Rusties Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the company’s five activity cost pools:
| Activity Cost Pool | Activity Measure | Expected Overhead Cost  | 
Expected Activity  | 
||
| Labor-related | Direct labor-hours | $ | 30,115 | 1,585 | DLHs | 
| Purchase orders | Number of orders | $ | 2,320 | 580 | orders | 
| Product testing | Number of tests | $ | 6,930 | 330 | tests | 
| Template etching | Number of templates | $ | 870 | 30 | templates | 
| General factory | Machine-hours | $ | 65,100 | 9,300 | MHs | 
2. The expected activity for the year was distributed among the company’s four products as follows:
| Expected Activity | ||||
| Activity Cost Pool | Product A | Product B | Product C | Product D | 
| Labor-related (DLHs) | 625 | 160 | 400 | 400 | 
| Purchase orders (orders) | 30 | 190 | 170 | 190 | 
| Product testing (tests) | 190 | 55 | 0 | 85 | 
| Template etching (templates) | 0 | 17 | 10 | 3 | 
| General factory (MHs) | 3,600 | 1,700 | 1,700 | 2,300 | 
Using the ABC data, determine the total amount of overhead cost assigned to each product.
  |