Question

In: Finance

Determine if Project B can be included in the capital budget, if the cost of your...

Determine if Project B can be included in the capital budget, if the cost of your initial investment is 11% and generates the following cash flows:

    Project B
0 -125
1 20
2 30
3 50
4 50
5 60
       
a. Can be selected as its IRR is 8%.
       
b. Should not be selected, as your IRR is less than the capital cost of the initial investment
       
c. Must not be selected, your MIRR is 10%.
       
d.Can be selected, because it has an NPV of $30.47
       
e. Can be selected because it has a PI of $1.18

Solutions

Expert Solution

Calculation of NPV:

NPV = -$125 + $20/1.11 + $30/1.11^2 + $50/1.11^3 + $50/1.11^4 + $60/1.11^5
NPV = $22.47

Calculation of IRR:

Let IRR be i%

NPV = -$125 + $20/(1+i) + $30/(1+i)^2 + $50/(1+i)^3 + $50/(1+i)^4 + $60/(1+i)^5
0 = -$125 + $20/(1+i) + $30/(1+i)^2 + $50/(1+i)^3 + $50/(1+i)^4 + $60/(1+i)^5

Using financial calculator, i = 16.79%

IRR = 16.79%

Calculation of MIRR:

Future value of cash inflows = $20*1.11^4 + $30*1.11^3 + $50*1.11^2 + $50*1.11 + $60
Future value of cash inflows = $248.495

MIRR = (Future value of cash inflows / Initial investment)^(1/n) - 1
MIRR = ($248.495 / $125)^(1/5) - 1
MIRR = 1.1473 - 1
MIRR = 0.1473 or 14.73%

Calculation of PI:

Present value of cash inflows = $20/1.11 + $30/1.11^2 + $50/1.11^3 + $50/1.11^4 + $60/1.11^5
Present value of cash inflows = $147.47

PI = Present value of cash inflows / Initial investment
PI = $147.47 / $125
PI = 1.18

The project can be selected because it has a PI of 1.18.


Related Solutions

prepare a capital budget for a project such as building or renovating a facility. Required: Determine...
prepare a capital budget for a project such as building or renovating a facility. Required: Determine the total cost of the project and the source of funds for the project. Did the cost of the project stay within budget? If the present value method was used, review the calculations. Do you agree with the calculations and methods used? If the present value was not used to evaluate the project, estimate the project’s net present value. Evaluate the capital budgeting procedures...
The most obvious cost in a capital budget is the actual cost of the capital expenditure...
The most obvious cost in a capital budget is the actual cost of the capital expenditure item. We must also consider other costs that will be incurred when we make the capital expenditure (purchase). These costs are important to include because they can be the difference between a successful implementation of the capital expenditure item and staying on budget. After reviewing the textbook readings, provide an example of a healthcare capital expenditure. Explain the rationale behind the purpose of a...
Project A Project B Cost of equipment required $ 155,000 $ 0 Working capital investment required...
Project A Project B Cost of equipment required $ 155,000 $ 0 Working capital investment required $ 0 $ 155,000 Annual cash inflows $ 25,000 $ 40,000 Salvage value of equipment in six years $ 8,600 $ 0 Life of the project 6 years 6 years The working capital needed for project B will be released at the end of six years for investment elsewhere. Perit Industries’ discount rate is 14%. Click here to view Exhibit 12B-1 and Exhibit 12B-2,...
What is included in a capital expenditure budget? How does a company maintain control over capital...
What is included in a capital expenditure budget? How does a company maintain control over capital expenditures?
1.Since all projects are different, how can you determine what should be included in the project...
1.Since all projects are different, how can you determine what should be included in the project concept and project plan? minimum - 150-200 words please
Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent...
Compute the payback statistic for Project B if the appropriate cost of capital is 12 percent and the maximum allowable payback period is three years. (If the project never pays back, then enter a "0" (zero).) Project B Time: 0 1 2 3 4 5 Cash flow: –$11,600 $3,410 $4,300 $1,640 $0 $1,120
It is your job to determine your company’s marginal cost of capital schedule. The firm’s current...
It is your job to determine your company’s marginal cost of capital schedule. The firm’s current capital structure, which it considers optimal, consists of 30% debt, 20% preferred stock, and 50% common equity. The firm has determined that it can borrow up to $15 million in debt at a pre-tax cost of 7%, an additional $9 million at a pre-tax cost of 9%, and any additional debt funds at 11%. The firm expects to retain $25 million of its earnings;...
It is your job to determine your company’s marginal cost of capital schedule. The firm’s current...
It is your job to determine your company’s marginal cost of capital schedule. The firm’s current capital structure, which it considers optimal, consists of 30% debt, 20% preferred stock, and 50% common equity. The firm has determined that it can borrow up to $15 million in debt at a pre-tax cost of 7%, an additional $9 million at a pre-tax cost of 9%, and any additional debt funds at 11%. The firm expects to retain $25 million of its earnings;...
If your company’s weighted average cost of capital is 17% and the IRR on a project...
If your company’s weighted average cost of capital is 17% and the IRR on a project is 12%, would it be profitable to invest?
You are considering the following project. Your cost of capital is 8%. The cash flows are...
You are considering the following project. Your cost of capital is 8%. The cash flows are as follow: Year 0 1 2 3 4 -1000 300 500 300 300 What is the NPV of the project? A. 165 B. 296 C. 400 D. 1400
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT