In: Accounting
The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year:
Niland Company |
|
Wages |
$310,000 |
Utilities |
17,000 |
Depreciation |
28,000 |
Total |
$355,000 |
The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows:
Amount Spent |
Units Produced |
|||
January |
$334,000 |
71,000 |
||
February |
316,000 |
64,000 |
||
March |
303,000 |
58,000 |
The Machining Department supervisor has been very pleased with this performance because actual expenditures for January–March have been significantly less than the monthly static budget of 355,000. However, the plant manager believes that the budget should not remain fixed for every month but should “flex” or adjust to the volume of work that is produced in the Machining Department. Additional budget information for the Machining Department is as follows:
Wages per hour |
$20 |
Utility cost per direct labor hour |
$1.1 |
Direct labor hours per unit |
0.2 |
Planned monthly unit production |
77,000 |
a. Prepare a flexible budget for the actual units produced for January, February, and March in the Machining Department. Assume depreciation is a fixed cost. If required, use per unit amounts carried out to two decimal places.
Niland Company |
|||
Machining Department Budget |
|||
For the Three Months Ending March 31 |
|||
January |
February |
March |
|
Units of production |
71,000 |
64,000 |
58,000 |
? |
$ |
$ |
$ |
? |
|||
? |
|||
Total |
$ |
$ |
$ |
Supporting calculations: |
|||
Units of production |
71,000 |
64,000 |
58,000 |
Hours per unit |
x |
x |
x |
Total hours of production |
|||
Wages per hour |
x $ |
x $ |
x $ |
Total wages |
$ |
$ |
$ |
Total hours of production |
|||
Utility costs per hour |
x $ |
x $ |
x $ |
Total utilities |
$ |
$ |
$ |
b. Compare the flexible budget with the actual expenditures for the first three months.
January |
February |
March |
|
Total flexible budget |
$ |
$ |
$ |
Actual cost |
|||
Excess of actual cost over budget |
$ |
$ |
$ |
c. What does this comparison suggest?
The Machining Department has performed better than originally thought. Yes or No |
|
The department is spending more than would be expected. Yes or No |
a)
Flexible budget for January, February and March in machining department;
Niland Company Machining department budget for the three months ending
March 31
Particulars |
January |
February |
March |
Units of production |
71000 |
64000 |
58000 |
1Wages |
$ 284000 |
$ 256000 |
$ 232000 |
2 Utilities |
$ 15620 |
$ 14080 |
$ 12760 |
3 Depreciation |
$ 28000 |
$ 28000 |
$ 28000 |
Total |
$ 327620 |
$ 298080 |
$ 272760 |
1)
Budgeted direct labor hours per unit = 0.2 hour
Wages per hour = $ 20
Flexible budget cost of wages for each month;
= Actual production * Standard hours of wages required * Standard rate
For January = 71000 units * 0.2 hour * $20 = $ 284000
For February = 64000 units * 0.2 * 20 = $ 256000
For March= 58000 * 0.2 * 20= $ 232000
2)
Budgeted direct labor hours per unit = 0.2 hour
Budgeted utility cost per direct labor hour = $ 1.1 per hour
Flexible budget cost of utilities for each month;
= Actual production * Standard hours of wages required * Standard rate
For January = 71000 units * $0.2 per unit * $ 1.1 = $ 15620
For February = 64000 units * $ 0.2 per unit * $ 1.1 = $ 14080
For March = 58000 units * $ 0.2 per unit * $ 1.1 = $ 12760
3)
Assuming that depreciation is a fixed cost. Fixed costs are constant for a relevant range of activity. Nothing is mentioned in the question regarding the change in relevant range. So depreciation cost will be same for all levels of activity.
b)
Comparison of flexible budget with actual expenditures
Particulars |
January |
February |
March |
Total Flexible budget cost |
$ 327620 |
$ 298080 |
$ 272760 |
Actual cost |
$ 334000 |
$ 316000 |
$ 303000 |
Excess of actual cost over budgeted |
$ 6380 |
$ 17920 |
$ 30240 |
c)
This comparison suggests that the machining department is spending more than would be expected. And the machining department is performed worse than originally thought. Because actual cost incurred on every month is exceeding the budgeted cost for actual production (flexible budget cost).