In: Finance
A company is considering three mutually exclusive projects with the below provided information. Which project the company should accept if its cost of capital is 10%?
Preject |
Project’s Life in years |
Initial Investment |
PV of Net Cash Flows at 10% |
X |
7 |
-17,000 |
23,000 |
Y |
6 |
-16,000 |
21,000 |
Z |
7 |
-16,000 |
21,000 |
Select one:
a. Project Z
b. Project X
c. Project Y
d. Projects X and Y
Compute the net present value of project X, using MS-excel as shown below:
The result of the above excel table is as follows:
Hence, the net present value of project X is $94,973.63.
Compute the net present value of project Z, using MS-excel as shown below:
The result of the above excel table is as follows:
Hence, the net present value of project Y is $75,460.47.
Compute the net present value of project Z, using MS-excel as shown below:
The result of the above excel table is as follows:
Hence, the net present value of project Z is $86,236.80.
The net present value of project X is highest, thus the project X should be selected.