In: Accounting
You need to prepare the budget forYellow tree for the quarter ending June2018. The budget must be preparedmonthly. The quarter consists of 13weeks. The forecasted sales are as
follows:
April
4 weeks
May
5 weeks
June
4 weeks
July
4 weeks
Sales Units
1,250
1,500
1,750
1,800
The company’s policy changed theinventory policy to keep closing inventoryof completed units at 25% of thefollowing month’s sales. Openinginventory on the 1st of April was 475units. The labour information is as follows:
Normal workinghours
8 hours per day
Weekend work
None, only if overtimeis required.
Number of employees
20 currently
Additional 10employees will beemployed for themonth of June
Normal time rate
R32.50 per hour
Overtime rate
30% above normaltime rate per hour
Hours per unit
3 hours
Required:
1. Calculate the production budgetfor the quarter. (3)
2. Calculate the budgeted labourhours per month. Split the hoursbetween normal time andovertime. (9)
3. Calculate the budgeted labourcost monthly. Split the costbetween normal time and overtime. (6
1.
Production Budget | ||||
April | May | June | Total | |
Sales | 1,250 | 1,500 | 1,750 | 4,500 |
Add: desired end inventory | 375 | 438 | 450 | 450 |
Less: Opening Inventory | 475 | 375 | 438 | 475 |
Production Budget | 1,150 | 1,563 | 1,763 | 4,475 |
Budgeted Labour Hours | ||||
April | May | June | Total | |
No of employees | 20 | 20 | 30 | 20 |
No of hours | 8 | 8 | 8 | 8 |
weeks | 4 | 5 | 4 | 4 |
No of days | 20 | 25 | 20 | 20 |
Normal Time | 3,200 | 4,000 | 4,800 | 12,000 |
Units to be produced | 1,150 | 1,563 | 1,763 | 4,475 |
No of units per unit | 3 | 3 | 3 | 3 |
Total no of hours required | 3,450 | 4,688 | 5,288 | 13,425 |
Overtime | 250 | 688 | 488 | 1,425 |
Budgeted Labour Cost | ||||
April | May | June | Total | |
Normal Time | 3,200 | 4,000 | 4,800 | 12,000 |
Rate per hour | 32.5 | 32.5 | 32.5 | 32.5 |
Normal Labour Cost | 104,000 | 130,000 | 156,000 | 390,000 |
Overtime | 250 | 688 | 488 | 1,425 |
Rate per hour | 42.3 | 42.3 | 42.3 | 42.3 |
Overtime Labour Cost | 10,563 | 29,047 | 20,597 | 60,206 |
Total Labour Cost | 114,563 | 159,047 | 176,597 | 450,206 |