Question

In: Finance

Consider the following two projects for Copper Mountain Sports. Both project are projected to produce cash...

Consider the following two projects for Copper Mountain Sports. Both project are projected to produce cash flows for 5 years at which time the equipment will have become technologically obsolete. For these projects, calculate the "cross-over rate". The cross -over rate is the discount rate where both projects would have the same NPV.

Year Snow Shoes Snowmobiles
0 -$250,000 -$250,000
1 $25,000 $150,000
2 $80,000 $160,000
3 $200,000 $75,000
4 $190,000 $50,000
5 $150000 $5000

a) 33.67%

b) These two projects do not have a cross-over rate

c) 10.55%

d) 30.52%

e) 32.30%

Solutions

Expert Solution

There are two ways to solve this question. One is to calculate the NPV at each of the given rate choices for each project. The second is to calculate the difference of CFs for both the projects and then calculate the IRR of the resulting CFs because crossover rate is where the NPV of both the projects is equal so the difference between them should be 0 and that is exactly what the IRR does, it makes the NPV of the CF stream equal 0. The CF Stream will be the difference of the CFs of each project.

Let's look at the difference of CF stream and calculate the IRR and then verify the same by putting as a discount rate for each individual project:

Step 1 calculate the difference of the CFs of the two projects

Year Snow Shoes Snowmobiles Difference
0 -250000 -250000 -250000-(-250000)=0
1 25000 150000 25000-150000=-125000
2 80000 160000 80000-160000=-80000
3 200000 75000 200000-75000=125000
4 190000 50000 190000-50000=140000
5 150000 5000 150000-5000=145000

Step 2) Calculate the IRR of the above CF stream:

IRR is the rate at which NPV = 0


IRR can be calculated using either a financial calculator or excel or through hit and trial:

Using Excel we get the IRR = 30.5232956623504 or 30.52% rounded to two decimal places

Step 3) Calculate the NPV of each of the projects using the discount rate of 30.52%

Snowshoe:

Year CF Discount Factor Discounted CF
0 $ -250,000.00 1/(1+0.305232956623504)^0= 1 1*-250000= $ -250,000.00
1 $     25,000.00 1/(1+0.305232956623504)^1= 0.766146759 0.766146759415952*25000= $     19,153.67
2 $     80,000.00 1/(1+0.305232956623504)^2= 0.586980857 0.586980856963565*80000= $     46,958.47
3 $   200,000.00 1/(1+0.305232956623504)^3= 0.449713481 0.449713481401834*200000= $     89,942.70
4 $   190,000.00 1/(1+0.305232956623504)^4= 0.344546526 0.344546526441682*190000= $     65,463.84
5 $   150,000.00 1/(1+0.305232956623504)^5= 0.263973205 0.263973204701317*150000= $     39,595.98
NPV = Sum of all Discounted CF $     11,114.65

Snowmobile:

Year CF Discount Factor Discounted CF
0 $ -250,000.00 1/(1+0.305232956623504)^0= 1 1*-250000= $ -250,000.00
1 $   150,000.00 1/(1+0.305232956623504)^1= 0.766146759 0.766146759415952*150000= $   114,922.01
2 $   160,000.00 1/(1+0.305232956623504)^2= 0.586980857 0.586980856963565*160000= $     93,916.94
3 $     75,000.00 1/(1+0.305232956623504)^3= 0.449713481 0.449713481401834*75000= $     33,728.51
4 $     50,000.00 1/(1+0.305232956623504)^4= 0.344546526 0.344546526441682*50000= $     17,227.33
5 $        5,000.00 1/(1+0.305232956623504)^5= 0.263973205 0.263973204701317*5000= $        1,319.87
NPV = Sum of all Discounted CF $     11,114.65

As the NPV of both the projects is the same, then 30.52% is definitely the crossover rate.

So the correct option is D


Related Solutions

Matterhorn Mountain Gear is evaluating two projects with the following cash flows: year project x project...
Matterhorn Mountain Gear is evaluating two projects with the following cash flows: year project x project y 0 -319,400 -299,050 1 146,100 137,300 2 163,600 154,500 3 128,700 120,250 What interest rate will make the NPV for the projects equal? a)14.22% b)18.31% c)12.64% d).26% e)18.05%
Consider the following two projects. The cost of capital for both projects is 15%. Project Year...
Consider the following two projects. The cost of capital for both projects is 15%. Project Year 0 1 2 3 4 5 Alpha -55,000 15,000 14,000 22,000 30,000 35,000 Gamma -80,000 40,000 30,000 25,000 25,000 20,000 Calculate the IRR for each project and determine which one is better. Calculate the NPV for each project and determine which one is better. Based on profitability index method, which project is better? Overall, which project should be accepted assuming they are mutually exclusive?...
Consider the following cash flows on two mutually exclusive projects for A- Z motorcars.Assuming both projects...
Consider the following cash flows on two mutually exclusive projects for A- Z motorcars.Assuming both projects require an annual return of 11 percent. year AZM Mini-Suv AFL Full-Suv 0 - 470000 - 820000 1 324000 354000 2 188000 428000 3 154000 294000 A    What is the pay back period for each projects B What is the NPV for each project C What is the IRR for each project Please note Do not do intermediate and run your answers to...
Consider project S and L, and their projected cashflows. Both projects are equally risky. (Assume cost...
Consider project S and L, and their projected cashflows. Both projects are equally risky. (Assume cost of capital is 10%) Expected after-tax cash flows Expected after-tax cash flows Year(t) Project S Project L 0(today) ($1,000) ($1,000) 1 500 100 2 400 300 3 300 400 4 100 600 Required; Find the NPV of each of the projects. Calculate the B/C ratio In each case state if we should accept the project or not and explain your answer.
Robin Hood Industries is considering two mutually exclusive projects with the following projected cash flows: Project...
Robin Hood Industries is considering two mutually exclusive projects with the following projected cash flows: Project A Project B Initial Investment -R635 000,00 -R1 300 000,00 Annual Cash flows Year 1 R120 000,00 R344 000,00 Year 2 R200 000,00 R300 000,00 Year 3 R90 000,00 R200 000,00 Year 4 R200 000,00 R200 000,00 Year 5 R120 000,00 R200 000,00 Year 6 R180 000,00 R300 000,00 Year 7 R180 000,00 R400 000,00 Year 8 R90 000,00 R550 000,00 Based on the...
Consider the following two projects: Cash flows Project A Project B C0 −$ 260 −$ 260...
Consider the following two projects: Cash flows Project A Project B C0 −$ 260 −$ 260 C1 110 138 C2 110 138 C3 110 138 C4 110 a. If the opportunity cost of capital is 10%, which of these two projects would you accept (A, B, or both)? b. Suppose that you can choose only one of these two projects. Which would you choose? The discount rate is still 10%. c. Which one would you choose if the cost of...
Consider the following two projects: Cash flows Project A Project B C0 −$ 280 −$ 280...
Consider the following two projects: Cash flows Project A Project B C0 −$ 280 −$ 280 C1 120 148 C2 120 148 C3 120 148 C4 120 a.What are the internal rates of return on the two projects? b. If the opportunity cost of capital is 11%, what is the profitability index for each project?
Consider the following cash flows on two mutually exclusive projects for the BHC Corporation . Both...
Consider the following cash flows on two mutually exclusive projects for the BHC Corporation . Both projects require an annual return of 10 percent. Year Project A Project B 0 -$425,000 -$750,000 1 $160,000 $360,000 2 $235,000 $300,000 3 $205,000 $300,000 As a financial analyst for BHC, you are asked the following questions: a. If your decision rule is to accept the project with the greater IRR, which project should you choose? b. Because you are fully aware of the...
Consider the following two mutually exclusive projects: Year Cash Flow (Project I) Cash Flow (Project II)...
Consider the following two mutually exclusive projects: Year Cash Flow (Project I) Cash Flow (Project II) 0 -$12,300 -$44,000 1 $1,800 $14,000 2 $6,000 $30,000 3 $2,000 $5,000 4 $5,000 $10,000 5 $7,000 $5,000 The required return is 10% for both projects. Assume that the internal rate of return (IRR) of Project I and Project II is 18% and 15%, respectively. a) Which project will you choose if you apply the NPV criterion? Why? b) Which project will you choose...
Q) Consider the following cash flow on two mutually exclusive projects. Year Project A (Rs) Project...
Q) Consider the following cash flow on two mutually exclusive projects. Year Project A (Rs) Project B(Rs) 0 -40000 -50000 1 20000 10000 2 15000 20000 3 15000 40000 The cash flow of project A are expressed in real terms while those of project B are expressed in nominal terms.The appropriate nominal discount rate is 15% and the inflation rate is 4%. Which project should be choosen.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT