Consider a project with a net investment of $40,000 and the following net cash flows: Annual Cash Flow Year 1 $25,000, Year 2 $36,000, Year 3 $8,000.
If the company's cost of capital is 5%, what would be the net present value of the project? (Using the financial calculator)
| CALCULATION OF THE NET PRESENT VALUE OF THE PROJECT | |||
| years | Cash Flow | PVF @ 5% | Present Value |
| 0 | $ -40,000 | $ 1.0000 | $ -40,000.00 |
| 1 | $ 25,000 | $ 0.9524 | $ 23,809.52 |
| 2 | $ 36,000 | $ 0.9070 | $ 32,653.06 |
| 3 | $ 8,000 | $ 0.8638 | $ 6,910.70 |
| Total | $ 23,373.29 | ||
| Net Present Value of the Project = | $ 23,373 | ||