In: Accounting
Question 1 [20 marks]
You oversee the production facility of CC Compounders Ltd. CC
Compounders Ltd manufactures compound which is being used in
various extrusion processes. You are preparing for a management
meeting. One of the points on the agenda is the explanation of the
variance between actual production cost and standard production
cost and to decide on action plans to address the reasons for the
variance.
The following is the standard cost per 1 ton of compound:
Per Unit | Price | Standard Cost per ton (R) | |
Material: AC1032 Powder |
175kg | R 3.75/kg | 656.25 |
Labour | |||
Mixing Department | 1.5 Hours | R125/hour | 187.50 |
Overheads: Overheads are allocated based on actual labour hours. |
175.00/hour | 262.50 | |
Total standard cost per unit | 1,106.25 |
Budgeted fixed costs amounts to R175,000 per month.
The cost clerk provided you with the following actual information
for the month.
Per Unit | Price | Total cost | |
Material: AC1032 Powder | 185 | R3.50/kg | 809,375 |
Labour | 2 | R126.50/hour | 316,250 |
Overheads | 365,219 | ||
Fixed Costs | 169,000 |
Production for the month was 1,250 units of compound.
Required:
1. Use standard cost variance analysis to analyse and explain the
manufacturing variance.
(Show all your calculations as method marks are being awarded)
(18)
2. Identify the two most important areas for management to focus
on. Support your suggestion with reference to the relevant variance
in point 1. (2)
Actual DATA for |
1250 |
units |
|
Quantity (AQ) |
Rate (AR) |
Actual Cost |
|
[A] |
[B] |
[A x B] |
|
Direct Material |
231250 kgs [1250 x 185] |
$ 3.50 |
$ 8,09,375.00 |
Direct labor |
2500 hours [1250 x 2] |
$ 126.50 |
$ 3,16,250.00 |
Variable Overhead |
2500 |
$ 146.09 [365219/2500] |
$ 3,65,219.00 |
Standard DATA for |
1250 |
Units |
|
Quantity (SQ) |
Rate (SR) |
Standard Cost |
|
[A] |
[B] |
[A x B] |
|
Direct Material |
218750 kgs [1250 x 175] |
$ 3.75 |
$ 8,20,312.50 |
Direct labor |
1875 [1250 x 1.5] |
$ 125.00 |
$ 2,34,375.00 |
Variable Overhead |
1875 |
$ 175.00 |
$ 3,28,125.00 |
Material Price Variance |
||||||
( |
Standard Rate |
- |
Actual Rate |
) |
x |
Actual Quantity |
( |
$ 3.75 |
- |
$ 3.50 |
) |
x |
231250 |
57812.5 |
||||||
Variance |
57812.5 |
Favourable-F |
||||
Material Quantity Variance |
||||||
( |
Standard Quantity |
- |
Actual Quantity |
) |
x |
Standard Rate |
( |
218750 |
- |
231250 |
) |
x |
$ 3.75 |
-46875 |
||||||
Variance |
46875 |
Unfavourable-U |
||||
Material Spending Variance |
||||||
( |
Standard Cost |
- |
Actual Cost |
) |
||
( |
$ 8,20,312.50 |
- |
$ 8,09,375.00 |
) |
||
10937.5 |
||||||
Variance |
10937.5 |
Favourable-F |
||||
Labor Rate Variance |
||||||
( |
Standard Rate |
- |
Actual Rate |
) |
x |
Actual Labor Hours |
( |
$ 125.00 |
- |
$ 126.50 |
) |
x |
2500 |
-3750 |
||||||
Variance |
3750 |
Unfavourable-U |
||||
Labour Efficiency Variance |
||||||
( |
Standard Hours |
- |
Actual Hours |
) |
x |
Standard Rate |
( |
1875 |
- |
2500 |
) |
x |
$ 125.00 |
-78125 |
||||||
Variance |
78125 |
Unfavourable-U |
||||
Labor Spending Variance |
||||||
( |
Standard Cost |
- |
Actual Cost |
) |
||
( |
$ 2,34,375.00 |
- |
$ 3,16,250.00 |
) |
||
-81875 |
||||||
Variance |
81875 |
Unfavourable-U |
||||
Variable Overhead Rate Variance |
||||||
( |
Standard Rate |
- |
Actual Rate |
) |
x |
Actual Labor Hours |
( |
$ 175.00 |
- |
$ 146.09 |
) |
x |
2500 |
72281 |
||||||
Variance |
72281 |
Favourable-F |
||||
Variable Overhead Efficiency Variance |
||||||
( |
Standard Hours |
- |
Actual Hours |
) |
x |
Standard Rate |
( |
1875 |
- |
2500 |
) |
x |
$ 175.00 |
-109375 |
||||||
Variance |
109375 |
Unfavourable-U |
||||
Variable Overhead Spending Variance |
||||||
( |
Standard Cost |
- |
Actual Cost |
) |
||
( |
$ 3,28,125.00 |
- |
$ 3,65,219.00 |
) |
||
-37094 |
||||||
Variance |
37094 |
Unfavourable-U |
Budgeted Fixed Cost = $ 175,000
Actual Fixed Cost = $ 169,000
Fixed Overhead Variance = 175000 – 169000 = $ 6000 Favourable.
Total Standard cost = $ 1,382,812.5
(Variable) + $ 175,000 (fixed) = $ 1,557,812.5
Total Actual Cost = $ 1,659,844
Total Variance = 1659844 – 1557812.5 = $ 102,031.5
Unfavourable.
This $ 102,031.5 Unfavourable variances is explained and classified into Material, Labor, Variable overhead and Fixed Overhead variance as shown above.
Two areas where management need to focus to improve are:
---Usage of raw material: The standard consumption for one unit is 175 kg of raw material, however, 185 kgs in actual were consumed in production 1 unit. This has resulted in unfavourable material Quantity variance. Management should see that raw material is used efficiently and consumption is adhere to the standards set.
---Consumption of hours: The standard hour per unit are set as 1.5 hours, however in actual, iit took 2 hours to produce 1 unit. This has resulted in Unfavourable Labor efficiency variance as well as unfavourable variable overhead efficiency variance. The management should focus that labor force work efficiently in the production. May be the work force need training and development to improve their efficiency.