Question

In: Finance

Question 2 (25 marks/Investment Decision Rules and Project Cash Flows) Consider a hypothetical economy that has...

Question 2 (25 marks/Investment Decision Rules and Project Cash Flows) Consider a hypothetical economy that has NO tax. ABC Ltd. is considering investing in a 2-year project which is expected to generate the following year-end cash flows: C1 = $110 million, C2 = $115 million. The yearly discount rate for the project is 10%. The initial cost of the project is $200 million.

(a) Compute the profit and NPV of the project.

(b) Based on the answer of part (a), should the project be accepted? Explain.

(c) ABC’s cut-off period is 2 years. Compute the PI and Payback of the project. Based on these two methods, should ABC accept the project?

(d) Write down the numerical formula for computing the IRR of this project. What is the minimum IRR value that would make this project acceptable? Explain.

(e) Given the recommendations based on the four decision rules above, which project should ABC Ltd. accept?

(f) Now suppose that of the $200m initial expenditure, $50m was used for the purchase of a machine that has an estimated economic life of four years. The machine will be fully depreciated (i.e., zero book value at the end of the machine’s economic life) on a straight-line basis and expected to have a resale value of $35m at the end of the project.

(i) Explain how this will affect the size of the terminal (end-of-project) cash flows.

(ii) How will this affect the NPV and the acceptance/rejection of the project (as compared to part (a))? Show your calculations.

Solutions

Expert Solution

a) Year0 Year1 Year2
Cashflows    (200.0)         110.0         115.0
NPV@ 10%         (5.0)<--Using NPV formula of excel
b) The project should not be accpeted as it has an Negetive NPV which means than it looses money for the investor
c) Profitability Index(PI)           1.13 <--(Sum of cashflows at C1 and C2)/Initial cost
Year0 Year1 Year2
Cashflows    (200.0)         110.0         115.0
Cumlative Cashflows         (90.0)           25.0
As the cumlative cashflows become positive somewhere inyear 2. The payback period will be somewhere between year1 and year2
Portion of year 2 in wich cash flows will be recovered=90/115
Total Payback period 1.78 <--=1+90/115
d) To calculate IRR using a formula, we would set the NPV as zero and solve for the discount rate (r), which is the IRR. Given the nature of this formula, IRR cannot be calculated analytically and we should calculate it through trial-and-error
The formula is 0=C0 +C1/(1+r)+C2/(1+r)^2
The minimum aceptable value of IRR would be that which makes the NPV equal to zero. Which means the project doesn’t make a profit either a loss
Year0 Year1 Year2
Cashflows    (200.0)         110.0         115.0
NPV           0.0
Required IRR 8.2% <--Calculated using goal seek function of excel

The above table gives the case facts along with the answers.

YOu can copy the table to excel for better visibility

Please reach out for any clarifications


Related Solutions

Question 2 (25 marks/Investment Decision Rules and Project Cash Flows) Consider a hypothetical economy that has...
Question 2 (25 marks/Investment Decision Rules and Project Cash Flows) Consider a hypothetical economy that has NO tax. ABC Ltd. is considering investing in a 2-year project which is expected to generate the following year-end cash flows: C1 = $110 million, C2 = $115 million. The yearly discount rate for the project is 10%. The initial cost of the project is $200 million. (a) Compute the profit and NPV of the project. (b) Based on the answer of part (a),...
Question 1 16 Marks Consider a project with the following cash flows: Consider a project with...
Question 1 16 Marks Consider a project with the following cash flows: Consider a project with the following cash flows: Year Cash Flow 0 R17,500 1 -80,500 2 138,425 3 -105,455 4 30,030 Required: 1.1.Fill in the following table: Cost of Capital (%) Project NPV 0 5 10 15 20 25 30 35 50 1.2.Use the values developed in part (1.1) to draw an NPV profile for this project. 1.3.What is the IRR for this project? 1.4.Describe the conditions under...
Question 2 (25 marks) (a) A project in South Korea requires an initial investment of 2...
Question 2 (a) A project in South Korea requires an initial investment of 2 billion South Korean won. The project is expected to generate net cash flows to the subsidiary of 3 billion and 4 billion won in the 2 years of operation, respectively. The project has no salvage value. The current value of the won is 1,100 won per U.S. dollar, and the value of the won is expected to remain constant over the next 2 years. (i). What...
Consider a project with free cash flows in one year of $90,000 in a weak economy...
Consider a project with free cash flows in one year of $90,000 in a weak economy or $117,000 in a strong economy, with each outcome being equally likely. The initial investment required for the project is $80,000, and the project's cost of capital is 15%. The risk-free interest rate is 5% . The firm has only this project and $80,000 cash. (Assuming perfect capital market) (For Q 1-3, please round your answer to the dollar, write as a number, e.g....
Question 1: Project Evaluation (10 marks) Part A For unconventional cash flows, there will often be...
Question 1: Project Evaluation Part A For unconventional cash flows, there will often be multiple IRRs. Under those circumstances, we cannot use IRR for evaluation purposes. i) Construct a hypothetical unconventional cash flow that yields two possible IRRs. Present your cash flows in a table and plot its NPV profile. (1.0 marks) ii) Construct a hypothetical unconventional cash flow that yields three possible IRRs. Present your cash flows in a table and plot its NPV profile. Furthermore, assess which of...
Consider a project with a net investment of $40,000 and the following net cash flows: Annual...
Consider a project with a net investment of $40,000 and the following net cash flows: Annual Cash Flow Year 1 $25,000, Year 2 $36,000, Year 3 $8,000. If the company's cost of capital is 5%, what would be the net present value of the project? (Using the financial calculator)
+Consider a Project that requires an initial investment of 2000 and generates cash flows of 200,...
+Consider a Project that requires an initial investment of 2000 and generates cash flows of 200, 600, 800 and 1200 in years 1 through 4. Use a discount rate of 10% Compute the Payback period (in years) for the project +Consider a Project that requires an initial investment of 2000 and generates cash flows of 200, 600, 800 and 1200 in years 1 through 4. Use a discount rate of 10% Compute the discounted payback period (in years) for the...
Question 2 25 Marks Kavango Ltd is considering investing in a project at a cost of...
Question 2 25 Marks Kavango Ltd is considering investing in a project at a cost of N$3 000 000. The estimated economic life of the project is 5 years. The company will use the straight-line method to depreciate the cost of the project over 5 years. The company estimates that sales will amount to 240 000 units per year at an estimated selling price of N$40 per unit. The company expects to incur fixed overheads, excluding depreciation of N$300 000...
Seaborn Co. has identified an investment project with the following cash flows.
Seaborn Co. has identified an investment project with the following cash flows. Year Cash Flow 1 $800            2 1,000            3 1,330            4 1,160            Required: (a) If the discount rate is 10 percent, what is the present value of these cash flows? (Click to select)  3,679.79  3,268.96  3,424.40  4,290.00  3,345.26 (b) What is the present value at 18 percent? (Click to select)  2,746.13  3,308.65  4,290.00  3,635.58  2,803.94 (c) What is the present value at 28 percent? (Click to select)  2,345.12  2,259.53  ...
A 25-year project has a cost of $1,500,000 and has annual cash flows of $400,000 in...
A 25-year project has a cost of $1,500,000 and has annual cash flows of $400,000 in years 1-15, and $200,000 in years 16-25. The company's required rate is 14%. Given this information, calculate the payback of the project. 2.25 years 4.25 years 2.75 years 3.75 years 3.25 years
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT