Question

In: Accounting

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:

2018

2019

2020

Cost incurred during the year

$

2,523,000

$

3,177,000

$

1,980,000

Estimated costs to complete as of year-end

6,177,000

1,800,000

0

Billings during the year

2,070,000

3,630,000

4,300,000

Cash collections during the year

1,835,000

3,400,000

4,765,000


Westgate recognizes revenue over time according to percentage of completion.

Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2019 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2020 (credit "Various accounts" for construction costs incurred).
3. Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract.
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

2018

2019

2020

Cost incurred during the year

$

2,523,000

$

3,835,000

$

3,235,000

Estimated costs to complete as of year-end

6,177,000

3,135,000

0


5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

2018

2019

2020

Cost incurred during the year

$

2,523,000

$

3,835,000

$

4,005,000

Estimated costs to complete as of year-end

6,177,000

4,170,000

0

Solutions

Expert Solution

Answer 1
Year 2018 2019 2020
Cost incurred during the year $          2,523,000 $          3,177,000 $          1,980,000
Cumulative cost incurred at end of year $          2,523,000 $          5,700,000 $          7,680,000
Cumulative cost incurred at end of year $          2,523,000 $          5,700,000 $          7,680,000
Add: Estimated costs to complete as of year-end $          6,177,000 $          1,800,000 $                           0
Total estimated cost $          8,700,000 $          7,500,000 $          7,680,000
Percentage of completion (cumulative cost incurred at end of year / Total estimated cost) 29.00% 76.00% 100.00%
Revenue recognized till the date (10000000 * percentage of completion) $          2,900,000 $          7,600,000 $        10,000,000
Less: Revenue recognized up to earlier year $                           0 $          2,900,000 $          7,600,000
Revenue recognized in current year $          2,900,000 $          4,700,000 $          2,400,000
Revenue recognized in current year $          2,900,000 $          4,700,000 $          2,400,000
Less: cost incurred during the year $          2,523,000 $          3,177,000 $          1,980,000
Gross Profit (Loss) $              377,000 $          1,523,000 $              420,000
Date General Journal Debit Credit
2018 Construction in progress      2,523,000
Various Accounts           2,523,000
(To record cost incurred in Progress.)
2018 Accounts receivable      2,070,000
Billings on construction contract           2,070,000
(To record Billings to Customer.)
2018 Cash      1,835,000
Accounts receivable           1,835,000
(To record cash collected from customer.)
2018 Construction in progress          377,000
Cost of construction      2,523,000
Construction Revenue           2,900,000
(To record recognize Revenue.)
2019 Construction in progress      3,177,000
Various Accounts           3,177,000
(To record cost incurred in Progress.)
2019 Accounts receivable      3,630,000
Billings on construction contract           3,630,000
(To record Billings to Customer.)
2019 Cash      3,400,000
Accounts receivable           3,400,000
(To record cash collected from customer.)
2019 Construction in progress      1,523,000
Cost of construction      3,177,000
Construction Revenue           4,700,000
(To record recognize Revenue.)
2020 Construction in progress      1,980,000
Various Accounts           1,980,000
(To record cost incurred in Progress.)
2020 Accounts receivable      4,300,000
Billings on construction contract           4,300,000
(To record Billings to Customer.)
2020 Cash      4,765,000
Accounts receivable           4,765,000
(To record cash collected from customer.)
2020 Construction in progress          420,000
Cost of construction      1,980,000
Construction Revenue           2,400,000
(To record recognize Revenue.)
2020 Billings on construction contract    10,000,000
Construction in progress         10,000,000
(To record completion of contract.)
Calculation 2018 2019
Beginning Account receivable           235,000
Billings      2,070,000        3,630,000
Less: Collections      1,835,000        3,400,000
Account receivable          235,000           465,000
Partial Balance sheet 2018 2019
Current assets
Account receivable               235,000            465,000
Construction in progress $ 2,900,000 $   7,600,000
Less: Billings      2,070,000        5,700,000
Cost in excess of Billings               830,000        1,900,000
Answer 4
Year 2018 2019 2020
Cost incurred during the year $          2,523,000 $          3,835,000 $          3,235,000
Cumulative cost incurred at end of year $          2,523,000 $          6,358,000 $          9,593,000
Cumulative cost incurred at end of year $          2,523,000 $          6,358,000 $          9,593,000
Add: Estimated costs to complete as of year-end $          6,177,000 $          3,135,000 $                           0
Total estimated cost $          8,700,000 $          9,493,000 $          9,593,000
Percentage of completion (cumulative cost incurred at end of year / Total estimated cost) 29.00% 66.97567% 100.00%
Revenue recognized till the date (10000000 * percentage of completion) $          2,900,000 $          6,697,567 $        10,000,000
Less: Revenue recognized up to earlier year $                           0 $          2,900,000 $          6,697,567
Revenue recognized in current year $          2,900,000 $          3,797,567 $          3,302,433
Revenue recognized in current year $          2,900,000 $          3,797,567 $          3,302,433
Less: cost incurred during the year $          2,523,000 $          3,835,000 $          3,235,000
Gross Profit (Loss) $              377,000 $              (37,433) $                67,433
Your Answer
Year 2018 2019 2020
Revenue $          2,900,000 $          3,797,567 $          3,302,433
Gross Profit (Loss) $              377,000 $              (37,433) $                67,433
Answer 5
Year 2018 2019 2020
Cost incurred during the year $          2,523,000 $          3,835,000 $          4,005,000
Cumulative cost incurred at end of year $          2,523,000 $          6,358,000 $        10,363,000
Cumulative cost incurred at end of year $          2,523,000 $          6,358,000 $        10,363,000
Add: Estimated costs to complete as of year-end $          6,177,000 $          4,170,000 $                           0
Total estimated cost $          8,700,000 $        10,528,000 $        10,363,000
Percentage of completion (cumulative cost incurred at end of year / Total estimated cost) 29.00% 60.39134% 100.00%
Revenue recognized till the date (10000000 * percentage of completion) $          2,900,000 $          6,039,134 $        10,000,000
Less: Revenue recognized up to earlier year $                           0 $          2,900,000 $          6,039,134
Revenue recognized in current year $          2,900,000 $          3,139,134 $          3,960,866
Revenue recognized in current year $          2,900,000 $          3,139,134 $          3,960,866
Less: cost incurred during the year $          2,523,000 $          3,835,000 $          4,005,000
Less: Provision For Loss of Project $              528,000
Add: Loss settled from Provision $              528,000
Gross Profit (Loss) $              377,000 $        (1,223,866) $              483,866
Your Answer
Year 2018 2019 2020
Revenue $          2,900,000 $          3,139,134 $          3,960,866
Gross Profit (Loss) $              377,000 $        (1,223,866) $              483,866
Provision For Loss of Project, When Estimated Project cost is more than Contract Price then Difference between them Provision should be made. And for future Amount of provision should be used for write of loss. For 2019, Provision = estimated cost less Contract revenue = 10,528,000 - 10,000,000 = 528,000

Related Solutions

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate Construction uses the completed contract method...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate Construction uses the completed contract method...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018. 2019 2020 Cost incurred during the year $2,624,000  $3,690,000  $2,074,600 Estimated costs to complete as of year-end 5,576,000   1,886,000 0 Billings during the year 2,200,000   4,114,000   3,686,000 Cash collections during the year 2,000,000   3,800,000   4,200,000 Westgate Construction uses the completed contract method of accounting for long-term construction contracts. Required: 1. Calculate the...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,610,000 $ 3,162,000 $ 2,230,800 Estimated costs to complete as of year-end 6,390,000 2,028,000 0 Billings during the year 2,100,000 3,672,000 4,228,000 Cash collections during the year 1,850,000 3,000,000 5,150,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,610,000 $ 3,162,000 $ 2,230,800 Estimated costs to complete as of year-end 6,390,000 2,028,000 0 Billings during the year 2,100,000 3,672,000 4,228,000 Cash collections during the year 1,850,000 3,000,000 5,150,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,640,000 $ 2,300,000 $ 2,926,000 Estimated costs to complete as of year-end 6,160,000 2,660,000 0 Billings during the year 2,080,000 2,860,000 5,060,000 Cash collections during the year 1,840,000 2,800,000 5,360,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 3,150,000 $ 2,475,000 Estimated costs to complete as of year-end 5,400,000 2,250,000 0 Billings during the year 2,150,000 3,100,000 4,750,000 Cash collections during the year 1,875,000 3,100,000 5,025,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,059,000 $ 2,627,000 $ 2,655,400 Estimated costs to complete as of year-end 5,041,000 2,414,000 0 Billings during the year 2,190,000 2,496,000 5,314,000 Cash collections during the year 1,895,000 2,400,000 5,705,000 Westgate recognizes revenue over time according to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT