Question

In: Accounting

The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...

The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year:

Niland Company
Machining Department
Monthly Production Budget

Wages

$310,000

Utilities

17,000

Depreciation

28,000

Total

$355,000

The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows:

Amount Spent

Units Produced

January

$334,000

71,000

February

316,000

64,000

March

303,000

58,000

The Machining Department supervisor has been very pleased with this performance because actual expenditures for January–March have been significantly less than the monthly static budget of 355,000. However, the plant manager believes that the budget should not remain fixed for every month but should “flex” or adjust to the volume of work that is produced in the Machining Department. Additional budget information for the Machining Department is as follows:

Wages per hour

$20

Utility cost per direct labor hour

$1.1

Direct labor hours per unit

0.2

Planned monthly unit production

77,000

a. Prepare a flexible budget for the actual units produced for January, February, and March in the Machining Department. Assume depreciation is a fixed cost. If required, use per unit amounts carried out to two decimal places.

Niland Company

Machining Department Budget

For the Three Months Ending March 31

January

February

March

Units of production

71,000

64,000

58,000

?

$

$

$

?

?

Total

$

$

$

Supporting calculations:

Units of production

71,000

64,000

58,000

Hours per unit

x

x

x

Total hours of production

Wages per hour

x $

x $

x $

Total wages

$

$

$

Total hours of production

Utility costs per hour

x $

x $

x $

Total utilities

$

$

$

b. Compare the flexible budget with the actual expenditures for the first three months.

January

February

March

Total flexible budget

$

$

$

Actual cost

Excess of actual cost over budget

$

$

$

c. What does this comparison suggest?

The Machining Department has performed better than originally thought. Yes or No

The department is spending more than would be expected. Yes or No

Solutions

Expert Solution

a)

Flexible budget for January, February and March in machining department;

Niland Company Machining department budget for the three months ending

March 31

Particulars

January

February

March

Units of production

71000

64000

58000

1Wages

$ 284000

$ 256000

$ 232000

2 Utilities

$ 15620

$ 14080

$ 12760

3 Depreciation

$ 28000

$ 28000

$ 28000

Total

$ 327620

$ 298080

$ 272760

1)

Budgeted direct labor hours per unit = 0.2 hour

Wages per hour = $ 20

Flexible budget cost of wages for each month;

= Actual production * Standard hours of wages required * Standard rate

For January = 71000 units * 0.2 hour * $20 = $ 284000

For February = 64000 units * 0.2 * 20 = $ 256000

For March= 58000 * 0.2 * 20= $ 232000

2)

Budgeted direct labor hours per unit = 0.2 hour

Budgeted utility cost per direct labor hour = $ 1.1 per hour

Flexible budget cost of utilities for each month;

= Actual production * Standard hours of wages required * Standard rate

For January = 71000 units * $0.2 per unit * $ 1.1 = $ 15620

For February = 64000 units * $ 0.2 per unit * $ 1.1 = $ 14080

For March = 58000 units * $ 0.2 per unit * $ 1.1   = $ 12760

3)

Assuming that depreciation is a fixed cost. Fixed costs are constant for a relevant range of activity. Nothing is mentioned in the question regarding the change in relevant range. So depreciation cost will be same for all levels of activity.

b)

Comparison of flexible budget with actual expenditures

Particulars

January

February

March

Total Flexible budget cost

$ 327620

$ 298080

$ 272760

Actual cost

$ 334000

$ 316000

$ 303000

Excess of actual cost over budgeted

$ 6380

$ 17920

$ 30240

c)

This comparison suggests that the machining department is spending more than would be expected. And the machining department is performed worse than originally thought. Because actual cost incurred on every month is exceeding the budgeted cost for actual production (flexible budget cost).


Related Solutions

The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $912,000 Utilities 56,000 Depreciation 92,000 Total $1,060,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $1,000,000 93,000 February 948,000 84,000 March 908,000 76,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $515,000 Utilities 38,000 Depreciation 63,000 Total $616,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $582,000 126,000 February 553,000 114,000 March 530,000 103,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $964,000 Utilities 62,000 Depreciation 103,000 Total $1,129,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $1,065,000 104,000 February 1,011,000 94,000 March 968,000 85,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $1,001,000 Utilities 50,000 Depreciation 84,000 Total $1,135,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $1,069,000 102,000 February 1,021,000 93,000 March 974,000 84,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $576,000 Utilities 26,000 Depreciation 44,000 Total $646,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $608,000 96,000 February 583,000 88,000 March 553,000 79,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $594,000 Utilities 35,000 Depreciation 59,000 Total $688,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $648,000 99,000 February 618,000 90,000 March 589,000 81,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $271,000 Utilities 16,000 Depreciation 27,000 Total $314,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $296,000 73,000 February 284,000 67,000 March 270,000 60,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $1,125,000 Utilities 90,000 Depreciation 50,000 Total $1,265,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $1,100,000 80,000 February 1,200,000 90,000 March 1,250,000 95,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $510,000 Utilities 25,000 Depreciation 43,000 Total $578,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $545,000 85,000 February 523,000 78,000 March 496,000 70,000 The Machining Department supervisor has been very pleased with this...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static...
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $629,000 Utilities 33,000 Depreciation 55,000 Total $717,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $676,000 110,000 February 644,000 100,000 March 613,000 90,000 The Machining Department supervisor has been very pleased with this...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT