In: Finance
Again, your manager has tasked you with providing a recommendation regarding two alternative projects. You have identified the following two projects with the following characteristics:
Project A Project B
CAPEX / Initial Outlay $500,000 $300,000
Project life 5 years 6 years
Revenue (per year) $350,000 $250,000
Variable costs $90,000 $80,000
Operating expense $60,000 $40,000
Investment in Net Working Capital (Year 0) $50,000 $30,000
The company’s tax rate is 30% and uses a straight-line depreciation method. There will be no ‘salvage’ value associated with these projects at the end of their project life. The company also anticipates it will recover all of the NWC at the end of the project. The company has a required rate of return of 13% per annum.
a) The Free Cash flows (FCF) of the two projects are calculated as shown below
Free Cashflow Calculation of project A ($) | ||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Revenues | 350000 | 350000 | 350000 | 350000 | 350000 | |
Less :Variable cost | 90000 | 90000 | 90000 | 90000 | 90000 | |
Less: Operating Expense | 60000 | 60000 | 60000 | 60000 | 60000 | |
Less : Depreciation | 100000 | 100000 | 100000 | 100000 | 100000 | |
Profit before tax | 100000 | 100000 | 100000 | 100000 | 100000 | |
Less: Tax @30% | 30000 | 30000 | 30000 | 30000 | 30000 | |
Profit after tax | 70000 | 70000 | 70000 | 70000 | 70000 | |
Add Depreciation | 100000 | 100000 | 100000 | 100000 | 100000 | |
Cost of machine | 500000 | 0 | 0 | 0 | 0 | 0 |
NWC | 50000 | 50000 | ||||
FCF | -550000 | 170000 | 170000 | 170000 | 170000 | 220000 |
Free Cashflow Calculation of project B ($) | |||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 |
Revenues | 250000 | 250000 | 250000 | 250000 | 250000 | 250000 | |
Less :Variable cost | 80000 | 80000 | 80000 | 80000 | 80000 | 80000 | |
Less: Operating Expense | 40000 | 40000 | 40000 | 40000 | 40000 | 40000 | |
Less : Depreciation | 50000 | 50000 | 50000 | 50000 | 50000 | 50000 | |
Profit before tax | 80000 | 80000 | 80000 | 80000 | 80000 | 80000 | |
Less: Tax @30% | 24000 | 24000 | 24000 | 24000 | 24000 | 24000 | |
Profit after tax | 56000 | 56000 | 56000 | 56000 | 56000 | 56000 | |
Add Depreciation | 50000 | 50000 | 50000 | 50000 | 50000 | 50000 | |
Cost of machine | 300000 | 0 | 0 | 0 | 0 | 0 | 0 |
NWC | 30000 | 30000 | |||||
FCF | -330000 | 106000 | 106000 | 106000 | 106000 | 106000 | 136000 |
b) NPV of project A =-550000+170000/0.13*(1-1/1.13^5)+50000/1.13^5 = $75067.31
NPV of project B =-330000+106000/0.13*(1-1/1.13^6)+30000/1.13^6 = $108149.83
Project B is better to invest as it has a higher NPV
c) The Sensitivity analysis analyses a project by changing one variable at a time and evaluating the effect of change of that variable on the Profit, NPV etc of the project. Helps in understanding Profit/NPV are more sensitive to which variable and less sensitive to which.
Scenario analysis shows various possible future scenarios and from the possible futures , it is possible to understand the risk and the probability of loss etc
Simulation assumes that variables have a certain probabilistic distribution and accordingly, the various possible cases (much more than that in scenario) are shown in simulation, From those simulations, it is possible to understand the probabilities of making loss, value at risk etc