In: Finance
Again, your manager has tasked you with providing a recommendation regarding two alternative projects. You have identified the following two projects with the following characteristics:
Project A Project B
CAPEX / Initial Outlay $500,000 $300,000
Project life 5 years 6 years
Revenue (per year) $350,000 $250,000
Variable costs $90,000 $80,000
Operating expense $60,000 $40,000
Investment in Net Working Capital (Year 0) $50,000 $30,000
The company’s tax rate is 30% and uses a straight-line depreciation method. There will be no ‘salvage’ value associated with these projects at the end of their project life. The company also anticipates it will recover all of the NWC at the end of the project. The company has a required rate of return of 13% per annum.
PROJECT A: | 0 | 1 | 2 | 3 | 4 | 5 | |
Annual revenues | $ 3,50,000 | $ 3,50,000 | $ 3,50,000 | $ 3,50,000 | $ 3,50,000 | ||
-Variable costs | $ 90,000 | $ 90,000 | $ 90,000 | $ 90,000 | $ 90,000 | ||
-Operating expenses | $ 60,000 | $ 60,000 | $ 60,000 | $ 60,000 | $ 60,000 | ||
-Depreciation [500000/5] | $ 1,00,000 | $ 1,00,000 | $ 1,00,000 | $ 1,00,000 | $ 1,00,000 | ||
=NOI | $ 1,00,000 | $ 1,00,000 | $ 1,00,000 | $ 1,00,000 | $ 1,00,000 | ||
-Tax at 30% | $ 30,000 | $ 30,000 | $ 30,000 | $ 30,000 | $ 30,000 | ||
=NOPAT | $ 70,000 | $ 70,000 | $ 70,000 | $ 70,000 | $ 70,000 | ||
+Depreciation | $ 1,00,000 | $ 1,00,000 | $ 1,00,000 | $ 1,00,000 | $ 1,00,000 | ||
=OCF | $ 1,70,000 | $ 1,70,000 | $ 1,70,000 | $ 1,70,000 | $ 1,70,000 | ||
-Capital expenditure | $ 5,00,000 | ||||||
-Change in NWC | $ 50,000 | $ -50,000 | |||||
=FCF | $ -5,50,000 | $ 1,70,000 | $ 1,70,000 | $ 1,70,000 | $ 1,70,000 | $ 2,20,000 | |
PVIF at 13% | 1 | 0.88496 | 0.78315 | 0.69305 | 0.61332 | 0.54276 | |
PV at 13% | $ -5,50,000 | $ 1,50,442 | $ 1,33,135 | $ 1,17,819 | $ 1,04,264 | $ 1,19,407 | |
NPV | $ 75,067 | ||||||
PROJECT B: | 0 | 1 | 2 | 3 | 4 | 5 | 6 |
Annual revenues | $ 2,50,000 | $ 2,50,000 | $ 2,50,000 | $ 2,50,000 | $ 2,50,000 | $ 2,50,000 | |
-Variable costs | $ 80,000 | $ 80,000 | $ 80,000 | $ 80,000 | $ 80,000 | $ 80,000 | |
-Operating expenses | $ 40,000 | $ 40,000 | $ 40,000 | $ 40,000 | $ 40,000 | $ 40,000 | |
-Depreciation [300000/6] | $ 50,000 | $ 50,000 | $ 50,000 | $ 50,000 | $ 50,000 | $ 50,000 | |
=NOI | $ 80,000 | $ 80,000 | $ 80,000 | $ 80,000 | $ 80,000 | $ 80,000 | |
-Tax at 30% | $ 24,000 | $ 24,000 | $ 24,000 | $ 24,000 | $ 24,000 | $ 24,000 | |
=NOPAT | $ 56,000 | $ 56,000 | $ 56,000 | $ 56,000 | $ 56,000 | $ 56,000 | |
+Depreciation | $ 50,000 | $ 50,000 | $ 50,000 | $ 50,000 | $ 50,000 | $ 50,000 | |
=OCF | $ 1,06,000 | $ 1,06,000 | $ 1,06,000 | $ 1,06,000 | $ 1,06,000 | $ 1,06,000 | |
-Capital expenditure | $ 3,00,000 | ||||||
-Change in NWC | $ 30,000 | $ -30,000 | |||||
=FCF | $ -3,30,000 | $ 1,06,000 | $ 1,06,000 | $ 1,06,000 | $ 1,06,000 | $ 1,06,000 | $ 1,36,000 |
PVIF at 13% | 1 | 0.88496 | 0.78315 | 0.69305 | 0.61332 | 0.54276 | 0.48032 |
PV at 13% | $ -3,30,000 | $ 93,805 | $ 83,014 | $ 73,463 | $ 65,012 | $ 57,533 | $ 65,323 |
NPV | $ 1,08,150 | ||||||
RECOMMENDATION: | |||||||
Project B is recommended as it has higher NPV. | |||||||
SENSITIVITY: | |||||||
Sensitivity measures the % change in NPV of a given % change in any of the variables. The variables may be revenues, costs, initial cost, | |||||||
salvage value etc. It helps to understand the importance of each variable to the metric used [NPV] and helps to understand the risks | |||||||
involed, when the variatio is unfavorable. | |||||||
SCENARIO ANALYSIS: | |||||||
Here, some of the variables, like revenues and costs are predicted for different economic scenarios with associated probabilities and | |||||||
the expected value of NPV, the SD of NPV and the coefficient of variation etc are found out to assess the risks involved in the project. | |||||||
SIMULATION: | |||||||
Using statistical techniques a normal distribution for the cash flows are developed and the expected values, SD and coefficient of | |||||||
variation are found out to assess the risk involved. |