In: Finance
For your analysis assume that the ASC uses a 7% discount rate for projects of this risk level, and that they will initially use a five-year time horizon. This is a tax-exempt not-for-profit organization so there will not be any income tax effects to consider in the calculations.
The business after buying the equipment is expected to generate gross revenues of $100,000 each year in the first two years and is expected to be $120,000 each year in the next three years. The services will be paid for by third parties and there is a demand for this new service. Deductions from revenue are expected to average 25% of gross revenues in each of the five years. The equipment cost is $210,000 and will cost $14,988 to install. After five years the equipment will be retired and it is expected that it could be sold for $25,000.
The costs for the service include part-time staffing costs of $12,000 and supply costs of $10,000 in each of the first two years. For the last three years, salaries are expected to be $14,000 and supplies are estimated to be $12,000 in each of those last three years. The equipment is under warranty in the first year so there is no extra fee paid. A maintenance contract costing $6,000 per year will be paid in years 2 through 5.
Required:
As per the data given, the NPV is calculated as per the below table:
| 
 Years  | 
 0  | 
 1  | 
 2  | 
 3  | 
 4  | 
 5  | 
 Total  | 
| 
 Equipment Cost  | 
 -$210,000  | 
 -$210,000  | 
|||||
| 
 Equipment Installation  | 
 -$14,988  | 
 -$14,988  | 
|||||
| 
 Gross Revenues  | 
 $100,000  | 
 $100,000  | 
 $120,000  | 
 $120,000  | 
 $120,000  | 
 $560,000  | 
|
| 
 Deduction from revenue  | 
 -$25,000  | 
 -$25,000  | 
 -$30,000  | 
 -$30,000  | 
 -$30,000  | 
 -$140,000  | 
|
| 
 Sale of Equipment  | 
 $25,000  | 
 $25,000  | 
|||||
| 
 Part-time staffing costs  | 
 -$12,000  | 
 -$12,000  | 
 -$14,000  | 
 -$14,000  | 
 -$14,000  | 
 -$66,000  | 
|
| 
 Supply Costs  | 
 -$10,000  | 
 -$10,000  | 
 -$12,000  | 
 -$12,000  | 
 -$12,000  | 
 -$56,000  | 
|
| 
 Machine Maintenance Contract  | 
 -$6,000  | 
 -$6,000  | 
 -$6,000  | 
 -$6,000  | 
 -$24,000  | 
||
| 
 Net Cash flow  | 
 -$224,988  | 
 $53,000  | 
 $47,000  | 
 $58,000  | 
 $58,000  | 
 $83,000  | 
 $74,012  | 
| 
 Present value factor @ 7.00%  | 
 1.0000  | 
 0.9346  | 
 0.8734  | 
 0.8163  | 
 0.7629  | 
 0.7130  | 
|
| 
 PV of Cash flows  | 
 -$224,988  | 
 $49,533  | 
 $41,052  | 
 $47,345  | 
 $44,248  | 
 $59,178  | 
 $16,367  | 
As calculated, the NPV of future cash flows is $16,367.
IRR is the rate at which the NPV of future cash flows is zero.
By trial and error method, the IRR comes to 9.48%.
Evaluation of the project as per NPV:
As the NPV of future cash flows is positive, the project looks attractive from the financial point of view.
Evaluation of the project as per IRR:
If the required rate of return from the company is less than the IRR i.e. 9.48%, the company should go ahead with the project.
However, if the required rate of return is more than the IRR, the company should not go ahead with the project.