In: Accounting
Hart Labs, Inc. provides mad cow disease testing for both state
and federal governmental agricultural agencies. Because the
company’s customers are governmental agencies, prices are strictly
regulated. Therefore, Hart Labs must constantly monitor and control
its testing costs. Shown below are the standard costs for a typical
test.
Direct materials (2 test tubes @ $1.46 per tube) | $2.92 | |
Direct labor (1 hour @ $24 per hour) | 24.00 | |
Variable overhead (1 hour @ $6 per hour) | 6.00 | |
Fixed overhead (1 hour @ $10 per hour) | 10.00 | |
Total standard cost per test | $42.92 |
The lab does not maintain an inventory of test tubes. As a result,
the tubes purchased each month are used that month. Actual activity
for the month of November 2020, when 1,475 tests were conducted,
resulted in the following.
Direct materials (3,050 test tubes) | $4,270 | |
Direct labor (1,550 hours) | 35,650 | |
Variable overhead | 7,400 | |
Fixed overhead | 15,000 |
Monthly budgeted fixed overhead is $14,000. Revenues for the month
were $75,000, and selling and administrative expenses were $5,000.
The price and quantity variances for direct materials and direct
labor as follows:
Materials price variance | $183 | Favorable | ||
Materials quantity variance | $146 | Unfavorable | ||
Labor price variance | $1,550 | Favorable | ||
Labor quantity variance | $1,800 | Unfavorable |
(d)
Provide possible explanations for each unfavorable variance.
(There are 2 Unfavorables - Material quantity variance and Labor quantity variance. Explanation is provided for only those as has been asked)
Material Quantity
variance = (Actual material - Standard material) X Standard cost
per unit
=> [3050 test tubes - (1475 tests X 2 test tubes)] X $1.46
=> (3050 - 2950) X $1.46
=> $146 UNFAVORABLE
It is unfavorable because it was BUDGETED that for
every test conducted, two test tubes would be used. In the month of
November 1475 tests were conducted so 2950 test tubes should have
been used (1475 tests X 2 test tubes) but in ACTUAL 3050 test tubes
were used showing 100 additional test tubes that were not required
and couldn't be used in the following month as test tubes are
supposed to be consumed in the month of purchase. Their budgeted
price for per test tube being $1.46 brings total material quantity
variance for $146 ($1.46 X 100 additional test tubes) which is
UNFAVORABLE for the Hart Labs Inc.
Labor Quantity variance
= (Actual hours - Standard hours) X Standard rate per labor
hour
=> [1550 hours - (1475 test X 1 labor hour)] X $24
=> (1550 hours - 1475 hours) X $24
=> $1800 UNFAVORABLE
It is Unfavorable because it was BUDGETED that for
every test conducted, one Labor hour will be used and paid for. In
the month of November 1475 tests were conducted so 1475 Labor hours
should have been used (1475 tests X $1 per labor hour) but in
ACTUAL 1550 labor hours were consumed showing 75 additional labor
hours which were paid for at the standard rate of $24 per hour
which brings total Labor quantity variance to $1800 ($24 X 75
additional labor hours) which is UNFAVORABLE for the Hart Labs
Inc.
(If you have any queries, kindly let me know in comments. Thank you)