In: Accounting
Q5 Elios Company produces two products, saws and drills. Three activities are used in their manufacture. These activities and their associated costs and bases are as follows:
Activity:
Stamping Budgeted Costs=$460,000 Activity Base=Machine Hours
Assembly Budgeted Costs=$648,000 Activity Base=Labor Hours
Setup Budgeted Costs=$160,000 Activity Base=Number of Setups
Activity Base: Saws Drills Total
Machine Hours 64,000 28,000 92,000
Labor Hours 16,000 92,000 108,000
Setups 20,000 60,000 80,000
Units Produced 16,000 32,000
(Each one is worth 5 points 25 points total)
What is the application rate for Stamping? _____________________________________
What is the application rate for Assembly? _____________________________________
What is the application rate for each Setup? ____________________________________
What is the overhead cost per unit for the Saws? $______________________________
What is the overhead cost per unit for the Drills? $______________________________
Answer a.
Stamping:
Budgeted Cost = $460,000
Expected machine-hours = 92,000
Application Rate = Budgeted Cost / Expected machine-hours
Application Rate = $460,000 / 92,000
Application Rate = $5.00 per machine-hour
Assembly:
Budgeted Cost = $648,000
Expected labor-hours = 108,000
Application Rate = Budgeted Cost / Expected labor-hours
Application Rate = $648,000 / 108,000
Application Rate = $6.00 per labor-hour
Setups:
Budgeted Cost = $160,000
Expected number of setups = 80,000
Application Rate = Budgeted Cost / Expected number of
setups
Application Rate = $160,000 / 80,000
Application Rate = $2.00 per setup
Answer b.
Saws:
Total Overhead Cost = 64,000 * $5.00 + 16,000 * $6.00 + 20,000 *
$2.00
Total Overhead Cost = $456,000
Overhead Cost per unit = $456,000 / 16,000
Overhead Cost per unit = $28.50
Drills:
Total Overhead Cost = 28,000 * $5.00 + 92,000 * $6.00 + 60,000 *
$2.00
Total Overhead Cost = $812,000
Overhead Cost per unit = $812,000 / 32,000
Overhead Cost per unit = $25.38