In: Finance
For your analysis assume that the ASC uses a 7% discount rate for projects of this risk level, and that they will initially use a five-year time horizon. This is a tax-exempt not-for-profit organization so there will not be any income tax effects to consider in the calculations.
The business after buying the equipment is expected to generate gross revenues of $100,000 each year in the first two years and is expected to be $120,000 each year in the next three years. The services will be paid for by third parties and there is a demand for this new service. Deductions from revenue are expected to average 25% of gross revenues in each of the five years. The equipment cost is $210,000 and will cost $14,988 to install. After five years the equipment will be retired and it is expected that it could be sold for $25,000.
The costs for the service include part-time staffing costs of $12,000 and supply costs of $10,000 in each of the first two years. For the last three years, salaries are expected to be $14,000 and supplies are estimated to be $12,000 in each of those last three years. The equipment is under warranty in the first year so there is no extra fee paid. A maintenance contract costing $6,000 per year will be paid in years 2 through 5.
Required:
As per the data given, the NPV is calculated as per the below table:
Years |
0 |
1 |
2 |
3 |
4 |
5 |
Total |
Equipment Cost |
-$210,000 |
-$210,000 |
|||||
Equipment Installation |
-$14,988 |
-$14,988 |
|||||
Gross Revenues |
$100,000 |
$100,000 |
$120,000 |
$120,000 |
$120,000 |
$560,000 |
|
Deduction from revenue |
-$25,000 |
-$25,000 |
-$30,000 |
-$30,000 |
-$30,000 |
-$140,000 |
|
Sale of Equipment |
$25,000 |
$25,000 |
|||||
Part-time staffing costs |
-$12,000 |
-$12,000 |
-$14,000 |
-$14,000 |
-$14,000 |
-$66,000 |
|
Supply Costs |
-$10,000 |
-$10,000 |
-$12,000 |
-$12,000 |
-$12,000 |
-$56,000 |
|
Machine Maintenance Contract |
-$6,000 |
-$6,000 |
-$6,000 |
-$6,000 |
-$24,000 |
||
Net Cash flow |
-$224,988 |
$53,000 |
$47,000 |
$58,000 |
$58,000 |
$83,000 |
$74,012 |
Present value factor @ 7.00% |
1.0000 |
0.9346 |
0.8734 |
0.8163 |
0.7629 |
0.7130 |
|
PV of Cash flows |
-$224,988 |
$49,533 |
$41,052 |
$47,345 |
$44,248 |
$59,178 |
$16,367 |
As calculated, the NPV of future cash flows is $16,367.
IRR is the rate at which the NPV of future cash flows is zero.
By trial and error method, the IRR comes to 9.48%.
Evaluation of the project as per NPV:
As the NPV of future cash flows is positive, the project looks attractive from the financial point of view.
Evaluation of the project as per IRR:
If the required rate of return from the company is less than the IRR i.e. 9.48%, the company should go ahead with the project.
However, if the required rate of return is more than the IRR, the company should not go ahead with the project.