Question

In: Finance

For a new 5-year project, your company is considering buying new machine costing $1,000,000. The expected...

For a new 5-year project, your company is considering buying new machine costing $1,000,000. The expected salvage of the machine at the end of the project is $80,000. The marketing department has forecasted that the company will be able to sell 120,000 units of new product per year at $15 per unit. The production department has indicated that the variable cost per unit will be $6. The company has forecasted that the incremental fixed costs associated with the project are $100,000. The company believes that the project will require an initial investment in operating net working capital of $150,000. Thereafter, the investment in operating net working capital will be 10% of sales.

The CCA rate is 25%, the tax rate is 40%, and the required rate of return is 15%.

1) Using net present value (NPV) calculation to determine if the company should purchase the new machine. Show all work.

2) Figure out the break-even number of units that the company must sell each year.

3) Using sensitivity analysis to determine which input (units sold, price per unit, variable cost per unit, or fixed cost) has the greatest forecasting risk. Change the input forecast by +5% and -5% to determine the impact on the NPV of the project.

4) Complete scenario analysis: a pessimistic scenario and a very pessimistic scenario. The value of the inputs for each scenario are shown in the table below. Calculate the NPV under these two additional scenarios.

Pessimistic

Very Pessimistic

Units sold

125,000

75,000

Price per unit

$13

$11

Variable cost per unit

$7

$8

Fixed Cost

$140,000

$160,000

Solutions

Expert Solution

1.

Please refer below table for income statement and cash flow:-

Year 0 1 2 3 4 5
Units Sold $1,20,000.00 $1,20,000.00 $1,20,000.00 $1,20,000.00 $1,20,000.00
Per Unit Sale Price $15.00 $15.00 $15.00 $15.00 $15.00
Sales $18,00,000.00 $18,00,000.00 $18,00,000.00 $18,00,000.00 $18,00,000.00
Unit Variable cost $6.00 $6.00 $6.00 $6.00 $6.00
Variable Cost $7,20,000.00 $7,20,000.00 $7,20,000.00 $7,20,000.00 $7,20,000.00
Fixed cost $1,00,000.00 $1,00,000.00 $1,00,000.00 $1,00,000.00 $1,00,000.00
Depriciation $2,50,000.00 $1,87,500.00 $1,40,625.00 $1,05,468.75 $79,101.56
Investment / Salvage Gain $10,00,000.00 $80,000.00
Working capital investment $1,50,000.00 $1,80,000.00 $1,80,000.00 $1,80,000.00 $1,80,000.00 $1,80,000.00
PBT -$11,50,000.00 $5,50,000.00 $6,12,500.00 $6,59,375.00 $6,94,531.25 $8,00,898.44
PAT $3,30,000.00 $3,67,500.00 $3,95,625.00 $4,16,718.75 $4,80,539.06
Cash Flow -$11,50,000.00 $5,80,000.00 $5,55,000.00 $5,36,250.00 $5,22,187.50 $5,59,640.63

In the table depriciation is calculated as below:-

Year Initial value Depriciation
1 1000000 250000
2 750000 187500
3 562500 140625
4 421875 105468.75
5 316406.3 79101.5625

Here CCA rate is 25% so each year have 25% of the asset value depriciation till the 5 year and at the 5 year we have salvage value of $80000.

We will calculate now NPV in excel as below:-

NPV (0.15, Value1 value2.....) + (-$1150000)

here value1 - $580000

Here NPV @15% will be $703403.34

2.

Now Quantity will be=

= (Fixed Cost) / (P-V)

= (100000 + 180000 ) / ( 15-6)

= 31111.11

= 31112

3.

In excel we will change rate with 20% and 10%

NPV @ 20% = $505813.41

NPV @ 10% = $942996.86

As here IRR is 39% so till 39% we will have positive NPV

4)

For pessimistic we have below:-

Year 0 1 2 3 4 5
Units Sold 125000 125000 125000 125000 125000
Per Unit Sale Price $13.00 $13.00 $13.00 $13.00 $13.00
Sales $16,25,000.00 $16,25,000.00 $16,25,000.00 $16,25,000.00 $16,25,000.00
Unit Variable cost $7.00 $7.00 $7.00 $7.00 $7.00
Variable Cost $8,75,000.00 $8,75,000.00 $8,75,000.00 $8,75,000.00 $8,75,000.00
Fixed cost $1,40,000.00 $1,40,000.00 $1,40,000.00 $1,40,000.00 $1,40,000.00
Depriciation $2,50,000.00 $1,87,500.00 $1,40,625.00 $1,05,468.75 $79,101.56
Investment / Salvage Gain $10,00,000.00 $80,000.00
Working capital investment $1,50,000.00 $1,62,500.00 $1,62,500.00 $1,62,500.00 $1,62,500.00 $1,62,500.00
PBT -$11,50,000.00 $1,97,500.00 $2,60,000.00 $3,06,875.00 $3,42,031.25 $4,48,398.44
PAT $1,18,500.00 $1,56,000.00 $1,84,125.00 $2,05,218.75 $2,69,039.06
Cash Flow -$11,50,000.00 $3,68,500.00 $3,43,500.00 $3,24,750.00 $3,10,687.50 $3,48,140.63

and NPV @ 15% will be negative

NPV = -$5577.47

For very pessimistic:-

Year 0 1 2 3 4 5
Units Sold 75000 75000 75000 75000 75000
Per Unit Sale Price $11.00 $11.00 $11.00 $11.00 $11.00
Sales $8,25,000.00 $8,25,000.00 $8,25,000.00 $8,25,000.00 $8,25,000.00
Unit Variable cost $8.00 $8.00 $8.00 $8.00 $8.00
Variable Cost $6,00,000.00 $6,00,000.00 $6,00,000.00 $6,00,000.00 $6,00,000.00
Fixed cost $1,60,000.00 $1,60,000.00 $1,60,000.00 $1,60,000.00 $1,60,000.00
Depriciation $2,50,000.00 $1,87,500.00 $1,40,625.00 $1,05,468.75 $79,101.56
Investment / Salvage Gain $10,00,000.00 $80,000.00
Working capital investment $1,50,000.00 $82,500.00 $82,500.00 $82,500.00 $82,500.00 $82,500.00
PBT -$11,50,000.00 -$2,67,500.00 -$2,05,000.00 -$1,58,125.00 -$1,22,968.75 -$16,601.56
PAT -$2,67,500.00 -$2,05,000.00 -$1.58,125.00 -$1.22.968.75 -$16,601.56
Cash Flow -$11,50,000.00 -$17,500.00 -$17,500.00 -$17,500.00 -$17,500.00 $62,500.00

NPV @ 15% Shall be -$1168888.58

Very bad NPV for very pessimistic case. for pessimistic case NPV is a little bit less than 0, however if Required rate of return is less than 15% than it could be more than 0.

Thank You!!


Related Solutions

A company is considering a 5-year project to open a new product line. A new machine...
A company is considering a 5-year project to open a new product line. A new machine with an installed cost of $90,000 would be required to manufacture their new product, which is estimated to produce sales of $80,000 in new revenues each year. The cost of goods sold to produce these sales (not including depreciation) is estimated at 55% of sales, and the tax rate at this firm is 40%. If straight-line depreciation is used to calculate annual depreciation, what...
QUESTION #5: X Company is considering buying a new machine that will cost $150,000 and that...
QUESTION #5: X Company is considering buying a new machine that will cost $150,000 and that will generate annual cash inflows of $31,470 for 6 years. What is the approximate internal rate of return?
Company A is considering the purchase of a new machine. The new machine is not expected...
Company A is considering the purchase of a new machine. The new machine is not expected to affect revenues, but pretax operating expenses will be reduced by $12,700 per year for 10 years. The old machine is now 5 years old, with 10 years of its scheduled life remaining. It was originally purchased for $61,500 and has been depreciated by the straight-line method. The old machine can be sold for $20,700 today The new machine will be depreciated by the...
CMS Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
CMS Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $545,000 is estimated to result in $97,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value of $70,000. The press also requires an initial working capital of $21,000, along with an additional $3,000 in working capital for each succeeding years of project. The tax rate is 34%, and the company's...
Starset Machine Shop is considering a 4-year project to improve its production efficiency. Buying a new...
Starset Machine Shop is considering a 4-year project to improve its production efficiency. Buying a new machine press for $460,000 is estimated to result in $190,000 in annual pretax cost savings. The press falls in the 5-year MACRS class, and it will have a salvage value at the end of the project of $74,000. The press also requires an initial investment in spare parts inventory of $35,000, along with an additional $3,850 in inventory for each succeeding year of the...
Geller Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geller Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $390,000 is estimated to result in $150,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $66,000. The press also requires an initial investment in spare parts inventory of $12,000, along with an additional $1,700 in inventory for each succeeding year of the...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $1,132,800 is estimated to result in $377,600 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $165,200. The press also requires an initial investment in spare parts inventory of $47,200, along with an additional $7,080 in inventory for each succeeding year...
Geller Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geller Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $480,000 is estimated to result in $195,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $81,000. The press also requires an initial investment in spare parts inventory of $21,000, along with an additional $2,600 in inventory for each succeeding year of the...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $950,400 is estimated to result in $316,800 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $138,600. The press also requires an initial investment in spare parts inventory of $39,600, along with an additional $5,940 in inventory for each succeeding year...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $566,400 is estimated to result in $188,800 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $82,600. The press also requires an initial investment in spare parts inventory of $23,600, along with an additional $3,540 in inventory for each succeeding year...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT