Question

In: Finance

Jojo's Bizzare is taking on two projects. The cost of project A is $ 70,000 and...

Jojo's Bizzare is taking on two projects. The cost of project A is $ 70,000 and the cost of B is $ 140,000. The firm’s cost of capital is 12% per year. After-tax cash flows are estimated to be $ 10,000 per year forever for project A. After-tax cash flow at time 1 will be $12,000 for the project B. However, the future cash flows from Project B are expected to increase by 3% per year forever. Compute NPV and IRR for both projects. Which project should Jojo's undertake? At what growth rate of future cash flows for the project B would Jojo's be indifferent? (NPVA = NPVB )? The cost of capital for both projects is still 12% per year.

Solutions

Expert Solution

Computation of NPV and IRR for Project A:

NPV = PV of future cash flow – Initial investment

      = Annual cash flow/Rate of return – Initial investment

NPVA = ($ 10,000/0.12) - $ 70,000

       = $ 83,333.33333 - $ 70,000

        = $ 13,333.33333 or $ 13,333.33

NPV at a discount rate equals to IRR is zero.

0 = $ 10,000/IRR – $ 70,000

$ 70,000 = $ 10,000/IRR

IRR = $ 10,000/$ 70,000 = 0.142857143 or 14.29 %

NPV of Project A is $ 13,333.33 and IRR is 14.29 %

Computation of NPV and IRR for Project B:

NPV = PV of future cash flow – Initial investment

      = [Annual cash flow/ (Rate of return- growth rate)] – Initial investment

NPVB = $ 12,000/ (0.12-0.03) - $ 140,000

       = ($ 12,000/ 0.09) - $ 140,000

        = $ 133,333.3333 - $ 140,000

       = - $ 6,666.666667 or - $ 6,666.66

NPV at a discount rate equals to IRR is zero.

0 = $ 12,000/(IRR-0.03) – $ 140,000

$ 140,000 = $ 12,000/(IRR-0.03)

IRR – 0.03 = $ 12,000/$ 140,000 = 0.085714286

IRR = 0.085714286 + 0.03 = 0.115714286 or 11.57 %

NPV of Project B is - $ 6,666.66 and IRR is 11.57 %

Jojo should undertake Project A as it has positive NPV and IRR higher than required rate of return.

NPV A = NPV B

NPVB = $ 13,333.33

$ 13,333.33 = $ 12,000/ (0.12 - g) - $ 140,000

$ 12,000/ (0.12 - g) = $ 140,000 + $ 13,333.33

                                = $ 153,333.33

0.12 – g = $ 12,000/$ 153,333.33

             = 0.07826087126654

g = 0.12 - 0.07826087126654 = 0.04173912873346 or 4.1739 %

A growth rate of 4.1739 % for future cash flow for Project B will Jojo’s be indifferent.


Related Solutions

You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $10,000 for 10 years. Project B costs $80,000 and generates cash flows of $2,000 for six years and then cash flows of $28,000 for four years. Report rates in percentage form to two decimal places i.e. 10.03% not 10% At what discount rate would make you indifferent between choosing one project or another? What is the highest discount rate in which...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $12,000 for 10 years. Project B costs $60,000 and generates cash flows of $2,000 for six years and then cash flows of $29,000 for four years. Which project would you accept if your discount rate was 10%? Which project would you accept if your discount rate was 5%?
You are considering two mutually-exclusive projects: Project A and Project B. The initial cash outlay (cost)...
You are considering two mutually-exclusive projects: Project A and Project B. The initial cash outlay (cost) associated with Project A is $60,000, whereas the initial cash outlay associated with Project B is $80,000. The required rate of return for both projects is 10%. The expected annual free cash flows from each project are as follows: Year Project A Project B 0 - 60,000 -80,000 1 13,000 15,000 2 13,000 15,000 3 13,000 15,000 4 13,000 15,000 5 13,000 15,000 6...
Consider the following two investment projects: Project A: it has an initial cost of 20,000 euros...
Consider the following two investment projects: Project A: it has an initial cost of 20,000 euros and requires additional investments of 5,000 euros at the end of the first year and 15,000 euros at the end of the second. This project is two years old and generates 20,000 euros per year in income. Project B: it has an initial cost of 20,000 euros and requires an additional investment of 10,000 euros at the end of the first year. This project...
Elemental is considering another project which requires new equipment at a cost of $70,000. The equipment...
Elemental is considering another project which requires new equipment at a cost of $70,000. The equipment has a 3 year tax life and will be fully depreciated by the straight-line method over 3 years. When the project closes down at the end of the third year, it is expected to sell for $5000 before taxes. The project will require new working capital of $10000, and is expected to be fully recovered at the end of the project's life. Project revenues...
Kennedy Air is evaluating a new project. The equipment will cost $70,000 plus $8,000 to install....
Kennedy Air is evaluating a new project. The equipment will cost $70,000 plus $8,000 to install. It will be depreciated using the MACRS 3-year class. The project would require an increase in inventories of $5,000 and an increase in A/P of $3,000. The firm’s yearly revenues would increase by $70,000 but would also increase operating costs by $20,000. The project is expected to last 3 years and the equipment can then be sold for $12,000. The firm’s tax rate is...
A company is evaluating two equal risky projects, S & L. Project S cost $2,050 and...
A company is evaluating two equal risky projects, S & L. Project S cost $2,050 and have cash inflows of $750, $760, $770, and $780 in years 1,2,3, and 4, respectively. Project L, costs $4,300 and have cash inflows of $1,500, $1,518, $1,536, and $1,554 in years 1,2,3, and 4 , respectively. The cost of Capital for both projects is 11%. What is the NPV and IRR of project S? What is the NPV and IRR for Project L? Is...
Two new software projects are proposed to a young, start-up company. The Alpha project will cost...
Two new software projects are proposed to a young, start-up company. The Alpha project will cost $150,000 to develop and is expected to have annual net cash flow of $40,000. The Beta project will cost $200,000 to develop and is expected to have annual net cash flow of $50,000. The company is very concerned about their cash flow. a.) Using the payback period, which project is better from a cash flow standpoint? Why? b.) If the project will take 10...
You are considering two investment projects each having the same cost. Each project is facing the...
You are considering two investment projects each having the same cost. Each project is facing the following events, probabilities and net profits: ALTERNATIVES:    a1: Newspaper a2: Pamphlet EVENTS: e1 e2 e3 e1 e2 e3 NET PROFITS: 4000 6000 9000 3000 7000 8000 PROBABILITIE: .25 .50 .25 .30 .50 .20 1. Construct a decision tree and show which project you would chose by using the expected value method ()? 2. Calculate the coefficient of variation of each project, and determine...
There are two projects: Project A and Project B a. Project A: CF0 = -6000; CF1-5...
There are two projects: Project A and Project B a. Project A: CF0 = -6000; CF1-5 = 2000; I/YR = 14. Calculate NPV, IRR, MIRR, Payback period, and discounted payback period for Project A. Project B: CF0 = -18000; CF1-5 = 5600; I/YR = 14. Calculate NPV, IRR, MIRR, Payback period, and discounted payback period for Project B. b. If the two projects are independent, which project(s) would be accepted? c. If the two projects are mutually exclusive, which project...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT