year |
2,070,000 |
3,630,000 |
4,300,000 |
||||||
Cash collections during the year |
1,835,000 |
3,400,000 |
4,765,000 |
||||||
Westgate recognizes revenue over time according to percentage of
completion.
Required:
1. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary
journal entries for the year 2018 (credit "Various accounts" for
construction costs incurred).
2-b. In the journal below, complete the necessary
journal entries for the year 2019 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2020 (credit "Various accounts" for
construction costs incurred).
3. Complete the information required below to
prepare a partial balance sheet for 2018 and 2019 showing any items
related to the contract.
4. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete
information.
2018 |
2019 |
2020 |
|||||||
Cost incurred during the year |
$ |
2,523,000 |
$ |
3,835,000 |
$ |
3,235,000 |
|||
Estimated costs to complete as of year-end |
6,177,000 |
3,135,000 |
0 |
||||||
5. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete
information.
2018 |
2019 |
2020 |
|||||||
Cost incurred during the year |
$ |
2,523,000 |
$ |
3,835,000 |
$ |
4,005,000 |
|||
Estimated costs to complete as of year-end |
6,177,000 |
4,170,000 |
0 |
||||||
Answer 1 | |||
Year | 2018 | 2019 | 2020 |
Cost incurred during the year | $ 2,523,000 | $ 3,177,000 | $ 1,980,000 |
Cumulative cost incurred at end of year | $ 2,523,000 | $ 5,700,000 | $ 7,680,000 |
Cumulative cost incurred at end of year | $ 2,523,000 | $ 5,700,000 | $ 7,680,000 |
Add: Estimated costs to complete as of year-end | $ 6,177,000 | $ 1,800,000 | $ 0 |
Total estimated cost | $ 8,700,000 | $ 7,500,000 | $ 7,680,000 |
Percentage of completion (cumulative cost incurred at end of year / Total estimated cost) | 29.00% | 76.00% | 100.00% |
Revenue recognized till the date (10000000 * percentage of completion) | $ 2,900,000 | $ 7,600,000 | $ 10,000,000 |
Less: Revenue recognized up to earlier year | $ 0 | $ 2,900,000 | $ 7,600,000 |
Revenue recognized in current year | $ 2,900,000 | $ 4,700,000 | $ 2,400,000 |
Revenue recognized in current year | $ 2,900,000 | $ 4,700,000 | $ 2,400,000 |
Less: cost incurred during the year | $ 2,523,000 | $ 3,177,000 | $ 1,980,000 |
Gross Profit (Loss) | $ 377,000 | $ 1,523,000 | $ 420,000 |
Date | General Journal | Debit | Credit |
2018 | Construction in progress | 2,523,000 | |
Various Accounts | 2,523,000 | ||
(To record cost incurred in Progress.) | |||
2018 | Accounts receivable | 2,070,000 | |
Billings on construction contract | 2,070,000 | ||
(To record Billings to Customer.) | |||
2018 | Cash | 1,835,000 | |
Accounts receivable | 1,835,000 | ||
(To record cash collected from customer.) | |||
2018 | Construction in progress | 377,000 | |
Cost of construction | 2,523,000 | ||
Construction Revenue | 2,900,000 | ||
(To record recognize Revenue.) | |||
2019 | Construction in progress | 3,177,000 | |
Various Accounts | 3,177,000 | ||
(To record cost incurred in Progress.) | |||
2019 | Accounts receivable | 3,630,000 | |
Billings on construction contract | 3,630,000 | ||
(To record Billings to Customer.) | |||
2019 | Cash | 3,400,000 | |
Accounts receivable | 3,400,000 | ||
(To record cash collected from customer.) | |||
2019 | Construction in progress | 1,523,000 | |
Cost of construction | 3,177,000 | ||
Construction Revenue | 4,700,000 | ||
(To record recognize Revenue.) | |||
2020 | Construction in progress | 1,980,000 | |
Various Accounts | 1,980,000 | ||
(To record cost incurred in Progress.) | |||
2020 | Accounts receivable | 4,300,000 | |
Billings on construction contract | 4,300,000 | ||
(To record Billings to Customer.) | |||
2020 | Cash | 4,765,000 | |
Accounts receivable | 4,765,000 | ||
(To record cash collected from customer.) | |||
2020 | Construction in progress | 420,000 | |
Cost of construction | 1,980,000 | ||
Construction Revenue | 2,400,000 | ||
(To record recognize Revenue.) | |||
2020 | Billings on construction contract | 10,000,000 | |
Construction in progress | 10,000,000 | ||
(To record completion of contract.) |
Calculation | 2018 | 2019 | |
Beginning Account receivable | 235,000 | ||
Billings | 2,070,000 | 3,630,000 | |
Less: Collections | 1,835,000 | 3,400,000 | |
Account receivable | 235,000 | 465,000 |
Partial Balance sheet | 2018 | 2019 | ||
Current assets | ||||
Account receivable | 235,000 | 465,000 | ||
Construction in progress | $ 2,900,000 | $ 7,600,000 | ||
Less: Billings | 2,070,000 | 5,700,000 | ||
Cost in excess of Billings | 830,000 | 1,900,000 |
Answer 4 | |||
Year | 2018 | 2019 | 2020 |
Cost incurred during the year | $ 2,523,000 | $ 3,835,000 | $ 3,235,000 |
Cumulative cost incurred at end of year | $ 2,523,000 | $ 6,358,000 | $ 9,593,000 |
Cumulative cost incurred at end of year | $ 2,523,000 | $ 6,358,000 | $ 9,593,000 |
Add: Estimated costs to complete as of year-end | $ 6,177,000 | $ 3,135,000 | $ 0 |
Total estimated cost | $ 8,700,000 | $ 9,493,000 | $ 9,593,000 |
Percentage of completion (cumulative cost incurred at end of year / Total estimated cost) | 29.00% | 66.97567% | 100.00% |
Revenue recognized till the date (10000000 * percentage of completion) | $ 2,900,000 | $ 6,697,567 | $ 10,000,000 |
Less: Revenue recognized up to earlier year | $ 0 | $ 2,900,000 | $ 6,697,567 |
Revenue recognized in current year | $ 2,900,000 | $ 3,797,567 | $ 3,302,433 |
Revenue recognized in current year | $ 2,900,000 | $ 3,797,567 | $ 3,302,433 |
Less: cost incurred during the year | $ 2,523,000 | $ 3,835,000 | $ 3,235,000 |
Gross Profit (Loss) | $ 377,000 | $ (37,433) | $ 67,433 |
Your Answer | |||
Year | 2018 | 2019 | 2020 |
Revenue | $ 2,900,000 | $ 3,797,567 | $ 3,302,433 |
Gross Profit (Loss) | $ 377,000 | $ (37,433) | $ 67,433 |
Answer 5 | |||
Year | 2018 | 2019 | 2020 |
Cost incurred during the year | $ 2,523,000 | $ 3,835,000 | $ 4,005,000 |
Cumulative cost incurred at end of year | $ 2,523,000 | $ 6,358,000 | $ 10,363,000 |
Cumulative cost incurred at end of year | $ 2,523,000 | $ 6,358,000 | $ 10,363,000 |
Add: Estimated costs to complete as of year-end | $ 6,177,000 | $ 4,170,000 | $ 0 |
Total estimated cost | $ 8,700,000 | $ 10,528,000 | $ 10,363,000 |
Percentage of completion (cumulative cost incurred at end of year / Total estimated cost) | 29.00% | 60.39134% | 100.00% |
Revenue recognized till the date (10000000 * percentage of completion) | $ 2,900,000 | $ 6,039,134 | $ 10,000,000 |
Less: Revenue recognized up to earlier year | $ 0 | $ 2,900,000 | $ 6,039,134 |
Revenue recognized in current year | $ 2,900,000 | $ 3,139,134 | $ 3,960,866 |
Revenue recognized in current year | $ 2,900,000 | $ 3,139,134 | $ 3,960,866 |
Less: cost incurred during the year | $ 2,523,000 | $ 3,835,000 | $ 4,005,000 |
Less: Provision For Loss of Project | $ 528,000 | ||
Add: Loss settled from Provision | $ 528,000 | ||
Gross Profit (Loss) | $ 377,000 | $ (1,223,866) | $ 483,866 |
Your Answer | |||
Year | 2018 | 2019 | 2020 |
Revenue | $ 2,900,000 | $ 3,139,134 | $ 3,960,866 |
Gross Profit (Loss) | $ 377,000 | $ (1,223,866) | $ 483,866 |
Provision For Loss of Project, When Estimated Project cost is more than Contract Price then Difference between them Provision should be made. And for future Amount of provision should be used for write of loss. For 2019, Provision = estimated cost less Contract revenue = 10,528,000 - 10,000,000 = 528,000 |