Question

In: Finance

Determine the net present value for a project that costs $229,000 and would yield after-tax cash...

Determine the net present value for a project that costs $229,000 and would yield after-tax cash flows of $21,000 per year for the first 14 years, $29,000 per year for the next 18 years, and $42,000 per year for the following 12 years. Your firm's cost of capital is 10.00%.

Question 16 options:

$2,488.65

$1,345.00

$1,588.16

$1,885.34

$2,714.89

Solutions

Expert Solution

Ans $1,885.34

the net present value for a project that costs $229,000 and would yield after-tax cash flows of $21,000 per year for the first 14 years, $29,000 per year for the next 18 years, and $42,000 per year for the following 12 years. Your firm's cost of capital is 10.00% is $1,885.34


Related Solutions

33. Determine the net present value for a project that costs $286,000 and would yield after-tax...
33. Determine the net present value for a project that costs $286,000 and would yield after-tax cash flows of $21,000 per year for the first 13 years, $29,000 per year for the next 12 years, and $42,000 per year for the following 12 years. Your firm's cost of capital is 8.00%.
what is the net present value of a project with the following after tax cash flows...
what is the net present value of a project with the following after tax cash flows using a discount rate of 10% year 0 45,000 year 1 14,000 year 2 14,000 year 3 10,000 year 4 10,000 year 5 8,000 would you accept the project? ehat is payback period? what is the profitbility index?
Determine the payback period in years for a project that costs $45,000 and would yield after-tax...
Determine the payback period in years for a project that costs $45,000 and would yield after-tax cash flows of $9,000 the first year, $11,000 the second year, $14,000 the third year, $16,000 the fourth year, $20,000 the fifth year, and $26,000 the sixth year.
What is the net present value of Project X if it has the following after tax...
What is the net present value of Project X if it has the following after tax cash flows? The interest rate is 6%              End of year 1 = ($300)        End of year 2 = $500 End of year 3 = $900 Please show equation that is easy to understand, able to put into TI-84.
What is the net present value of a capital investment project that has the following, after-tax...
What is the net present value of a capital investment project that has the following, after-tax cash flows for a company that requires a 14% rate of return on the project? Time- 0 1 2 3 Cash Flow- 3,800 500 1,700 7,200
Develop a spreadsheet to determine the net present value or present worth of the following project:...
Develop a spreadsheet to determine the net present value or present worth of the following project: Bonus Depreciation: 0% Investment: 140,000 Revenue/Savings: 25,000 Incremental Expense/Cost: 5,000 Salvage Value: 25,000 Project Life: 10 years MACRS Schedule: 7 years Tax Rate: 25% MARR: 12% Inflation: 3% Is this a good investment to make? Rework the problem with Bonus Depreciation of 50% and 100% Determine the internal rate of return for the project in the previous problem with all three levels of Bonus...
When a project entails significant social costs, the private net present value—the value of the project...
When a project entails significant social costs, the private net present value—the value of the project to its sponsor—exceeds the true (societal) net present value, namely the combined value to all the affected constituencies inclusive of the social costs. Should the externalities be taken into account when evaluating such a project? In your response, identify stakeholders’ roles, legalities, guidelines, policies or processes that might be considered/required to ensure a sponsor’s compliance or curb undesirable behavior? (See Finnerty Chapter 6) initial...
Forecast the Net Present Value of a project given the cash inflows and cash outflows of...
Forecast the Net Present Value of a project given the cash inflows and cash outflows of the project. Then use this information to simulate the uncertainty of forecasting a project’s NPV. A likely scenario might be: Project A is a multi-year project; it begins on January 1, 2011 and is scheduled to end on December 31, 2014 (fixed cost is $215,000) The cash outflow for Project A is estimated at $100,000 at the beginning in the first year of the...
1. a) What is the net present value of a project that has upfront costs of...
1. a) What is the net present value of a project that has upfront costs of $5 million and pays end of the year cash flows of $1 million in one year, $2 million in two years, and $3 million in three years if the annual discount rate for the project is 3 percent? Show how much money you would have at the end of three years if you bought the project and what you would have instead if you...
What is the net present value of a project that has an initial cash outflow of...
What is the net present value of a project that has an initial cash outflow of $-13,000, at time 0, and the following cash flows for years 1-4? The required return is 10.0%. DO NOT USE DOLLAR SIGNS OR COMMAS IN YOUR ANSWER. ENTER YOUR ANSWER TO THE NEAREST DOLLAR (e.g. 1250). Year Cash Flows 1 $3,950 2 $3,750 3 $5,900 4 $6,400
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT