Question

In: Finance

All techniques with NPV profile Mutually exclusive projects   Projects A and​ B, of equal​ risk, are...

All techniques with NPV profile Mutually exclusive projects   Projects A and​ B, of equal​ risk, are alternatives for expanding Rosa​ Company's capacity. The​ firm's cost of capital is 16​%. The cash flows for each project are shown in the following​ table:

Initial investment   $130,000   $100,000
Year   Cash inflows  
1   $30,000   $30,000
2   $35,000   $30,000
3   $40,000   $30,000
4   $45,000   $30,000
5   $50,000   $30,000

a.  Calculate each​ project's payback

period.

b.  Calculate the net present value​ (NPV) for each project.

c.  Calculate the internal rate of return​ (IRR) for each project.

d.  Indicate which project you would recommend.

Solutions

Expert Solution

No project should be chosen as NPV is negative for both.


Related Solutions

Q1. (CLO3) All techniques with NPV profile—Mutually exclusive projects Fitch Industries is in the process of...
Q1. (CLO3) All techniques with NPV profile—Mutually exclusive projects Fitch Industries is in the process of choosing the better of two equal-risk, mutually exclusive capital expenditure projects—M and N. The relevant cash flows for each project are shown in the following table. The firm’s cost of capital is 14%. Project M Project N Initial investment $28,500 $27,000 1 $10,000 $11,000 2 $10,000 $10,000 3 $10,000 9,000 4 $10,000 8,000 a. Calculate each project’s payback period. b. Calculate the net present...
Projects A and B, both of equal risk, are mutually exclusive alternatives for expanding Corporation’s capacity....
Projects A and B, both of equal risk, are mutually exclusive alternatives for expanding Corporation’s capacity. The firm’s cost of capital is 13%. The cash flows for each project are shown in the following table.                                     Project A                                              Project B                         Year 0:             ($80,000)                     Year 0:             ($80,000)                         Year 1:             $15,000                        Year 1:             $15,000                         Year 2:             $20,000                        Year 2:             $15,000                         Year 3:             $25,000                        Year 3:             $15,000                         Year 4:             $30,000                        Year 4:             $35,000                         Year 5:             $30,000                       ...
Projects A and B, both of equal risk, are mutually exclusive alternatives for expanding Corporation’s capacity....
Projects A and B, both of equal risk, are mutually exclusive alternatives for expanding Corporation’s capacity. The firm’s cost of capital is 13%. The cash flows for each project are shown in the following table.                                     Project A                                              Project B                         Year 0:             ($80,000)                      Year 0:             ($80,000)                         Year 1:             $15,000                        Year 1:             $15,000                         Year 2:             $20,000                        Year 2:             $15,000                         Year 3:             $25,000                        Year 3:             $15,000                         Year 4:             $30,000                        Year 4:             $35,000                         Year 5:             $30,000                        Year 5:            ...
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen....
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will   agree. Projects W and X are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project W Project X 0 –$1,000 –$1,500 1...
The following two projects of equal risk are mutually exclusive alternatives for expanding the firm’s capacity....
The following two projects of equal risk are mutually exclusive alternatives for expanding the firm’s capacity. The firm’s cost of capital is 15%. The cash flows for each project are given in the following table. Year Project A Project B 0 210,000 20,000 1 15,000 12,000 2 30,000 10,500 3 32,000 9,500 4 425,000 8,200 Required: a) Calculate each project’s payback period. Using the payback period criterion which project is preferable? b) Calculate the net present value for each project....
The following two projects of equal risk are mutually exclusive alternatives for expanding the firm’s capacity....
The following two projects of equal risk are mutually exclusive alternatives for expanding the firm’s capacity. The firm’s cost of capital is 15%. The cash flows for each project are given in the following table. PROJECT A PROJECT B Initial investment 210,000 20,000 Year Net cash inflows Net cash inflows 1 15,000 12,000 2 30,000 10,500 3 32,000 9,500 4 425,000 8,200
You have two mutually exclusive projects A and B and have constructed the NPV profiles for...
You have two mutually exclusive projects A and B and have constructed the NPV profiles for these projects. You find that the IRR of A is greater than the IRR of B but at an 8% cost of capital using the NPV method you would prefer project B. What is causing the NPV profile pattern that you are observing? Which project do you prefer and why? Essentially you are preferring one method over another so you need to discuss the...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? What is the NPV of project​ A? ​$ nothing ​ (Round to the nearest​ cent.) What is the NPV of project​ B? ​$ ​(Round to the nearest​ cent.) Which project would be chosen and​ why? ​(Select the best choice​.) A....
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR PROJECT A CASH FLOW PROJECT B CASH FLOW    0 −​$110,000 −​$110,000    1        30,000               0    2        30,000               0    3        30,000               0    4        30,000               0    5        30,000      220,000 ​(Click on the icon located on the​ top-right corner of the data table above in order to copy its contents into a spreadsheet.​) If the appropriate discount rate on these...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 -105,000 -105,000 1 40,000 0 2 40,000 0 3 40,000 0 4 40,000 0 5 40,000 240,000 If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? What is the NPV of project​ A? What is the NPV of project...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT