4. Find the Discounted Payback period for the following projects.
The discount rate is 7%.
Initial Outlay 17,827
Year 1 5917
Year 2 5484
Year 3 5968
Year 4 8405
Calculation of discounted payback period: | ||||
Time | Amount | PVf@ 7% | PV | Cumulative |
- | (17,827.00) | 1.00 | (17,827.00) | (17,827.00) |
1.00 | 5,917.00 | 0.93 | 5,529.91 | (12,297.09) |
2.00 | 5,484.00 | 0.87 | 4,789.94 | (7,507.16) |
3.00 | 5,968.00 | 0.82 | 4,871.67 | (2,635.49) |
4.00 | 8,405.00 | 0.76 | 6,412.13 | 3,776.64 |
Discounted payback period= 3+2635.49/6412.13 | ||||
Discounted payback period= 3.41 years |