In: Finance
Zayas has identified the following two mutually exclusive projects.
Year | Cash Flow (A) | Cash Flow (B) |
0 | -$78,500 | -$78,500 |
1 | $43,000 | $21,000 |
2 | $29,000 | $28,000 |
3 | $23,000 | $34,000 |
4 | $21,000 | $41,000 |
a. What is the IRR for each project and if you apply the IRR decision rule which project would you accept
b. If the required return is 11% what is the NPV for each of these projects? Which project would you choose?
If possible, please show formula and do not use excel. Thanks!
a.
Project A
Let the IRR be x.
Now , Present Value of Cash Outflows=Present Value of Cash Inflows
78,500 = 43,000/(1.0x) +29,000/ (1.0x)^2 +23,000/(1.0x)^3+ $ 21,000/(1.0x)^4
Or x= 20.705%
Hence the IRR is 20.705%
Project B
Let the IRR be y.
Now , Present Value of Cash Outflows=Present Value of Cash Inflows
78,500 =21,000/(1.0y) + 28,000/ (1.0y)^2 + 34,000 /(1.0y)^3 + 41,000 /(1.0y)^4
Or y= 18.728%
Hence the IRR is 18.728%
Since the IRR of Project A is higher than that of Project B, Project A will be accepted.
b. NPV = Present Value of Cash Inflows - Present Value of Cash Outflows
For Project A :
NPV = [ $ 43,000 * 1/(1.11) ^ 1 + $ 29,000* 1/(1.11) ^2 + $ 23,000* 1/(1.11) ^3 + $ 21,000* 1/(1.11) ^4 ] - $ 78,500
= $ 14,426.54
For Project B :
NPV = [ $ 21,000 * 1/(1.11) ^ 1 + $ 28,000* 1/(1.11) ^2 + $ 34,000* 1/(1.11) ^3 + $ 41,000* 1/(1.11) ^4 ] - $ 78,500
= $ 15,012.82
Since the NPV of Project B is higher than that of Project A, Project B will be accepted.