Question

In: Accounting

In early 20X1, Textron Inc. entered into an agreement with Scantech Ltd. for the construction of...

In early 20X1, Textron Inc. entered into an agreement with Scantech Ltd. for the construction of a new office building. Construction is expected to take three years to complete. The initial total estimated cost of the building was $28 million, and the price of the contract was set at $38 million. At December 31, 20X1, the total cumulative cost incurred was $18 million. Due to increasing costs of materials, the total estimated cost of the project at the end of 20X1 was $31 million. By the end of the 20X2 fiscal year, an additional $9 million of costs was incurred. At December 31, 20X2, the total estimated cost of the project remained the same as at December 31, 20X1.

What amount should Textron recognize as gross profit (the profit element) for the December 31, 20X2, fiscal year?

A) $2.0 million

B) $3.2 million

C) $4.0 million

D) $6.1 million

Solutions

Expert Solution

ANSWER
Explanation :
Calculation Textron recognize as gross profit (the profit element) for the December 31, 20X2, fiscal year
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price Total Revenue to be recognized (F) (E * D) Revenue for current period (G) Gross Profit (H) (G-A)
(E)
20X1 $                  18 $                  18 $                  31 58.06% $                  38 $                  22 $                  22 $                    4
20X2 $                    9 $                  27 $                  31 87.10% $                  38 $                  33 $                  11 $                    2
So, the Correct option is A) $2 million

Related Solutions

Ballan Ltd entered into a non-cancellable lease agreement with Manufacturer Ltd to lease construction equipment from...
Ballan Ltd entered into a non-cancellable lease agreement with Manufacturer Ltd to lease construction equipment from Manufacturer Ltd under the following terms: Lease term 9 years Useful life of leased asset 11 years Expected residual value at end of lease $6,000 Lease payment at inception (beginning) $7,000 Lease payments (at end of each year) $5,000 per annum (9 payments) Implicit interest rate for lease 11% Fair Value of Equipment $37,031 Present Value of minimum lease payments $34,685 Ballan does not...
On 31 December 20X0, Columbia Inc. (Lessee) entered into an agreement with Scotia Ltd. (the Lessor)...
On 31 December 20X0, Columbia Inc. (Lessee) entered into an agreement with Scotia Ltd. (the Lessor) to lease equipment. Columbia Inc. will make four equal payments of $100,000 at the beginning of each lease year. Columbia Ltd. anticipates that the equipment will have a residual value of $80,000 at the end of the lease, net of removal costs. Columbia Inc. has the option of (1) paying $80,000 to retain the equipment or (2) allowing Scotia Ltd. to remove it. Scotia...
On 31 December 2000, Columbia Inc. entered into an agreement with Scotia Ltd. to lease equipment...
On 31 December 2000, Columbia Inc. entered into an agreement with Scotia Ltd. to lease equipment with a useful life of 6 years. Columbia Inc. will make four equal payments of $134,000 at the beginning of each lease year. Columbia Inc. anticipates that the equipment will have a residual value of $91,200 at the end of the lease, net of removal costs. Columbia Inc. has the option of extending the lease by (1) paying $91,200 to retain the equipment or...
On 1 January 20x1, Success Co. entered into a lease agreement to lease a highly specialised...
On 1 January 20x1, Success Co. entered into a lease agreement to lease a highly specialised machinery (which had a useful life of 20 years) from Victory Leasing Co. Victory Leasing Co. had bought the new machinery for a cash consideration of $1,122,095. The terms of the lease agreement included the following: Non-cancellable lease term of 15 years, with a renewal option for another 5 years Lease rental of $100,000 per year for the first 15 years and $50,000 per...
Profit Ltd has entered into an agreement to lease a truck from C ity Ltd. The...
Profit Ltd has entered into an agreement to lease a truck from C ity Ltd. The terms of the agreement include Commencement of lease 1 January 2016 Term of lease 4 years Fair value of the truck $720,000 Annual lease payment, payable in advance $200,048 Purchase option at the end of the lease term $6,000 Implicit interest rate 8% The expected useful life of the truck to Profit Ltd is five years. To obtain the lease, Profit Ltd paid the...
SorCo. Inc. has just entered into a sale agreement with a customer. The contract is for $1,100,000. However, the payments will be made as follows: 1 August 20X1
SorCo. Inc. has just entered into a sale agreement with a customer. The contract is for $1,100,000. However, the payments will be made as follows: 1 August 20X1 on date of delivery $500,000; 1 August 20X2 $300,000 and 1 August 20X3 $300,000. SorCo has estimated that the interest rate required for this customer is 7%.Required:Prepare the journal entry required to record the sale on 1 August 20X1 and the receipt of cash on 1 August 20X2 and 20X3.
Stone Age Construction Pte Ltd entered into a construction contract to build a commercial building for Bintang Ltd for $9,200,000.
Stone Age Construction Pte Ltd entered into a construction contract to build a commercial building for Bintang Ltd for $9,200,000. Construction commenced on 1 January 2021. The following details relate to the construction project as at 31 December 2021:                                                   S'000Progress billing to-date             5,520Cash receipt to-date                  5,120Costs incurred to-date               4,032Estimated total costs                  6,400Stone Age Construction Pte Ltd accounted for the contract using the percentage-of-completion method.Required:(a) For the year ended 2021, calculate the percentage of completion to-date, revenue recognised for the year...
On 1 July 2020, Newcastle Ltd entered into an agreement on to lease a processing plant...
On 1 July 2020, Newcastle Ltd entered into an agreement on to lease a processing plant with a fair value of $569,230 to Sydney Ltd. The terms of the lease agreement were: Lease term 3 years Annual rental payment, in arrears $225,000 The total residual value of the plant at the end of lease term $50,000 Residual value guarantee by Sydney (lessee) Ltd $20,000 The economic life of this plant is four years. Annual rental payment commences on 30 June...
Q6. In July of 2016, Zeon, LLC entered into an agreement with Marz, Inc. to: ...
Q6. In July of 2016, Zeon, LLC entered into an agreement with Marz, Inc. to:  make Marz its exclusive Power Tool supplier for Zeon and its member stores for four years;  "aggressively and regularly" advertise and promote Marz's products;  dedicate on average at least 12 lineal feet of shelf space to Marz products in its member stores; and  purchase $25 million in Power Tools during the term of the agreement Given Zeon’s volume purchase commitment, Marz...
Customer Corp. entered into a five-year lease agreement with Supplier Ltd, on 1 July 2019. The...
Customer Corp. entered into a five-year lease agreement with Supplier Ltd, on 1 July 2019. The lease is for a number of spa baths. Supplier Ltd acquired the spa baths on 1 July 2019, at the fair value of $1,009,850. Customer Corp. uses the spa baths at a club. The baths are expected to have an economic life of seven years, after which time they will have no residual value. There is a bargain purchase option that Customer Corps will...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT