In: Accounting
Required information
[The following
information applies to the questions displayed
below.]
In 2018, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2020. Information related to the contract is
as follows:
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,204,000 | $ | 3,192,000 | $ | 2,424,400 | |||
Estimated costs to complete as of year-end | 5,396,000 | 2,204,000 | 0 | ||||||
Billings during the year | 2,140,000 | 3,256,000 | 4,604,000 | ||||||
Cash collections during the year | 1,870,000 | 3,200,000 | 4,930,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
rev: 09_15_2017_QC_CS-99734
Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)
1) Year 2018
Cost incurred during the year = $2,204,000
Total Estimated cost to complete the contract = $5,396,000+$2,204,000
= $7,600,000
Percentage of completion in 2018 = Cost incurred in 2018/Total Estimated Cost
= $2,204,000/$7,600,000 = 0.29 or 29%
Revenue to be recognized in 2018 = Contract Price*Percentage of Completion
= $10,000,000*29% = $2,900,000
Gross Profit for 2018 = Revenue recognized - Cost incurred
= $2,900,000 - $2,204,000 = $696,000
Year 2019
Cost incurred upto 2019 = Cost incurred in 2018+Cost incurred in 2019
= $2,204,000+$3,192,000 = $5,396,000
Total Estimated cost for contract = $5,396,000+$2,204,000 = $7,600,000
Percentage of completion upto 2019 = Cost incurred upto 2019/Total Estimated Cost
= $5,396,000/$7,600,000 = 0.71 or 71%
Revenue to be recognized upto 2019 = Contract Price*Percentage of Completion
= $10,000,000*71% = $7,100,000
Revenue to be recognized in 2019 = Revenue upto 2019 - Revenue recognized in 2018
= $7,100,000 - $2,900,000 = $4,200,000
Gross Profit for 2019 = Revenue recognized for 2019 - Cost incurred in 2019
= $4,200,000 - $3,192,000 = $1,008,000
Year 2020
Cost incurred upto 2020 = Cost incurred in 2018+Cost incurred in 2019+Cost incurred in 2020
= $2,204,000+$3,192,000+$2,424,400 = $7,820,400
Total Cost for contract = $7,820,400
Percentage of completion upto 2020 = Cost incurred upto 2020/Total Cost
= $7,820,400/$7,820,400 = 1.00 or 100%
Revenue to be recognized upto 2020 = Contract Price*Percentage of Completion
= $10,000,000*100% = $10,000,000
Revenue to be recognized in 2020 = Revenue upto 2020 - Revenue recognized upto 2019
= $10,000,000 - $7,100,000 = $2,900,000
Gross Profit for 2020 = Revenue recognized for 20120- Cost incurred in 2020
= $2,900,000 - $2,424,400 = $475,600
Particulars | 2018 | 2019 | 2020 |
Revenue to be Recognized | 2,900,000 | 4,200,000 | 2,900,000 |
Gross Profit to be recognized | 696,000 | 1,008,000 | 475,600 |