Question

In: Accounting

Question 1 [20 marks] You oversee the production facility of CC Compounders Ltd. CC Compounders Ltd...

Question 1 [20 marks]
You oversee the production facility of CC Compounders Ltd. CC Compounders Ltd manufactures compound which is being used in various extrusion processes. You are preparing for a management meeting. One of the points on the agenda is the explanation of the variance between actual production cost and standard production cost and to decide on action plans to address the reasons for the variance.
The following is the standard cost per 1 ton of compound:

Per Unit Price Standard Cost per ton (R)
Material:
AC1032 Powder
175kg R 3.75/kg 656.25
Labour
Mixing Department 1.5 Hours R125/hour 187.50
Overheads:
Overheads are allocated based on actual labour hours.
175.00/hour 262.50
Total standard cost per unit 1,106.25

Budgeted fixed costs amounts to R175,000 per month.
The cost clerk provided you with the following actual information for the month.

Per Unit Price Total cost
Material: AC1032 Powder 185 R3.50/kg 809,375
Labour 2 R126.50/hour 316,250
Overheads 365,219
Fixed Costs 169,000

Production for the month was 1,250 units of compound.
Required:
1. Use standard cost variance analysis to analyse and explain the manufacturing variance.
(Show all your calculations as method marks are being awarded) (18)
2. Identify the two most important areas for management to focus on. Support your suggestion with reference to the relevant variance in point 1. (2)

Solutions

Expert Solution

  • All working forms part of the answer
  • Actual data and standard data for actual 1250 units for Variances calculation:

Actual DATA for

1250

units

Quantity (AQ)

Rate (AR)

Actual Cost

[A]

[B]

[A x B]

Direct Material

231250 kgs [1250 x 185]

$              3.50

$       8,09,375.00

Direct labor

2500 hours [1250 x 2]

$            126.50

$       3,16,250.00

Variable Overhead

2500

$            146.09 [365219/2500]

$       3,65,219.00

Standard DATA for

1250

Units

Quantity (SQ)

Rate (SR)

Standard Cost

[A]

[B]

[A x B]

Direct Material

218750 kgs [1250 x 175]

$                3.75

$       8,20,312.50

Direct labor

1875 [1250 x 1.5]

$            125.00

$       2,34,375.00

Variable Overhead

1875

$            175.00

$       3,28,125.00

  • Requirement 1: Variance analysis

Material Price Variance

(

Standard Rate

-

Actual Rate

)

x

Actual Quantity

(

$                        3.75

-

$                       3.50

)

x

231250

57812.5

Variance

57812.5

Favourable-F

Material Quantity Variance

(

Standard Quantity

-

Actual Quantity

)

x

Standard Rate

(

218750

-

231250

)

x

$                           3.75

-46875

Variance

46875

Unfavourable-U

Material Spending Variance

(

Standard Cost

-

Actual Cost

)

(

$         8,20,312.50

-

$        8,09,375.00

)

10937.5

Variance

10937.5

Favourable-F

Labor Rate Variance

(

Standard Rate

-

Actual Rate

)

x

Actual Labor Hours

(

$                   125.00

-

$                  126.50

)

x

2500

-3750

Variance

3750

Unfavourable-U

Labour Efficiency Variance

(

Standard Hours

-

Actual Hours

)

x

Standard Rate

(

1875

-

2500

)

x

$                      125.00

-78125

Variance

78125

Unfavourable-U

Labor Spending Variance

(

Standard Cost

-

Actual Cost

)

(

$         2,34,375.00

-

$        3,16,250.00

)

-81875

Variance

81875

Unfavourable-U

Variable Overhead Rate Variance

(

Standard Rate

-

Actual Rate

)

x

Actual Labor Hours

(

$                   175.00

-

$                  146.09

)

x

2500

72281

Variance

72281

Favourable-F

Variable Overhead Efficiency Variance

(

Standard Hours

-

Actual Hours

)

x

Standard Rate

(

1875

-

2500

)

x

$                      175.00

-109375

Variance

109375

Unfavourable-U

Variable Overhead Spending Variance

(

Standard Cost

-

Actual Cost

)

(

$         3,28,125.00

-

$        3,65,219.00

)

-37094

Variance

37094

Unfavourable-U

Budgeted Fixed Cost = $ 175,000
Actual Fixed Cost = $ 169,000
Fixed Overhead Variance = 175000 – 169000 = $ 6000 Favourable.

Total Standard cost = $ 1,382,812.5 (Variable) + $ 175,000 (fixed) = $ 1,557,812.5
Total Actual Cost = $ 1,659,844
Total Variance = 1659844 – 1557812.5 = $ 102,031.5 Unfavourable.

This $ 102,031.5 Unfavourable variances is explained and classified into Material, Labor, Variable overhead and Fixed Overhead variance as shown above.

  • Requirement 2

Two areas where management need to focus to improve are:

---Usage of raw material: The standard consumption for one unit is 175 kg of raw material, however, 185 kgs in actual were consumed in production 1 unit. This has resulted in unfavourable material Quantity variance. Management should see that raw material is used efficiently and consumption is adhere to the standards set.

---Consumption of hours: The standard hour per unit are set as 1.5 hours, however in actual, iit took 2 hours to produce 1 unit. This has resulted in Unfavourable Labor efficiency variance as well as unfavourable variable overhead efficiency variance. The management should focus that labor force work efficiently in the production. May be the work force need training and development to improve their efficiency.


Related Solutions

You oversee the production facility of CC Compounders Ltd. CC Compounders Ltd manufactures compound which is...
You oversee the production facility of CC Compounders Ltd. CC Compounders Ltd manufactures compound which is being used in various extrusion processes. You are preparing for a management meeting. One of the points on the agenda is the explanation of the variance between actual production cost and standard production cost and to decide on action plans to address the reasons for the variance. The following is the standard cost per 1 ton of compound: Per Unit Price Standard Cost per...
SECTION B: MANAGEMENT ACCOUNTING Question 1 [20 marks] You oversee the production facility of CC Compounders...
SECTION B: MANAGEMENT ACCOUNTING Question 1 [20 marks] You oversee the production facility of CC Compounders Ltd. CC Compounders Ltd manufactures compound which is being used in various extrusion processes. You are preparing for a management meeting. One of the points on the agenda is the explanation of the variance between actual production cost and standard production cost and to decide on action plans to address the reasons for the variance. The following is the standard cost per 1 ton...
Question 1 30 marks You are the manager of Compounders Ltd. The company mixes compound for...
Question 1 30 marks You are the manager of Compounders Ltd. The company mixes compound for smaller plastic extrusion companies. Compounders Ltd has six (6) mixing machines with a maximum capacity (100%) of 250 ton per month. However, due to power cuts, the machines are currently being operated at 75% of installed capacity. One (1) ton of a compound mixture consists of two (2) raw materials: 0.7 ton of Electrolyte and 0.3 ton of Copper Wire. Assume no wastage. There...
Question 3 (20 Marks) Part A (6 marks) XYZ Windows Ltd is involved in a research...
Question 3 Part A XYZ Windows Ltd is involved in a research and development project to create a filtering window that removes the need for curtains. For the current year ended 30 June 2020 expenditure on the project is as follows: Research $235,000 Development $500,000 The window is expected to return profits of $70,000 per year for the 10 years commencing 1 July 2020. Assuming the company uses a straight-line method amortisation. This company uses a discount rate of 8...
Question 4 (20 Marks – 36 Minutes) Nov Sup. 2014 Opuwo Investment CC opened a new...
Question 4 (20 Marks – 36 Minutes) Nov Sup. 2014 Opuwo Investment CC opened a new manufacturing facility. In the first month the following changes were observed in their inventory: Opening inventory nil Produced 16 000 units Sold 12 000 units Closing inventory 4 000 units Each unit is sold for N$35. The costs incurred are as follows: Materials N$15 per unit produced Labour N$7 per unit produced Indirect manufacturing costs (fixed) N$40 000 Selling cost (fixed) N$15 200 Administration...
QUESTION 3 [20 MARKS] PCL (Pty) Ltd gave you the following expenses that were budgeted to...
QUESTION 3 [20 MARKS] PCL (Pty) Ltd gave you the following expenses that were budgeted to produce 10,000 units in their factory as shown below: Pula Materials 70 Labour 25 Variable factory overheads 20 Fixed factory overhead (P100,000) 10 Direct Variable expenses 5 Selling expenses (10% were fixed costs) 13 Distribution expenses (20% were fixed) 7 Fixed Administrative expenses (P50,000) 5 Total cost of sale per unit 155 Required: Prepare a flexible budget for the production of 8,000 units.
QUESTION #2 (20 marks) Part A (14 marks) Lunenberg Ltd, a publicly accountable enterprise, began business...
QUESTION #2 Part A Lunenberg Ltd, a publicly accountable enterprise, began business on January 1, 2015 and follows IFRS. Its pretax accounting income for the first two years was as follows: 2015 $ 80,000 2016 150,000 The following items caused the only differences between pretax accounting income and taxable income. 1. In 2015, the company collected $75,000 in rental revenue; of this amount, $25,000 was earned in 2015; the other $50,000 will be earned equally during 2016 and 2017. The...
Question 2 (20 marks) In a given period the production data and costs for a process...
Question 2 In a given period the production data and costs for a process were: Production: 2100 units fully complete. 700 units partly complete. The degree of completion of the partly complete units was: Material 80% complete Labour 60% complete Overheads 50% complete The costs for the period were: Material P24 800 Labour P16 750 Overheads P36 200 Required: (a) Calculate the total equivalent production units (b) Calculate the cost per complete unit (c) Determine the value of W-I-P
You are the manager of Compounders Ltd. The company mixes compound for smaller plastic extrusion companies....
You are the manager of Compounders Ltd. The company mixes compound for smaller plastic extrusion companies. Compounders Ltd has six (6) mixing machines with a maximum capacity (100%) of 250 ton per month. However, due to power cuts, the machines are currently being operated at 75% of installed capacity. One (1) ton of a compound mixture consists of two (2) raw materials: 0.7 ton of Electrolyte and 0.3 ton of Copper Wire. Assume no wastage. There are no opening and...
You are the manager of Compounders Ltd. The company mixes compound for smaller plastic extrusion companies....
You are the manager of Compounders Ltd. The company mixes compound for smaller plastic extrusion companies. Compounders Ltd has six (6) mixing machines with a maximum capacity (100%) of 250 ton 250 ton per machine. However, due to power cuts, the machines are currently being operated at 75% of installed capacity. One (1) ton of a compound mixture consists of two (2) raw materials: 0.7 ton of Electrolyte and 0.3 ton of Copper Wire. Assume no wastage. There are no...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT