In: Accounting
Forecast the Net Present Value of a project given the cash inflows and cash outflows of the project. Then use this information to simulate the uncertainty of forecasting a project’s NPV.
A likely scenario might be:
Given this information we can determine the NPV of Project A using a simple Excel spreadsheet. We can then use Crystal Ball to simulate the uncertainty associated with forecasting the NPV of Project A. Table 1 is an example of the spreadsheet, or Discounted Cash Flow model, developed to calculate Project A’s NPV. The Excel spreadsheet (Figure 1) contains the actual data and formulas used for this exercise.
| 
 Project A  | 
||||||
| 
 Year  | 
 Inflow  | 
 Outflow  | 
 Net  | 
 Discount  | 
 Net  | 
 Inflation  | 
| 
 *2011  | 
 $0  | 
 $100,000  | 
 0.02  | 
|||
| 
 2011  | 
 $0  | 
 $50,000  | 
 0.02  | 
|||
| 
 2012  | 
 $25,000  | 
 $50,000  | 
 0.02  | 
|||
| 
 2013  | 
 $120,000  | 
 $0  | 
 0.02  | 
|||
| 
 2014  | 
 $200,000  | 
 $15,000  | 
 0.02  | 
|||
| 
 Total  | 
||||||
Table 1 – Project A Cash Flow Analysis
(a). Complete Table 1 to calculate Project A’s NPV. The net cash flow of Project A is calculated by taking the total of all years’ net flow, and when discounted at the rate of 12% (required rate of return for project selection) plus the annual inflation rate of 2%, the net present value of the project’s cash flow can be estimated. So, at first glance, the project would seem to be a good candidate for selection. But there are uncertainties to this scenario. What if Project A does not generate the cash inflows estimated here, or at the time the inflows are expected? Perhaps the annual inflation rate is 3% rather than 2%. We can use Crystal Ball to simulate the risk, or uncertainty, involved in using NPV for project selection.
| Inflation rate 2% | ||||||||
| Calculation of cost capital = 1+r = (1+0.12)(1+0.02) >>> r = 14.24% | ||||||||
| Year | Inflows | Outflows | Net flow | Discounted Factor 14.24% | Net Present Value | Inflation rate | ||
| 2011 | $ - | $ 1,00,000.00 | $ -1,00,000.00 | 1.00 | -1,00,000.00 | 0.02 | ||
| 2011 | $ - | $ 50,000.00 | $ -50,000.00 | 1.00 | -50,000.00 | 0.02 | ||
| 2012 | $ 25,000.00 | $ 50,000.00 | $ -25,000.00 | 0.88 | -21,883.75 | 0.02 | ||
| 2013 | $ 1,20,000.00 | $ - | $ 1,20,000.00 | 0.77 | 91,948.54 | 0.02 | ||
| 2014 | $ 2,00,000.00 | $ 15,000.00 | $ 1,85,000.00 | 0.67 | 1,24,084.39 | 0.02 | ||
| NPV | 44,149.18 | |||||||
| Inflation rate 3% | ||||||||
| Calculation of cost capital = 1+r = (1+0.12)(1+0.03) >>> r = 15.36% | ||||||||
| Year | Inflows | Outflows | Net flow | Discounted Factor 15.36% | Net Present Value | Inflation rate | ||
| 2011 | $ - | $ 1,00,000.00 | $ -1,00,000.00 | 1.00 | -1,00,000.00 | 0.03 | ||
| 2011 | $ - | $ 50,000.00 | $ -50,000.00 | 1.00 | -50,000.00 | 0.03 | ||
| 2012 | $ 25,000.00 | $ 50,000.00 | $ -25,000.00 | 0.87 | -21,671.29 | 0.03 | ||
| 2013 | $ 1,20,000.00 | $ - | $ 1,20,000.00 | 0.75 | 90,171.80 | 0.03 | ||
| 2014 | $ 2,00,000.00 | $ 15,000.00 | $ 1,85,000.00 | 0.65 | 1,20,505.26 | 0.03 | ||
| NPV | 39,005.77 | |||||||