The total costs incurred in 2019 at various output levels in a factory have been measured as follows:

Output (Units)

Total Cost ($)

40

1800

70

2,400

80

2,600

100

3,000

160

4,200

When output is 200 units or more, another factory unit must be rented and fixed costs therefore increase by 50%. Variable cost per unit is forecast to rise by 20% at the start of 2020.

Required:

Using the high-low method and least squares method-

a.       Calculate the Variable cost per unit.

b.      Calculate Total Fixed Cost.

c.       Develop the cost function that links Cost to Output (2020).

d.      Calculate the estimated total costs of producing 200 units in 2020.

e.       Calculate the estimated output if total cost is $15,400 in 2020.

Solutions

Expert Solution


Related Solutions

The following table shows the total output per hour produced in a factory for various levels of employment of labor:
The following table shows the total output per hour produced in a factory for various levels of employment of labor:Number ofWorkersTotalOutput18218330441550655759861A) The firm sells each unit of output at $2, and each worker is paid a wage of $12.After how many workers, does diminishing returns start to occur?B)The firm sells each unit of output at $2, and each worker is paid a wage of $12.How many workers should the firm employ in order to maximize profit?
On March 31, 2019, Dorchester Corporation recorded the following factory overhead costs incurred:             Factory Manager Salary          &n
On March 31, 2019, Dorchester Corporation recorded the following factory overhead costs incurred:             Factory Manager Salary                  $5,500             Factory Utilities                                  2,800             Machinery Deprecation 9,000             Machinery Repairs 1,800             Factory Rent     2,000 The overhead application rate is based on direct labor hours.  The preset formula for overhead application estimated that $22,000 would be incurred, and 2,000 direct labor hours would be worked. During March, 650 hours were actually worked on Job Order 3-1 and 1,200 hours were actually worked on Job Order 3-2. Use this...
Research and Development Costs Cressman Company incurred R&D costs for various projects in 2019 as follows:...
Research and Development Costs Cressman Company incurred R&D costs for various projects in 2019 as follows: Materials used for research $ 250,000 Materials used for development 160,000 Equipment acquired that will have alternative uses in future    research projects for 4 years 2,000,000 Personnel costs of employees involved in research 600,000 Personnel costs of employees involved in development 400,000 Consulting fees paid to outsiders for research 30,000 Consulting fees paid to outsiders for development 100,000 Indirect costs reasonably allocable for research...
Nova Company’s total overhead costs at various levels of activity follow: Month Machine-Hours Total Overhead Costs...
Nova Company’s total overhead costs at various levels of activity follow: Month Machine-Hours Total Overhead Costs April 78,000 $ 214,000 May 115,500 286,000 June 96,000 238,000 July 106,000 246,640 Assume that the total overhead costs consist of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 78,000 machine-hour level of activity is as follows: Utilities (V) $ 48,640 Supervisory salaries (F) 22,600 Maintenance (M) 142,760 Total overhead costs $ 214,000 V = variable; F = fixed; M...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 49,000    $209,260        May 39,000    $182,860        June 59,000    $235,660        July 69,000    $262,060   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 58,500     Supervisory salaries (fixed) 65,000   Maintenance (mixed) 59,360   Total overhead cost $ 182,860 The...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 49,000    $191,570        May 39,000    $166,270        June 59,000    $216,870        July 69,000    $242,170   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 54,600     Supervisory salaries (fixed) 53,000   Maintenance (mixed) 58,670   Total overhead cost $ 166,270 The...
Prospero Corporation’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...
Prospero Corporation’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Costs August 8,000 $119,400 September 12,000 $142,800 October 16,000 $166,200 November 4,000 $93,120 Assume that the total overhead costs above consist of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 4,000 machine-hour level of activity is: Utilities (variable) $11,520 Supervisory salaries (fixed) 15,600 Maintenance (mixed)   66,000 Total overhead costs $93,120 Prospero Corporation’s management wants to break down the maintenance...
Noise levels at various road construction sites were measured in decibels. The mean               the noise levels...
Noise levels at various road construction sites were measured in decibels. The mean               the noise levels in a sample of 64 construction sites was 85 decibels. The               population standard deviation is 10 decibels. Find the 95% confidence interval for               the true mean noise level at road construction sites.
Classify Costs Following is a list of various costs incurred in producing replacement automobile parts. With...
Classify Costs Following is a list of various costs incurred in producing replacement automobile parts. With respect to the production and sale of these auto parts, classify each cost as either variable costs, fixed costs, or mixed costs. 1. Oil used in manufacturing equipment 2. Plastic 3. Property taxes, $165,000 per year on factory building and equipment 4. Salary of plant manager 5. Cost of labor for hourly workers 6. Packaging 7. Factory cleaning costs, $6,000 per month 8. Metal...
Classify Costs Following is a list of various costs incurred in producing replacement automobile parts. With...
Classify Costs Following is a list of various costs incurred in producing replacement automobile parts. With respect to the production and sale of these auto parts, classify each cost as either variable costs, fixed costs, or mixed costs. 1. Oil used in manufacturing equipment 2. Plastic 3. Property taxes, $165,000 per year on factory building and equipment 4. Salary of plant manager 5. Cost of labor for hourly workers 6. Packaging 7. Factory cleaning costs, $6,000 per month 8. Metal...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT