Question

In: Finance

your manager has identified two possible investment projects A and B that are expected to last...

your manager has identified two possible investment projects A and B that are expected to last for four years. The jnitial investment is $225000 for project A and $350000 for project B . the manager estimates the companys cost of capital is 9%
the expected cash flow for each project over next four years are:
year 1,2 ,3 ,4
projectA 60000, 80000,85000,75000
project B 130000,115000,100000,85000
Required
1. calculate the net present value for both projects
2. calculate the discounted payback period for both projects

Solutions

Expert Solution

Answer :

1. NPV for both projects :

Year Project A Cash Flows Project B Cash Flows PVF @9% Discounted Cash Flow of Project A Discounted Cash Flow of Project B
1 60000 130000 0.91743119266 55045.87156 119266.055
2 80000 115000 0.84167999327 67334.39946 96793.19923
3 85000 100000 0.77218348006 65635.59581 77218.34801
4 75000 85000 0.70842521107 53131.89083 60216.14294
Present Value of Cash Inflow 241147.7577 353493.7452
Less : Cash Outflow 225000 350000
NPV 16147.75766 3493.745218

2. Discounted Payback period for both project :

Year Project A Cash Flows Project B Cash Flows PVF @9% Discounted Cash Flow of Project A Cumulative Discounted Cash Flow Discounted Cash Flow of Project B Cumulative Discounted Cash Flow
1 60000 130000 0.91743119266 55045.87156 55045.87156 119266.055 119266.055
2 80000 115000 0.84167999327 67334.39946 122380.271 96793.19923 216059.2543
3 85000 100000 0.77218348006 65635.59581 188015.8668 77218.34801 293277.6023
4 75000 85000 0.70842521107 53131.89083 241147.7577 60216.14294 353493.7452

Payback Period = Complete Years + Remaining Cash flow / Cashflow for the year to be recovered

Project A Payback Period = 3 + [(225000-188015.8668) / 53131.89083]

= 3 + [36984.1332/53131.89083]

= 3 + 0.6961

= 3.6961 Years

Project B Payback Period = 3 + [(350000-293277.6023) / 60216.14294]

= 3 + [56722.3977/60216.14294]

= 3 + 0.942

= 3.942 Years


Related Solutions

Your firm has identified three potential investment projects. The projects and their cash flows are shown​...
Your firm has identified three potential investment projects. The projects and their cash flows are shown​ here:  ​( Project Cash Flow Today ​(millions) Cash Flow in One Year ​(millions) A −$6 $17 B $3 $6 C $16 −$5 Suppose all cash flows are certain and the​ risk-free interest rate is 7%. a. What is the NPV of each​ project? b. If the firm can choose only one of these​ projects, which should it​ choose? c. If the firm can choose...
Your firm has identified three potential investment projects. The projects and their cash flows are shown​...
Your firm has identified three potential investment projects. The projects and their cash flows are shown​ here: Project Cash Flow Today ​(millions) Cash Flow in One Year ​(millions) A −$7 $17 B $6 $6 C $15 −$14 Suppose all cash flows are certain and the​ risk-free interest rate is 7%. a. What is the NPV of each​ project? b. If the firm can choose only one of these​ projects, which should it​ choose? c. If the firm can choose any...
What is the EAC of two projects: project A, which costs $150 and is expected to last two years, and project B, which costs $190 and is expected to last three years?
  Q2. What is the EAC of two projects: project A, which costs $150 and is expected to last two years, and project B, which costs $190 and is expected to last three years? The cost of capital is 12%. (1 mark) Answer: Q3. A company pays annual dividends of $10.40 with no possibility of it changing in the next several years. If the firm’s stock is currently selling at $80, what is the required rate of return? (1 mark)...
Zayas has identified the following two mutually exclusive projects. Year Cash Flow (A) Cash Flow (B)...
Zayas has identified the following two mutually exclusive projects. Year Cash Flow (A) Cash Flow (B) 0 -$78,500 -$78,500 1 $43,000 $21,000 2 $29,000 $28,000 3 $23,000 $34,000 4 $21,000 $41,000 a. What is the IRR for each project and if you apply the IRR decision rule which project would you accept b. If the required return is 11% what is the NPV for each of these projects? Which project would you choose? If possible, please show formula and do...
You are considering an investment in two projects, A and B. Both projects will cost $115,000,...
You are considering an investment in two projects, A and B. Both projects will cost $115,000, and the projected cash flows are as follows: YEAR PROJECT A PROJECT B 1 $7,188    $51,750 2 $21,562    $38,812 3 $40,250    $28,750 4 $50,315    $21,563 5    $57,500 $14,375 Using Excel and show formulas a. Assuming that the WACC is 9.4%, calculate the payback period, discounted payback period, NPV, PI, IRR, and MIRR. If the projects are mutually exclusive, which...
An entrepreneur has a choice of two mutually exclusive investment projects, Project A and Project B....
An entrepreneur has a choice of two mutually exclusive investment projects, Project A and Project B. Each lasts for one time period and the firm has no other projects. Project A will result in a cash flow of £27 million in the good state and £10 million in the bad state. Each outcome is equally likely. Project B will result in a cash flow of £34 million in the good state and zero in the bad state. Each outcome is...
I ONLY NEED THE LAST PART ANSWERED NPV Your division is considering two investment projects, each...
I ONLY NEED THE LAST PART ANSWERED NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $23 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 8,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What...
Bumble’s Bees, Inc., has identified the following two mutually exclusive projects: Bumble’s Bees, Inc., has identified...
Bumble’s Bees, Inc., has identified the following two mutually exclusive projects: Bumble’s Bees, Inc., has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 -17,000 -17,000 1 8,000 2,000 2 7,000 5,000 3 5,000 9,000 4 3,000 9,500 Calculate the Internal Rate of Return (IRR) for each of the project using Trial and Error method. Apply the IRR decisionrule, which project should the company accept? If the required return is 11 percent, evaluate the...
Garage, Inc., has identified the following two projects: Year Cash flow (A) Cash flow(B) 0 -$29,000...
Garage, Inc., has identified the following two projects: Year Cash flow (A) Cash flow(B) 0 -$29,000 -$29,000 1 14,400 4,300 2 12,300 9,800 3 9,200 15,200 4 5,100 16,800 A and B are mutually exclusive projects. 1. What is the crossover rate? 2. Which project should be accepted if the required rate of return is 13 percent? 3. Which project should be accepted if the required rate of return is 16 percent? 4. Which project should be accepted if the...
Canadian Metal, Mining, and Petroleum Company are analyzing two projects for possible investment. Only one investment...
Canadian Metal, Mining, and Petroleum Company are analyzing two projects for possible investment. Only one investment will be made. The first project is an oil? drilling project in Alberta at a cost of $500 million that will produce $100 million per year in Years 5 through 10 and $200 million per year in Years 11 through 20. The second project is an expansion of an aluminum smelter in Mapletree, Quebec, and will cost $500 million and will produce $87 million...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT