Question

In: Accounting

Problem 20-1A (Part Level Submission) Lott Company uses a job order cost system and applies overhead...

Problem 20-1A (Part Level Submission) Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job No. 49 had been completed at a cost of $90,000 and was part of finished goods inventory. There was a $15,000 balance in the Raw Materials Inventory account. During the month of January, Lott Company began production on Jobs 51 and 52, and completed Jobs 50 and 51. Jobs 49 and 50 were also sold on account during the month for $122,000 and $158,000, respectively. The following additional events occurred during the month. 1. Purchased additional raw materials of $90,000 on account. 2. Incurred factory labor costs of $70,000. Of this amount $16,000 related to employer payroll taxes. 3. Incurred manufacturing overhead costs as follows: indirect materials $17,000; indirect labor $20,000; depreciation expense on equipment $12,000; and various other manufacturing overhead costs on account $16,000. 4. Assigned direct materials and direct labor to jobs as follows. Job No. Direct Materials Direct Labor 50 $10,000 $5,000 51 39,000 25,000 52 30,000 20,000 Collapse question part (a) Calculate the predetermined overhead rate for 2017, assuming Lott Company estimates total manufacturing overhead costs of $840,000, direct labor costs of $700,000, and direct labor hours of 20,000 for the year. (Round answer to the nearest whole percent, e.g. 25%.) Predetermined overhead rate % SHOW LIST OF ACCOUNTS LINK TO TEXT LINK TO TEXT LINK TO TEXT LINK TO TEXT LINK TO TEXT Attempts: 0 of 3 used SAVE FOR LATER SUBMIT ANSWER Expand question part (b) The parts of this question must be completed in order. This part will be available when you complete the part above. Expand question part (c) The parts of this question must be completed in order. This part will be available when you complete the part above. Expand question part (d) The parts of this question must be completed in order. This part will be available when you complete the part above. Expand question part (e) The parts of this question must be completed in order. This part will be available when you complete the part above. Expand question part (f) The parts of this question must be completed in order. This part will be available when you complete the part above. Expand question part (g) The parts of this question must be completed in order. This part will be available when you complete the part above. Expand question part (h) The parts of this question must be completed in order. This part will be available when you complete the part above.

Solutions

Expert Solution

predetermined overhead rate
Estimated manufacturing overhead/total estimated direct labor costs
840,000/700000
120.00%
job no 50
Date Direct direct MOH
materials labor
beg. 20,000 12,000 16,000
Jan 10,000 5,000 6,000
30,000 17,000 22,000
cost of completed job
Direct materials 30,000
direct labor 17,000
MOH 22,000
total cost 69,000
job no 51
Date Direct direct MOH
materials labor
Jan 39,000 25,000 30,000
39,000 25,000 30,000
cost of completed job
Direct materials 39,000
direct labor 25,000
MOH 30000
total cost 94,000
Job 52
Date Direct direct MOH
materials labor
Jan 30,000 20,000 24,000
No Account titles & Explanations Debit Credit
1) Raw materials inventory 90,000
Accounts payable 90,000
2) Factory labor 70,000
Factory wages payable 54,000
employer payroll taxes payable 16,000
3) manufacturing overhead 65,000
raw materials inventory 17,000
Factory labor 20,000
Accumulated depreciation 12,000
Accounts payable 16,000
No Account titles & Explanations Debit Credit
1) Work in process inventory 79,000
Raw materials inventory 79,000
2) work in process inventory 50,000
Factory labor 53,000
3) Work in process inventory 60000
manufacturing overhead 60,000
Account titles & Explanations Debit Credit
finished goods inventory 163,000
work in process inventory 163,000
(job 50 +job 51 =
No Account titles & Explanations Debit Credit
Accounts receivable 280000
sales 280,000
cost of goods sold
finished goods inventory 159,000
(job 49+job 50) 159,000
finished goods inventory 94,000 Job No 51
finished goods inventory
opening 90,000 COGS 159,000
WIP 163,000
end bal 94,000
manufacturing overhead 5,000 under applied
manufacturing overhead
Actual 65,000 Applied 60,000
bal 5,000

Related Solutions

Problem 15-1A (Part Level Submission) Lott Company uses a job order cost system and applies overhead...
Problem 15-1A (Part Level Submission) Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job No. 49 had been completed at a cost of $90,000 and was part of...
Problem 20-1A Lott Company uses a job order cost system and applies overhead to production on...
Problem 20-1A Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $22,000, direct labor $13,200, and manufacturing overhead $17,600. As of January 1, Job No. 49 had been completed at a cost of $99,000 and was part of finished goods inventory....
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $22,600, direct labor $13,560, and manufacturing overhead $18,080. As of January 1, Job 49 had been completed at a cost of $101,700 and was part of finished goods inventory. There was a $16,950...
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 25,000, direct labor $ 15,000, and manufacturing overhead $ 20,000. As of January 1, Job No. 49 had been completed at a cost of $ 112,500 and was part of finished...
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 22,000, direct labor $ 13,200, and manufacturing overhead $ 17,600. As of January 1, Job No. 49 had been completed at a cost of $ 99,000 and was part of finished...
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $22,400, direct labor $13,440, and manufacturing overhead $17,920. As of January 1, Job 49 had been completed at a cost of $100,800 and was part of finished goods inventory. There was a $16,800...
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 22,400 , direct labor $ 13,440 , and manufacturing overhead $ 17,920 . As of January 1, Job No. 49 had been completed at a cost of $ 100,800 and was...
Prepare entries in a job order cost system and job cost sheets. Lott Company uses a...
Prepare entries in a job order cost system and job cost sheets. Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job 49 had been completed at a cost of...
ABC Company uses a job order cost system and applies overhead to production on the basis...
ABC Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2014, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job No. 49 had been completed at a cost of $90,000 and was part of finished goods inventory. There was...
Oriole Company uses a job order cost system and applies overhead to production on the basis...
Oriole Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $21,000, direct labor $12,600, and manufacturing overhead $16,800. As of January 1, Job 49 had been completed at a cost of $94,500 and was part of finished goods inventory. There was a $15,750...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT