Question

In: Accounting

The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...

The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year:

Niland Company
Machining Department
Monthly Production Budget
Wages $515,000
Utilities 38,000
Depreciation 63,000
Total $616,000

The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows:

Amount Spent Units Produced
January $582,000 126,000
February 553,000 114,000
March 530,000 103,000

The Machining Department supervisor has been very pleased with this performance because actual expenditures for January–March have been significantly less than the monthly static budget of 616,000. However, the plant manager believes that the budget should not remain fixed for every month but should “flex” or adjust to the volume of work that is produced in the Machining Department. Additional budget information for the Machining Department is as follows:

Wages per hour $15
Utility cost per direct labor hour $1.1
Direct labor hours per unit 0.25
Planned monthly unit production 137,000

a. Prepare a flexible budget for the actual units produced for January, February, and March in the Machining Department. Assume depreciation is a fixed cost. If required, use per unit amounts carried out to two decimal places.

Niland Company
Machining Department Budget
For the Three Months Ending March 31
January February March
Units of production 126,000 114,000 103,000
$ $ $
Total $ $ $
Supporting calculations:
Units of production 126,000 114,000 103,000
Hours per unit x x x
Total hours of production
Wages per hour x $ x $ x $
Total wages $ $ $
Total hours of production
Utility costs per hour x $ x $ x $
Total utilities $ $ $

b. Compare the flexible budget with the actual expenditures for the first three months.

January February March
Total flexible budget $ $ $
Actual cost
Excess of actual cost over budget $ $ $

What does this comparison suggest?

The Machining Department has performed better than originally thought.
The department is spending more than would be expected.

Solutions

Expert Solution

a

Particulars January February March
Production      126,000.00      114,000.00      103,000.00
Variable costs:
wages:
Hours per unit                  0.25                  0.25                  0.25
Total hours              31,500              28,500              25,750
Wages per hour                      15                      15                      15
Total wages            472,500            427,500            386,250
Utility cost per hour                  1.10                  1.10                  1.10
Total utilities              34,650              31,350              28,325
Total variable costs      507,150.00      458,850.00      414,575.00
Depreciation        63,000.00        63,000.00        63,000.00
Total costs      570,150.00      521,850.00      477,575.00

b

Particulars January February March
Total flexible budget      570,150.00      521,850.00      477,575.00
Actual cost 582000 553000 530000
Excess of actual over budget        11,850.00        31,150.00        52,425.00

The department is spending more than would be expected.


Related Solutions

The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $912,000 Utilities 56,000 Depreciation 92,000 Total $1,060,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $1,000,000 93,000 February 948,000 84,000 March 908,000 76,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $310,000 Utilities 17,000 Depreciation 28,000 Total $355,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $334,000 71,000 February 316,000 64,000 March 303,000 58,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $964,000 Utilities 62,000 Depreciation 103,000 Total $1,129,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $1,065,000 104,000 February 1,011,000 94,000 March 968,000 85,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $1,001,000 Utilities 50,000 Depreciation 84,000 Total $1,135,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $1,069,000 102,000 February 1,021,000 93,000 March 974,000 84,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $576,000 Utilities 26,000 Depreciation 44,000 Total $646,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $608,000 96,000 February 583,000 88,000 March 553,000 79,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $594,000 Utilities 35,000 Depreciation 59,000 Total $688,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $648,000 99,000 February 618,000 90,000 March 589,000 81,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $271,000 Utilities 16,000 Depreciation 27,000 Total $314,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $296,000 73,000 February 284,000 67,000 March 270,000 60,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $1,125,000 Utilities 90,000 Depreciation 50,000 Total $1,265,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $1,100,000 80,000 February 1,200,000 90,000 March 1,250,000 95,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $510,000 Utilities 25,000 Depreciation 43,000 Total $578,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $545,000 85,000 February 523,000 78,000 March 496,000 70,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $629,000 Utilities 33,000 Depreciation 55,000 Total $717,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $676,000 110,000 February 644,000 100,000 March 613,000 90,000 The Machining Department supervisor has been very pleased with this...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT