Question

In: Accounting

Prepare a report showing the overhead cost of the order for hard rock drills according to the ABC system. What is the total overhead cost assigned to the order?

Ace Mining Tools Ltd. of Calgary makes specialty tools used in the mining industry. The company uses an ABC system for internal decision making. The company has four activity cost pools, as listed below:

 

Activity Cost Pool Activity Measure Activity Rate
Order size Direct labour-hours $17.60
Customer orders Customer orders $360.00
Product testing Testing hours $79.00
Selling Sales calls $750.00

 

The managing director of the company would like information concerning the cost of a recently completed order for hard-rock drills. The order required 100 direct labour-hours, 20 hours of product testing, and five sales calls.

 

Required:

Prepare a report showing the overhead cost of the order for hard rock drills according to the ABC system. What is the total overhead cost assigned to the order?

Solutions

Expert Solution

 

Activity Cost Pool (a)
Activity Rate
(b)
Activity
(a) × (b)
ABC Cost
Order size $18 per direct labour-hour $100 direct labour-hours $1,760
Customer orders 360 per customer order $1 customer order 360
Product testing $79 per product testing hour $20 product testing hours 1,580
Selling $750 per sales call 5 sales calls 3,750
Total         $7,450

 


According to these calculations, the total overhead cost of the order is $7,450.

Related Solutions

Using the ABC system, how much total manufacturing overhead cost would be assigned to Product TOSP?
Kulka Corporation manufactures two products Product F82D and Product TO5P. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products F82D and TO5P. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product TOSP?Multiple Choice $147,000$304,500 $156,000$303,000
Using the ABC data, determine the total amount of overhead cost assigned to each product.
Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Activity Measure ExpectedOverhead Cost Expected Activity Labor-related Direct labor-hours $ 311,500   44,500   DLHs Purchase orders Number of orders $ 8,840   221   orders Parts management Number of part types $ 71,280   99   part types Board etching Number of boards $ 63,700   1,820...
Using the ABC data, determine the total amount of overhead cost assigned to each product.
Rusties Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company’s five activity cost pools: Activity Cost Pool Activity Measure ExpectedOverhead Cost ExpectedActivity Labor-related Direct labor-hours $ 30,115 1,585 DLHs Purchase orders Number of orders $ 2,320 580 orders Product testing Number of tests $ 6,930 330 tests Template etching Number of templates $ 870 30 templates General factory Machine-hours $ 65,100 9,300 MHs  ...
ABC Company uses a job order cost system with overhead applied to products on the basis...
ABC Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $259,530 and total machine hours at 63,300. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job:     Job 101 Job 102 Job 103 Total Direct materials used $ 11,800...
ABC Company uses a job order cost system with overhead applied to products on the basis...
ABC Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $222,840 and total machine hours at 61,900. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job: Job 101 Job 102 Job 103 Total Direct materials used $ 10,200...
ABC Company uses a job order cost system and applies overhead to production on the basis...
ABC Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2014, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job No. 49 had been completed at a cost of $90,000 and was part of finished goods inventory. There was...
The cost accountant for River Rock Beverage Co. estimated that total factory overhead cost for the...
The cost accountant for River Rock Beverage Co. estimated that total factory overhead cost for the Blending Department for the coming fiscal year beginning February 1 would be $130,000, and total direct labor costs would be $100,000. During February, the actual direct labor cost totaled $12,500, and factory overhead cost incurred totaled $16,750. Required: a. What is the predetermined factory overhead rate based on direct labor cost? b. Journalize the entry to apply factory overhead to production for February 28....
Prepare a statement of cost showing: (a) value of materials consumed (b) total cost of production...
Prepare a statement of cost showing: (a) value of materials consumed (b) total cost of production (c) cost of goods sold and (d) the amount of profit From the following details relating to a toy manufacturing concern: Opening stock: raw materials                                25,000 Finished goods                                                          20,000 Raw materials purchased                                   2, 50,000 Wages paid to laborers 1, 00,000 Closing stock: raw materials                                   20,000 Finished goods                                                           25,000 Chargeable expenses                                                10,000 Rent, rates, and taxes (factory)                                25,000 Motive power                                                             10,000 Factory heating and lighting...
Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y and Product Z?
The Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:Activity Cost PoolActivity MeasureEstimated Overhead CostExpectedActivityMachiningMachine-hours$203,00010,000MHsMachine setupsNumber of setups$121,900230setupsProduction designNumber of products$87,0002productsGeneral factoryDirect labor-hours$379,50015,000DLHsActivity MeasureProduct YProduct ZMachining8,3001,700Number...
Using the ABC system, what percentage of the Product Design cost is assigned to Product Y and Product Z?
14-4The manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:Activity Cost PoolActivity MeasureEstimated Overhead CostExpectedActivityMachiningMachine-hours$203,00010,000MHsMachine setupsNumber of setups$121,900230setupsProduction designNumber of products$87,0002productsGeneral factoryDirect labor-hours$379,50015,000DLHsActivity MeasureProduct YProduct ZMachining8,3001,700Number of...
ADVERTISEMENT