Given data is:
- Estimated amount to perform the scheduled exercise =
Gh¢5000
- Sanctioned amount by the management = Gh¢4600.
- Deficit amount is Gh¢400. This is exactly 8% of the estimated
amount.
Task is - How to perform the scheduled exercise within
Gh¢4600?
The following points will enable the maintenance department to
perform the exercise successfully. The deficit amount 8% is
bifurcated into 4 areas of activities such as Re-working cost 2%;
Rejections cost 2%; Postponements cost 2% and through simplifying
the procedures 2% can be saved. So, totally 8% can be absorbed by
adopting the following activities.
- Re-working to be avoided - In engineering industry always there
will be an opportunity of re-working. Let it be loading or
unloading, fitting or dismantling, re-inspection ...etc all these
activities comes under re-working. Re-working cost the time, labor,
supervising, brainstorming, engineering change ...etc. So,
re-working in any manner should be avoid. This will save the
maintenance department for an amount of 2%.of the estimated
cost.
- Rejections to be avoided - Rejections, damages, unpredictables
are having the room in working. If these are avoided the 2% of
estimated cost can be saved.
- Postponements to be avoided - While working, situations will
force the working team to postpone the activity for some time.
Postponements will cost the time. Time is the money. If the
postponements avoided then 2% of estimated cost can be saved.
- Review the maintenance procedures, and simplify them -
Maintenance procedure of the particular exercise to be reviewed
once again. Surely there will be a room for simplification. It will
be possible to narrow the time up to some extent. Brainstorming
along with team members will enable the team leader for
simplification of procedure for the given exercise. So that 2% of
estimated cost can be saved.
Conclusion: By practicing the above 4 points,
it will be possible to save 8%. Saving means earning. As stated
above, the deficit amount is 8% i.e. Gh¢400. So that the scheduled
activities can be carry out with Gh¢4600 successfully.