Question

In: Finance

1) A project has the following cash flows: Year 0 -$22,500, Year 1 $12,650, Year 2...

1) A project has the following cash flows:

Year 0 -$22,500, Year 1 $12,650, Year 2 $10,900, and Year 3 $6,500. What is the IRR of the project? Please round your answer to two decimal places.

2) Following question 1, suppose the cost of capital is 15%. Would you accept or reject the project according to the IRR criterion? Accept or Reject

3) Following questions 1 and 2, which of the following statements about the IRR rule is false?

- The IRR of the project would be higher if the cash flow in year 3 is increased to $7,500.

- The IRR of the project will remain the same as in question 1 even if the cost of capital is increased to 20%.

- The investment decision by the IRR rule will remain unchanged even if the cost of capital is increased to 20%.

- Both (B) and (C) are false.

4) OpenSeas Inc., is evaluating the purchase of a new cruise ship. The ship would cost $400 million today. OpenSeas expects annual cash flows from the new ship to be $70 million and these cash flows will last forever. The cost of capital is 16%. What is the IRR of the new cruise ship? Answer in unit of %

Solutions

Expert Solution

1) IRR of the Project:

Particulars Year 0 Year 1 Year 2 Year 3 NPV in $
Project Cashflows (22500) 12650 10900 6500 ---
NPV @ 12% (22500) 11294.64 8689.4 4626.57 2110.6
NPV @ 18% (R1) (22500) 10720.34 7828.21 3956.1 4.65
NPV @ 18.5% (R2) (22500) 10675.1 7762.29 3906.23 (156.37)

IRR= R1 + {NPV1 * (R2-R1)} / {NPV1-NPV2}

IRR= 18 + {4.65 * (18.5-18)} / {4.65- (156.37)}

IRR= 18.0144% or 18.01 % appx.

2) Higher IRR of the project represent the greater the amount through which it exceeds the expection of the shareholders (CoC). Higher the IRR means higher cash flows to the company.

Here Cost of capital is 15% and IRR is 18.01%. Hence the project should be accepted. It will add up the cash flows of company by 3.01% (18.01% - 15%).

3) False IRR Rule is-

<The investment decision by the IRR rule will remain unchanged even if the cost of capital is increased to 20%.>

Rational: Companies use IRR to evalute particular project's profitability and cash flows as compared to its cost of capital. If Cost of capital exceeds IRR of the project; then the project has to be re-evaluated and preferably rejected.

4) IRR is 17.5% for OpenSeas Inc. of a new cruise ship:

Particulars Year 0 Year 'n' NPV in $
Project Cashflows (400) 70 --
NPV @ 17% (400) 411.76 11.76
NPV @ 17.5% (400) 400 0

Related Solutions

A project has the following cash flows : Year Cash Flows 0 −$12,000 1 5,290 2...
A project has the following cash flows : Year Cash Flows 0 −$12,000 1 5,290 2 7,630 3 5,040 4 −1,580 Assuming the appropriate interest rate is 10 percent, what is the MIRR for this project using the discounting approach? 19.21% 15.23% 13.96% 11.63% 17.77%
A project has the following cash flows : Year Cash Flows 0 −$11,700 1 5,110 2...
A project has the following cash flows : Year Cash Flows 0 −$11,700 1 5,110 2 7,360 3 4,800 4 −1,640 Assuming the appropriate interest rate is 7 percent, what is the MIRR for this project using the discounting approach?
A project has the following cash flows: Year Cash Flows 0 −$127,800 1 47,000 2 63,800...
A project has the following cash flows: Year Cash Flows 0 −$127,800 1 47,000 2 63,800 3 51,600 4 28,100 The required return is 8.3 percent. What is the profitability index for this project?
A project has the following cash flows: Year Cash Flow 0 –$ 16,100 1 6,800 2...
A project has the following cash flows: Year Cash Flow 0 –$ 16,100 1 6,800 2 8,100 3 6,600 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) NPV $ What is the NPV at a discount rate of 11 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV $ What is the NPV...
A project has the following cash flows: Year Cash Flow 0 $ 73,000 1 –54,000 2...
A project has the following cash flows: Year Cash Flow 0 $ 73,000 1 –54,000 2 –27,600 What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Internal rate of return             % What is the NPV of this project if the required return is 5 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round...
A project has the following cash flows:    Year Cash Flow 0 $64,100 1 –30,100 2...
A project has the following cash flows:    Year Cash Flow 0 $64,100 1 –30,100 2 –48,100    a. What is the IRR for this project?    b. What is the NPV of this project, if the required return is 11.5 percent?    c. NPV at 0 percent?    d. NPV at 23 percent?
A project has the following cash flows: Year Cash Flow 0 –$ 15,600 1 6,300 2...
A project has the following cash flows: Year Cash Flow 0 –$ 15,600 1 6,300 2 7,600 3 6,100     What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)      NPV $       What is the NPV at a discount rate of 9 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)      NPV $   ...
A project has the following cash flows. What is the payback period? Year 0 1 2...
A project has the following cash flows. What is the payback period? Year 0 1 2 3 4 cash flow -$14500 $2200 $4800   $6500 $7500 A project has the following cash flows. What is the internal rate of return? Year 0 1 2 3 Cash flows -$89300 $32900 $64200 $5800 A project has the following cash flows. What is the payback period? Year 0 1 2 3 4 Cash flow -$28000 $11600 $11600 $6500 $6500 And how to solve this...
A project has the following cash flows:    Year Cash Flow 0 $ 43,500 1 –  ...
A project has the following cash flows:    Year Cash Flow 0 $ 43,500 1 –   22,500 2 –   33,500    a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project, if the required return is 12 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round...
Yellow Day has a project with the following cash flows: Year Cash Flows 0 −$27,000 1...
Yellow Day has a project with the following cash flows: Year Cash Flows 0 −$27,000 1 10,550 2 20,300 3 9,720 4 −3,600 What is the MIRR for this project using the reinvestment approach? The interest rate is 7 percent
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT