Question

In: Finance

There are two mutually exclusive projects, where the basic information is provided below. Assume a DN...

There are two mutually exclusive projects, where the basic information is provided below. Assume a DN alternative does not exist. MARR is 10% per year. Which project do you choose and why?

Long term

Short Term (Lease)

Initial Cost

$45,000

$15,000

Major overhaul costs (every ten years)

$12,000

Not existent

Minor overhaul costs (every 5 years)

$6000

Not existent

Annual Operating cost

$2000

$1500

Useful Life

Infinity

10

Salvage value

$1,500

$2,500 (deposit return)

Solutions

Expert Solution

Answer:   * All amounts in $

Short Term (Lease) Project

MARR= 10% per Year,  Initial Cost = 15000,  Annual Opearting Cost = 1500

Salvage Value= 2500, Time = 10 yrs.

Year 0 1 2 3 4 5 6 7 8 9 10
Cashflow 15000 1500 1500 1500 1500 1500 1500 1500 1500 1500 -1000

PV of Short Term (Lease) Project is nothing but Present Value of all future Cash Flow including Initial Cost, Annual Cost and Salvage Value for 10 years.

So, PV = 15000 + 1500 [1/(1.1)^1 +1/(1.1)^2 + 1/ (1.1)^3 +.....................1/(1.1)^9] - [1000/(1.1)^10]

= 15000 + 8638.54- 385.5433

PV = 23253

Profitability Index (PI) = Total PV / Initial Investment = 23253/15000= 1.55

  Long Term Project

MARR= 10% per Year,  Initial Cost = 45000,  Annual Opearting Cost = 2000

Salvage Value= 1500, Time = 10 Infinity

Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 nth year
Cashflow 45000 2000 2000 2000 2000 8000 2000 2000 2000 2000 14000 2000 2000 2000 2000 8000 1500

PV= 45000 + [2000/(1.1)^1 + 2000/(1.1)^2+2000/(1.1)^3+2000/(1.1)4+(2000+6000)/(1.1)^5 + 2000/(1.1)^6 + .......+(2000+12000)/(1.1)^10+............] - 1500 at last

PV = 45000 + 2000[1/(1.1) + 1/(1.1)^2+............up to Infinite] + 6000 [1/(1.1)^5+1/(1.1)^15+1/(1.1)^25+....up to infinite] + 12000 [1/(1.1)^10+1/(1.1)^20+1/(1.1)^20+....up to infinite] -1500 at Infinite period

PV = 45000 + 20000 +6063+ 6083 + 0

PV = 77146

Profitability Index (PI) = Total PV / Initial Investment =77146/45000=1.71

Therefore, as per PI value, it is evident that Long Term Project will be more suitable as compare to Short Term (Lease) Project.


Related Solutions

A company is considering three mutually exclusive projects with the below provided information. Which project the...
A company is considering three mutually exclusive projects with the below provided information. Which project the company should accept if its cost of capital is 10%?                                                                                                                                                 Preject Project’s Life in years Initial Investment PV of Net Cash Flows at 10% X 7 -17,000 23,000 Y 6 -16,000 21,000 Z 7 -16,000 21,000 Select one: a. Project Z b. Project X c. Project Y d. Projects X and Y
Assume the projects below are mutually exclusive and the WACC is 10%. Which project should be...
Assume the projects below are mutually exclusive and the WACC is 10%. Which project should be chosen based on each of the following decision rules: NPV, IRR, MIRR, and Payback? Overall, which project should be chosen? Year Project A Project B 0 -$75,000.00 -$110,000.00 1 $46,000.00 $50,000.00 2 $24,000.00 $35,000.00 3 $10,000.00 $20,000.00 4 $10,000.00 $10,000.00 5 $6,000.00 $10,000.00 6 $4,000.00 $30,000.00
Use the following information for problems 1 to 5. Assume that the projects are mutually exclusive....
Use the following information for problems 1 to 5. Assume that the projects are mutually exclusive. Year Cash Flow (A) Cash Flow (B) 0 -$37,500 -$37,500 1 $17,300 $5,700 2 $16,200 $12,900 3 $13,800 $16,300 4 $7,600 $27,500 1.         What is the IRR for each of these projects? Using the IRR decision rule, which project should the company accept? Is this decision necessarily correct? 2.         If the required return is 11 percent, what is the NPV for each...
The estimated cashflows for two mutually exclusive projects are shown below. (A) Using a cost of...
The estimated cashflows for two mutually exclusive projects are shown below. (A) Using a cost of capital of 14%, which project should be taken based on the NPV amounts? (B) Calculate the IRR for both projects.  Based on the IRR amounts, which project should be taken? (C) Why are your answer to parts A and B not the same? (D) Using a cost of capital of 17%, which project should be taken based on the NPV amounts? (E) Create an NPV...
A firm is considering two mutually exclusive projects, A and B. The projects are different in...
A firm is considering two mutually exclusive projects, A and B. The projects are different in that they have different returns depending on general economic conditions. The firm forecasts that return on the market, and the returns on each project, along with their associated probabilities will be given by the following table. You can assume a 5% risk free rate and a 6% market risk premium. Assume the CAPM holds. Compare the expected returns to the cost of capital for...
IRRlMutually exclusive projects   Bell Manufacturing is attempting to choose the better of two mutually exclusive projects...
IRRlMutually exclusive projects   Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the​ firm'swarehouse capacity. The relevant cash flows for the projects are shown in the following​ table: Initial investment        $500,000         $320,000 Year                 1          $130,000         $130,000 2          $120,000         $120,000 3          $130,000         $105,000 4          $200,000         $90,000 5          $250,000         $40,000 The​ firm's cost of capital is 17​%. a.  Calculate the IRR for each of the projects. Assess the acceptability of each project on the basis of the IRRs. b.  Which project is​ preferred?
Consider the following cash flows of two mutually exclusive projects for Spartan Rubber Company. Assume the...
Consider the following cash flows of two mutually exclusive projects for Spartan Rubber Company. Assume the discount rate for both projects is 7 percent. Year Dry Prepreg Solvent Prepreg 0 –$ 1,890,000 –$ 900,000 1 1,119,000 470,000 2 938,000 790,000 3 769,000 428,000 a. What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback period Dry Prepreg years Solvent Prepreg years b. What is the NPV...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the discount rate for both projects is 12 percent. Year Dry Prepreg Solvent Prepreg 0 –$ 1,800,000 –$ 800,000 1 1,110,000 425,000 2 920,000 700,000 3 760,000 410,000    a. What is the payback period for both projects? (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)     b. What is the NPV for both projects? (Do not round intermediate...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the...
Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the discount rate for both projects is 8 percent. Year Dry Prepreg Solvent Prepreg 0 –$ 1,810,000 –$ 805,000 1 1,111,000 430,000 2 922,000 710,000 3 761,000 412,000    a. What is the payback period for both projects? (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)      Payback period   Dry Prepeg years   Solvent Prepeg years          b. What is...
Consider the following cash flows of two mutually exclusive projects for A–Z Motorcars. Assume the discount...
Consider the following cash flows of two mutually exclusive projects for A–Z Motorcars. Assume the discount rate for both projects is 8 percent. Year AZM Mini-SUV AZF Full-SUV 0 –$ 530,000 –$ 880,000 1 336,000 366,000 2 212,000 452,000 3 166,000 306,000 a. What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback period AZM Mini-SUV years AZF Full-SUV years b. What is the NPV for...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT