Question

In: Finance

A project has the following cash flows: Year Cash Flows 0 −$127,800 1 47,000 2 63,800...

A project has the following cash flows: Year Cash Flows 0 −$127,800 1 47,000 2 63,800 3 51,600 4 28,100 The required return is 8.3 percent. What is the profitability index for this project?

Solutions

Expert Solution

Ans 1.24

Year Project Cash Flows (i) DF@ 8.3% DF@ 8.3% (ii) PV of Project B( (i) * (ii) )
1 47000 1/((1+8.3%)^1) 0.923                     43,397.97
2 63800 1/((1+8.3%)^2) 0.853                     54,395.60
3 51600 1/((1+8.3%)^3) 0.787                     40,622.28
4 28100 1/((1+8.3%)^4) 0.727                     20,426.43
NPV                  1,58,842.28
Total of PV of Cash Inflows 158842.28
Cash Outflows 127800
Profitability Index = 1.24
Present value of cash Inflow / Initial Investment (Cash Outflows) (158842.28 / 127800)

Related Solutions

A project has the following cash flows: Year Cash Flow 0 $ 47,000 1 – 26,000...
A project has the following cash flows: Year Cash Flow 0 $ 47,000 1 – 26,000 2 – 37,000 What is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)   IRR % What is the NPV of this project, if the required return is 12 percent? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2...
Solo Corp. is evaluating a project with the following cash flows: Year Cash flow 0 -47,000...
Solo Corp. is evaluating a project with the following cash flows: Year Cash flow 0 -47,000 1 16900 2 20,300 3 25,800 4 19,600 5 -9,500 The company uses an interest rate of 10 percent on all of its projects.   a. Calculate the MIRR of the project using the discounting approach method. (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. Calculate the MIRR of the project using the...
A project has the following cash flows : Year Cash Flows 0 −$12,000 1 5,290 2...
A project has the following cash flows : Year Cash Flows 0 −$12,000 1 5,290 2 7,630 3 5,040 4 −1,580 Assuming the appropriate interest rate is 10 percent, what is the MIRR for this project using the discounting approach? 19.21% 15.23% 13.96% 11.63% 17.77%
A project has the following cash flows : Year Cash Flows 0 −$11,700 1 5,110 2...
A project has the following cash flows : Year Cash Flows 0 −$11,700 1 5,110 2 7,360 3 4,800 4 −1,640 Assuming the appropriate interest rate is 7 percent, what is the MIRR for this project using the discounting approach?
1) A project has the following cash flows: Year 0 -$22,500, Year 1 $12,650, Year 2...
1) A project has the following cash flows: Year 0 -$22,500, Year 1 $12,650, Year 2 $10,900, and Year 3 $6,500. What is the IRR of the project? Please round your answer to two decimal places. 2) Following question 1, suppose the cost of capital is 15%. Would you accept or reject the project according to the IRR criterion? Accept or Reject 3) Following questions 1 and 2, which of the following statements about the IRR rule is false? -...
A project has the following cash flows: Year Cash Flow 0 –$ 16,100 1 6,800 2...
A project has the following cash flows: Year Cash Flow 0 –$ 16,100 1 6,800 2 8,100 3 6,600 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) NPV $ What is the NPV at a discount rate of 11 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV $ What is the NPV...
A project has the following cash flows: Year Cash Flow 0 $ 73,000 1 –54,000 2...
A project has the following cash flows: Year Cash Flow 0 $ 73,000 1 –54,000 2 –27,600 What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Internal rate of return             % What is the NPV of this project if the required return is 5 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round...
A project has the following cash flows:    Year Cash Flow 0 $64,100 1 –30,100 2...
A project has the following cash flows:    Year Cash Flow 0 $64,100 1 –30,100 2 –48,100    a. What is the IRR for this project?    b. What is the NPV of this project, if the required return is 11.5 percent?    c. NPV at 0 percent?    d. NPV at 23 percent?
A project has the following cash flows: Year Cash Flow 0 –$ 15,600 1 6,300 2...
A project has the following cash flows: Year Cash Flow 0 –$ 15,600 1 6,300 2 7,600 3 6,100     What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)      NPV $       What is the NPV at a discount rate of 9 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)      NPV $   ...
A project has the following cash flows. What is the payback period? Year 0 1 2...
A project has the following cash flows. What is the payback period? Year 0 1 2 3 4 cash flow -$14500 $2200 $4800   $6500 $7500 A project has the following cash flows. What is the internal rate of return? Year 0 1 2 3 Cash flows -$89300 $32900 $64200 $5800 A project has the following cash flows. What is the payback period? Year 0 1 2 3 4 Cash flow -$28000 $11600 $11600 $6500 $6500 And how to solve this...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT