Q3 An engineer in the maintenance department after presenting a
Ghe5000 scheduled activities to management was...
Q3 An engineer in the maintenance department after presenting a
Ghe5000 scheduled activities to management was given Ghe4600 to
carry out the exercise. Explain what he can do in order to perform
the said exercise on time?
Q3 An engineer in the maintenance department after presenting a
Gh¢5000 scheduled activities to management was given Gh¢4600 to
carry out the exercise. Explain what he can do in order to perform
the said exercise on time?
Question : An alternative classification of
maintenance and development activities is as follows:
• Functional maintenance = corrective maintenance+ adaptive
maintenance+ non-functional
perfective maintenance (i.e. improving quality)+ replacement of a
system by a functional
equivalent.
• Functional development = functional perfective maintenance (i.e.
adding new features) +
development of new systems.
Could this classification provide us with a better picture of the
real maintenance effort?
Question: Discuss the impact of component reuse
on maintainability.
Can you please answer these two...
An alternative classification of maintenance and development
activities is as follows:
• Functional maintenance = corrective maintenance + adaptive
maintenance + non-functional perfective maintenance (i.e. improving
quality) + replacement of a system by a functional equivalent.
• Functional development = functional perfective maintenance
(i.e. adding new features) + development of new systems.
Could this classification provide us with a better picture of
the real maintenance effort? Explain in detail and provide an
example if possible
Please HELP and thanks in...
An engineer has a fluctuating budget for the maintenance of a
particular machine. During each of the first 5 years, $500 per year
will be budgeted. During the second 5 years, $1000 per year will be
budgeted. In addition, $2000 will be budgeted for an overhaul of
the machine at the end of the fourth year, and again at the end of
the eighth year. What unifrom annual expenditure would be
equivalent, if interest rate is 10% per year?
Evaluate the commercially available CMMS (computerized
maintenance management system) applied for maintenance management
of medical equipment in the hospital:
Advantages and limitations
Implementation challenges and
recommendations
The following activities are part of a project to be scheduled
using CPM:
ACTIVITY
IMMEDIATE PREDECESSOR
TIME (WEEKS)
A
—
7
B
A
6
C
A
2
D
C
4
E
B, D
3
F
D
4
G
E F
6
a. Draw the network (20 points)
b. What is the critical path?
c. How many weeks will it take to complete the project ?
d. Identify the early start, early finish, late start, and late
finish for each activity...
Consider the following network of a project consisting of 7
activities with a scheduled project duration of 36 weeks. Direct
cost $12,000 with 36 weeks Indirect cost of $ 150 per week and
delay damages of $ 500 per week for project duration beyond 30
weeks, and no incentive plan. the following table of time-cost
data. Suppose the project should be completed in 30 weeks, what is
the total project cost?
Activity
Predecessor.
Normal Time (weeks)
Crash Time (weeks)
Normal...
Q3:
Identify manual and automated techniques used in storage and
maintenance of health records, and differentiate between the
UHDDSOASIS, HEDIS and UACDS healthcare datasets and identify the
types of data collected