In: Accounting
The production supervisor of the Machining Department for Hagerstown Company agreed to the following monthly static budget for the upcoming year:
Hagerstown Company Machining Department Monthly Production Budget |
|
Wages | $310,000 |
Utilities | 15,000 |
Depreciation | 26,000 |
Total | $351,000 |
The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows:
Amount Spent | Units Produced | |||
May | $331,000 | 71,000 | ||
June | 312,000 | 64,000 | ||
July | 299,000 | 58,000 |
The Machining Department supervisor has been very pleased with this performance because actual expenditures for May–July have been significantly less than the monthly static budget of 351,000. However, the plant manager believes that the budget should not remain fixed for every month but should “flex” or adjust to the volume of work that is produced in the Machining Department. Additional budget information for the Machining Department is as follows:
Wages per hour | $20.00 |
Utility cost per direct labor hour | $1.00 |
Direct labor hours per unit | 0.20 |
Planned monthly unit production | 77,000 |
a. Prepare a flexible budget for the actual units produced for May, June, and July in the Machining Department. Assume depreciation is a fixed cost. If required, use per unit amounts carried out to two decimal places.
Hagerstown Company | |||
Machining Department Budget | |||
For the Three Months Ending July 31 | |||
May | June | July | |
Units of production | 71,000 | 64,000 | 58,000 |
Wages | $ | $ | $ |
Utilities | |||
Depreciation | |||
Total | $ | $ | $ |
Supporting calculations: | |||
Units of production | 71,000 | 64,000 | 58,000 |
Hours per unit | x | x | x |
Total hours of production | |||
Wages per hour | x $ | x $ | x $ |
Total wages | $ | $ | $ |
Total hours of production | |||
Utility costs per hour | x $ | x $ | x $ |
Total utilities | $ | $ | $ |
Feedback
For each level of production, show wages, utilities, and depreciation.
b. Compare the flexible budget with the actual expenditures for the first three months.
May | June | July | |
Total flexible budget | $ | $ | $ |
Actual cost | |||
Excess of actual cost over budget | $ | $ | $ |
Hagerstown Company | |||
Machining Department Budget | |||
For the Three Months Ending July 31 | |||
May | June | July | |
Units of production | 71,000 | 64,000 | 58,000 |
Wages | 284000 | 256000 | 232000 |
Utilities | 14200 | 12800 | 11600 |
Depreciation | 26000 | 26000 | 26000 |
Total | 324200 | 294800 | 269600 |
Supporting calculations: | |||
Units of production | 71,000 | 64,000 | 58,000 |
Hours per unit | 0.2 | 0.2 | 0.2 |
Total hours of production | 14200 | 12800 | 11600 |
Wages per hour | 20 | 20 | 20 |
Total wages | 284000 | 256000 | 232000 |
Total hours of production | 14200 | 12800 | 11600 |
Utility costs per hour | 1 | 1 | 1 |
Total utilities | 14200 | 12800 | 11600 |
January | February | March | |
Total flexible budget | 324,200 | 294,800 | 269,600 |
Actual cost | 331,000 | 312,000 | 299,000 |
Excess of actual cost over budget | 6,800 | 17,200 | 29,400 |